Tundra Mine Remediation Project
Water Licence Renewal Public Hearing
July 28, 2016
Tundra Mine Remediation Project Water Licence Renewal Public - - PowerPoint PPT Presentation
Tundra Mine Remediation Project Water Licence Renewal Public Hearing July 28, 2016 Outline 1. Tundra Mine Then and Now 2. Project Schedule 3. Phase II Finalization a. Remediation Overview b. Adaptive Management Overview 4. Phase II
July 28, 2016
2
3
4
5
6
7
8
9
successfully treated and discharged to Hambone Lake
Containment Area (TCA) (task ~80% complete).
completed).
earth cover complete
minimal future expansion anticipated
to assist with water management to minimize contact with residual tailings. Maintenance of these Site features is included under C&M.
rock
10
Photo: August 2014
11
12
Regulatory Approvals Contractor Mobilization
2025 2024 2023 2022 2021 2020 2018 2017 2016 2019
Adaptive Management Phase II Remediation
Contractor Hire Long Term Monitoring Short Term Monitoring (5 years) Regulatory Approvals for LTM
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
– Several species are potentially at risk in Hambone Lake due to pre-existing baseline conditions in the lake – None of the treated effluent discharge alternatives would have a substantively greater negative effect on current conditions in Hambone Lake
– None of the treated effluent discharge scenarios with effluent arsenic levels of 0.2 mg/L or less (2-year discharge) are predicted to pose risks to aquatic species – While phytoplankton might be affected temporarily in Powder Mag, the overall risk of adverse effects is judged to be low as the arsenic level recovers quickly and only very sensitive phytoplankton species would possibly be affected
39
Hambone Powder Mag Sandy Whale Tail
Effluent Quality
40
41
Monthly Avg (mg/L) Max Grab (mg/L) Arsenic 0.5 1.0
42
43
44
45
46
47
WL Condition Approved Plan Title(s) Approved Ver. Document Date Approval Date WATER LICENCE MV2009L8-0008 Part B, Item 09 Reclamation Plan N/A yet Part B, Item 10 Status of Environment Report N/A yet Part D, Item 01 Tundra Mine Tailings Wastewater Treatment Plant Design Report Original July 13, 2010 August 19, 2010 Part D, Item 03 Water Treatment Monitoring and Discharge Plan Original May 26, 2014 May 22, 2014 Part D, Item 09 Erosion, Sediment and Drainage Control Plan Rev 16 April 10, 2016 June 9, 2016 Part D, Item 11 Tailings Confirmatory Sampling Program Rev 2 May 11, 2011 May 27, 2011 Part D, Item 13 Hydrocarbon Contaminated Materials Treatment Plan Rev 4 April 9, 2014 June 19, 2014 Part D, Item 21 PHC Wastewater Facility Design Plan Original May 6, 2011 June 23, 2011 Part D, Item 23 PHC Wastewater Treatment Facility Operation and Maintenance Plan Original May 6, 2011 June 23, 2011 Part D, Item 26 Common Excavation Work Plan Originals May 11, 2011 May 27, 2011 Part D, Item 28 Tailings Containment Area (TCA) Cover Design Report Rev 1 June 29, 2012 January 2, 2013 Part D, Item 34 Development of Tundra Mine Construction Monitoring, Long-Term Monitoring, and Status of the Environment Programs Rev 1 January 1, 2011 June 9, 2011 Part D, Item 38 Incineration Management Plan Rev 9 May 17, 2014 October 31, 2014 Part D, Item 40 Sewage Facility Design Report Rev 6 January 31, 2014 April 24, 2014 Part D, Item 42 Sewage Disposal Facility Operation and Maintenance Plan Rev 3 January 31, 2011 April 28, 2011 Part D, Item 47 Off-site Waste Management Plan Rev 4 March 13, 2014 April 24, 2014 Part D, Item 50 Water Quality Monitoring Program Protocols and QA/QC Plan Original July 16, 2010 July 26, 2010 Part G, Item 01 Tundra Mine Remediation Spill Contingency Plan Rev 11 September 1, 2014 October 31, 2014 LAND USE PERMIT MV2009X0019 Part C, Item 36 Wildlife Management Plan for the Tundra Mine Original 21-Jul-10
48
49
50
51
52
Hydrocarbon impacted material remedial objectives and MV2009L8-0008 excavation criteria:
53
54
55
56
57