Getting ready 21 June, 2017 for APA # 1 proto 1 21 June 2017 - - PowerPoint PPT Presentation

getting ready
SMART_READER_LITE
LIVE PREVIEW

Getting ready 21 June, 2017 for APA # 1 proto 1 21 June 2017 - - PowerPoint PPT Presentation

William Miller-UMN Getting ready 21 June, 2017 for APA # 1 proto 1 21 June 2017 1-APA #1 shipping schedule Schedule is holding Shipping Box to arrive at PSL on 23-June Week of 26-June PSL fits suspension system, works on


slide-1
SLIDE 1

proto

William Miller-UMN 21 June, 2017

Getting ready for APA # 1

21 June 2017 1

slide-2
SLIDE 2

proto

1-APA #1 shipping schedule

Schedule is holding

  • Shipping Box to arrive at PSL on 23-June
  • Week of 26-June PSL fits suspension system, works on

procedures

  • Bill and Curt travel to PSL 29/30-June
  • Box is closed up 6/7-July
  • Trucked to O’Hare on 10-July (Charles, Curt, Bill fly to CERN)
  • Departs via plane for Luxembourg 11-July
  • Trucked to CERN on 14-July

21 June 2017 2

17-July 17 uncrate and start the process!

slide-3
SLIDE 3

proto

APA #1 Installation Procedures

21 June 2017 3

DocDB # 4019 Procedure # Procedure Name Start End Lead Author Status PD-SP_01-01 Uncrate APA#1 APA arrives at EHN1

  • utside of SAS

APA is positioned in clean room in Photon Detector Install Area PSL + Bill M. 1st Draft posted PD-SP_01-02 Install Photon Detectors APA is positioned in clean room in Photon Detector Install Area APA is positioned in the CE Install Area Dave W. Started PD-SP_01-03 Install CE APA is positioned in the CE Install Area APA is positioned in the Cold Test Box Matt W. 1st Draft posted PD-SP_01-04 Cold Box testing APA is positioned in the Cold Test Box APA Cold Test Box work complete Roberto (coordinator) not yet started PD-SP_01-05 Move to TCO APA Cold Test Box work complete APA is hanging in the cryostat on Bridge Beam A (near the TCO) Bill not yet started

We need to continue to push hard on this front

slide-4
SLIDE 4

proto

APA Lifting Fixture-Status In Progress

21 June 2017 4

  • New APA lifting

fixture design is processing this is a snap shot from today

  • They have a draft set
  • f procedures for

using the fixture for a rotation and will be reviewing it a transportation expert

  • n Friday
slide-5
SLIDE 5

proto

Transport Beam-Not known

Finalize design of the transport beam and accessories and have it manufactured This includes:

  • The tie plates to connect to

the cold box or Cryostat

  • Push pin blocks to hold the

APA, CPA or End Wall

  • Connection to the Clean

Room Trolley System

21 June 2017 5

They found the stainless steel beam needed in Europe

Simplify connection with simple welded plate?

slide-6
SLIDE 6

proto

APA Trolley-Status

21 June 2017 6

Action Item: Done

  • Dan Swenson has completed

drawing including new strap design from Dan Wenman

  • Trolley is now in hand at Total

Tool and the custom length strap is being manufactured. It should be shipping to Ash River early next week.

  • Total Tool is making the spacer

block and ordering the pins and bolts

  • Ash River will include it our

shipment of tools to CERN

slide-7
SLIDE 7

proto

APA “Coat Hanger”-Status - Done

21 June 2017 7

PSL has confirmed that they are supplying the Coat Hanger and all bolts/pins required to install it with APA The APA “Coat Hanger” supports the APA when it is in the Vertical position gets installed before it is lifted in the box

slide-8
SLIDE 8

proto

Cable Trays-Status- In Progress

21 June 2017 8

The cable trays are the first things installed after the inspection of the APA They are needed to manage cables for both the PD and the CE and the APA can not be moved without them

CERN is supplying the cable trays, the 200mm Stainless is back ordered so we may have to plated for now or 150mm Manhong supplied part list everything has been

  • rdered plus spares to be

shipped to AR and included in our Tool shipment

slide-9
SLIDE 9

proto

Other Items Required

  • Need to order several more PSL stand-offs for APA Rivnut holes

to make “handle”. CERN design?

  • Shipment of tools and lifting winch trolleys from Ash River,

waiting on cable tray and Trolley parts- Is Shipping 6-July is that too late? Still trying for the 29-June

  • Complete list of man-lift or other access equipment that we

need CERN to supply for APA 1- Started on APA-1-Parts-Tools list.xls

  • We did a study of sling lengths needed for APA rotation at Ash

River to clear hand railing and enter the SAS. We will supply documentation and lengths next week- List in APA-1-Parts- Tools-list.xlx

21 June 2017 9

slide-10
SLIDE 10

proto

Trail Assembly Components?

21 June 2017 10

  • This came up this week that

LSU could use the End Wall feet and lifting plates-BUT then we can not take the end wall down

  • Using CPA parts to test full

size 12m length week of 7- August

  • It will be costly to ship

everything back and it may be useful for DUNE studies?

  • Can I remove flammable

boxes out of my building?