An Update on Monitoring Activities for the Giant Mine Remediation Project Working Group Meeting July 9, 2015
1 MV2007L8-0031
An Update on Monitoring Activities for the Giant Mine Remediation - - PowerPoint PPT Presentation
MV2007L8-0031 An Update on Monitoring Activities for the Giant Mine Remediation Project Working Group Meeting July 9, 2015 1 What is the purpose of the GMRP Baseline Investigations and Monitoring Activities? To contribute to the Long
1 MV2007L8-0031
2
3
4
5
6
7
8
9
10
11
12
13
14
– required in order to establish a starting point for the remediation project to which progress can be compared
15
16
1. Foreshore Tailings Area Underwater Aquatic Habitat Survey 2. Baker Creek Outlet Ecological Assessment & Comparative Hydrodynamic Modelling 3. Baker Creek Outlet Sediment & Pore Water Characterization (underway; completion in July/August 2015) 4. Metal Concentrations in Sediments and Surface Waters adjacent to N’Dilo and Dettah in Yellowknife Bay (follow-up program to be completed in 2015/2016) 5. Baseline Aquatics & Fisheries Studies in Gar Lake, Trapper Lake, Upper Shot Lake and Lower Shot Lake (for the Baker Creek north diversion evaluation in response to Measure 11 from MVEIRB on the Report of EA) 6. Upper Baker Creek Sediment & Surface Water Characterization Study 7. Site Runoff & Storm Event Surface Water Quality Sampling Program – There are also other non GMRP-funded ongoing and completed projects
17
18
19
21
22
– Potential sediment toxicity and how it relates to the aquatic environment – Arsenic mobility within the sediment and between the sediment surface and the water column, and potential effects on aquatic
– Estimate of the volume of contaminated sediments present in the BCO
23
concentrations in UBC
distribution and chemical signature of arsenic-contaminated sediments, particularly to determine whether sediments from LML and UBC are affected by natural or anthropogenic (originating from human activity) sources.
24
Upper Baker Creek (UBC) Sediment & Surface Water Characterization
25
Creek (Reach 7 to 11) sediments sampled as well as small unnamed lakes near the creek.
– Elevated concentrations are pronounced in wetland areas – Distribution of arsenic is patchy, (similar to lower Baker Creek on the Mine: Reach 0 to 6).
ranged from 16 to 746 mg/kg.
1,200 mg/kg.
samples tested--this substance is rarely observed under natural conditions, indicating that it is from a man-made source.
the samples collected. There was no correlation based on distance from Mine.
26
portion of the arsenic available for uptake by humans and aquatic organisms.
bioaccessibility percentages
downstream through Upper Baker Creek is likely from the Mine
– Roaster stack is the primary source of the man-made arsenic via atmospheric (air-borne) deposition onto the land and subsequent runoff to the creeks and lakes.
effective and successful.
27
locations adjacent to the communities of N’Dilo Dettah
– Locations commonly used by community members – 5 sites in N’Dilo and 4 site in Dettah – Communities of Dettah and Ndilo involved in study, including a training component for community members to learn sampling techniques. – Collaborative effort between Environment Canada, the GNWT Cumulative Impacts Monitoring Program (CIMP) and the Yellowknives Dene First Nation (YKDFN) – The results from a CIMP study 19 other lakes in the area were used for comparison
28
Sample Locations in Sediments and Surface Waters adjacent to N’Dilo and Dettah in Yellowknife Bay
29
mg/kg), consistent with inputs from mining, although arsenic concentrations were within the range of other Yellowknife area lakes.
measured in 19 other lakes near Yellowknife.
both locations—from the 40’s and 50’s (averaging ~700 mg/kg) with two peaks noted at depth.
– Dettah: unfiltered: 0.4-1.3 ug/L; filtered: 0.4-1.3 ug/L; total recoverable As: 0.38- 1.38 ug/L; and – Ndilo: unfiltered: 2.0-2.3 ug/L; filtered: 1.8-2.1 ug/L; total recoverable As: 2.33- 2.71 ug/L.
identified in the 2014/2015 study.
30
– Aquatic program included field collection of biota. – Fisheries program included lake habitat characterization, fish presence, and community composition.
31
Baseline Aquatic Habitat in Trapper Lake
32
– Highest in Trapper Lake (up to 0.235 mg/L, 47 times the guideline) and Gar Lake (up to 0.136 mg/L, 27 times the guideline) – Lowest in Upper Shot Creek (up to 0.012 mg/L, just over two times the guideline) and Lower Shot Creek (up to 0.009 mg/L, slightly less than two times the guideline).
Mayflies, generally considered to be pollution sensitive, were present in all four lakes.
– Fish habitat assessments in all four lakes indicated a lack of adequate habitat to support fish (ie: shallow water that may freeze to bottom on winter).
33
34
– To provide a better understanding of potential As loading into Baker Creek and Back Bay from the Giant; and – To develop a better understanding of surface water flow into these two water bodies.
35
Site Runoff & Storm Event Surface Water Quality Sampling Program
36
Site Runoff & Storm Event Surface Water Quality Sampling Program Results for 2014/2015
– Water chemistry total arsenic concentrations ranged from 0.00503 mg/L to 4.56 mg/L. – However, majority of these total arsenic concentrations consist
– Only approximately 1% by volume of As (III) was present in each
37
– New sample locations added to the north and along YK Bay to fill a few gaps noted last year. – Our initial sampling episode was completed during freshet (May 2015).
38
39
– Uplands; – Wetlands (including open water); – Riparian areas; and – Disturbed areas.
– inform project site activities.
40
41
– Eleven federally-listed species at risk have the potential to occur
– Barn swallow and horned grebe were the only species detected and confirmed to breed on site during past surveys. – Barn swallows nest on habitats that are well represented across the site and any abandoned mine structures could be used for nesting.
42
43
characterize the distribution of arsenic in shallow soils across the undeveloped areas of the Site.
– The results of this program will provide key data for a future risk assessment and inform discussion regarding end land use and project design.
across the Site with the collection of 354 soil samples in the undisturbed areas.
– All samples were analyzed for bulk chemistry (ie metals). – The results of the bulk chemistry analysis were used to select a subset of 50 samples for arsenic speciation testing (completed by Queen’s University, Heather Jamieson group).
44
Assessment of Regional Soil Quality – Sample Locations by Terrain Type
45
mining-related anthropogenic sources
– former Roaster Stack emissions, and; – dust from mine rock and tailings.
and these concentrations decreased quickly with depth.
distance from the former Roaster Stack
– secondary source from the tailings areas also confirmed.
46
– arsenic trioxide; – arsenopyrite; and – roaster oxides.
47
– High concentrations of arsenic present (shallow soil (20 – 17,000 ug/g), intermediate/deep soil: (14 – 3,400 ug/g)) – Impacted soils are shallow (typically less than 200mm in depth). – Primarily Arsenic trioxide
– Arsenic concentrations lower compared to outcrop terrain (shallow soil (<1.0 – 900 ug/g), intermediate/deep soil: (3.2 - 45ug/g)) – Consist of both arsenic trioxide and arsenopyrite.
– Concentrations of arsenic were significantly lower in the wetland areas (shallow soil (<0.01 – 3.1 ug/g), intermediate/deep soil: (<0.01 – 0.073 ug/g)) – Arsenic trioxide was not dominant in the shallow soils.
is 340 ug/g
48
49
50