proto
William Miller-UMN 21 June, 2017
Getting ready for APA # 1
21 June 2017 1
Getting ready 21 June, 2017 for APA # 1 proto 1 21 June 2017 - - PowerPoint PPT Presentation
William Miller-UMN Getting ready 21 June, 2017 for APA # 1 proto 1 21 June 2017 1-APA #1 shipping schedule Schedule is holding Shipping Box to arrive at PSL on 23-June Week of 26-June PSL fits suspension system, works on
21 June 2017 1
Schedule is holding
procedures
21 June 2017 2
21 June 2017 3
DocDB # 4019 Procedure # Procedure Name Start End Lead Author Status PD-SP_01-01 Uncrate APA#1 APA arrives at EHN1
APA is positioned in clean room in Photon Detector Install Area PSL + Bill M. 1st Draft posted PD-SP_01-02 Install Photon Detectors APA is positioned in clean room in Photon Detector Install Area APA is positioned in the CE Install Area Dave W. Started PD-SP_01-03 Install CE APA is positioned in the CE Install Area APA is positioned in the Cold Test Box Matt W. 1st Draft posted PD-SP_01-04 Cold Box testing APA is positioned in the Cold Test Box APA Cold Test Box work complete Roberto (coordinator) not yet started PD-SP_01-05 Move to TCO APA Cold Test Box work complete APA is hanging in the cryostat on Bridge Beam A (near the TCO) Bill not yet started
21 June 2017 4
fixture design is processing this is a snap shot from today
using the fixture for a rotation and will be reviewing it a transportation expert
Finalize design of the transport beam and accessories and have it manufactured This includes:
the cold box or Cryostat
APA, CPA or End Wall
Room Trolley System
21 June 2017 5
Simplify connection with simple welded plate?
21 June 2017 6
Action Item: Done
drawing including new strap design from Dan Wenman
Tool and the custom length strap is being manufactured. It should be shipping to Ash River early next week.
block and ordering the pins and bolts
shipment of tools to CERN
21 June 2017 7
PSL has confirmed that they are supplying the Coat Hanger and all bolts/pins required to install it with APA The APA “Coat Hanger” supports the APA when it is in the Vertical position gets installed before it is lifted in the box
21 June 2017 8
The cable trays are the first things installed after the inspection of the APA They are needed to manage cables for both the PD and the CE and the APA can not be moved without them
to make “handle”. CERN design?
waiting on cable tray and Trolley parts- Is Shipping 6-July is that too late? Still trying for the 29-June
need CERN to supply for APA 1- Started on APA-1-Parts-Tools list.xls
River to clear hand railing and enter the SAS. We will supply documentation and lengths next week- List in APA-1-Parts- Tools-list.xlx
21 June 2017 9
21 June 2017 10
LSU could use the End Wall feet and lifting plates-BUT then we can not take the end wall down
size 12m length week of 7- August
everything back and it may be useful for DUNE studies?
boxes out of my building?