Gi Giant M Mine R Remediation
- n
Proj
- ject
t
Water Licence Intervention – Slater Environmental Consulting
Gi Giant M Mine R Remediation on Proj oject t Water Licence - - PowerPoint PPT Presentation
Gi Giant M Mine R Remediation on Proj oject t Water Licence Intervention Slater Environmental Consulting Role o of S f Slater Environmental C Consulti ting Independent Advisor to Giant Mine Working Group (GMWG) Role in Water
Water Licence Intervention – Slater Environmental Consulting
Independent Advisor to Giant Mine Working Group (GMWG)
independent technical expertise and advice … to the GMWG…”
Role in Water Licence Process
early 2019
May 2019
that evidence examined…”
position of the GMWG, or any party on the GMWG
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 2
Information Package Giant Mine Remediation Project”
Session
Recommendations – Giant Mine Remediation Project”
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 3
Yellowknife industrial remediation standard of 340 mg/kg of arsenic
widespread across the site and beyond
will be left in place – a permanent exposure source for humans and the environment
activities
long-term management of human activities
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 4
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 5
Objectives
residents have been, and continue to be, informed of residual hazards” Versus
residents use this information to make and implement land use decisions that avoid unacceptable risks
Criteria
appropriate day-to-day action – e.g., not camping in areas with high arsenic concentrations
they are permanent?
appropriate constraints in place
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 6
administrative constraints on future land use in parts of the project area that have soil arsenic concentrations that exceed residential standards but do not include physical barriers
these constraints and monitoring of their effectiveness
CANNOT be.
authority
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 7
smaller animals at the site to be affected by arsenic and antimony.”
health of vegetation at the site
assessment assumptions
abundance and diversity of vegetation and mammals
conclusions
MMP
addressing the recommendations from the risk assessment.
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 8
project performance or unforeseen environmental (social, cultural?) conditions
Management Plan – Contingency action if water quality exceeds discharge criteria
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 9
within timeframes that allow for effective response.
management responses in response to triggers being reached or exceeded.
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 10
and where should we monitor if we want to detect and respond to changes quickly?
we need to respond?
make?
us figure out what to do?
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 11
Management Plan for Phases 1 and 2
uncertainty, e.g.:
Creek
remediated areas
components
and timing
management
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 12
Phase 2 – Closure Implementation
Phase 3 – Post-closure
Assessment – Measure 6
term projects
and contingencies
up front funding
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 13
structures
mechanisms and funding mechanisms are linked
and funding mechanisms makes sense for the post-closure GMRP
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 14
administration and funding mechanisms
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 15
further analysis and design related to pit remediation, including about materials for pit filling and the need for pit covers.
been shared, and further work is proposed
warrants further discussion
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 16
and future conditions of the terrestrial environment
land reclamation and expectations for future conditions of the terrestrial environment
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 17
conditions to inform people about risks
where risks are negligible
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 18
Require further testing
residuals for the new water treatment plant
sludge samples from the existing effluent treatment plant
conditions are not the same
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 19
for Phase 1 of the project – current operations
contains very little detail, with details to be submitted as part of Design and Construction Plans.
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 20
monitoring plans should be in place for both Baker Creek and Yellowknife Bay for all phases of the project
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 21
effluent quality criteria for sulphate and chloride
criteria for sulphate and chloride
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 22
remediation of nearshore sediments
proposed covers
closure criteria is planned
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 23 Photo: SRK Consulting
December 12, 2019 Slater Environmental Consulting - Advisor to Giant Mine Working Group 24