Prepared for WECC
May 15, 2019
Generation and Transmission Resource Cost Update 2019 Prepared for - - PowerPoint PPT Presentation
Generation and Transmission Resource Cost Update 2019 Prepared for WECC May 15, 2019 Contents Background, approach, and sources Transmission resource capital cost update B&V cost framework and recent inflation metrics
May 15, 2019
– Benchmarking vs. estimated Tx project costs
– Comparison of costs across public sources for solar PV, wind, Li-ion battery storage – Benchmarking vs. recent public PPA prices and RFP bids
reports for WECC
2
3
compared on a variable-cost basis
their actual prospective costs to ratepayers by combining variable and fixed costs
Total Cost Fuel and Variable Costs
Fixed Cost
(E3 Capital Cost Tool)
4
In preparation for its upcoming 20-year study plan, WECC has asked E3 to provide guidance on resource cost to use in that study These capital costs will serve as an input to the 20-year study’s LTPT, allowing for the development of robust scenarios through cost minimization
standard lifetime, financing, and O&M assumptions to calculate levelized costs of each resource
This efforts builds on similar work performed in late 2016–early 2017 INPUTS MODELS STUDY RESULTS 20-Year Study
Twenty-Year Capital Expansion Plan
Generation Portfolio Transmission Topology Gen Capital Costs Tx Capital Costs
Long-Term Planning Tools
(Capital Expansion Optimization)
SCDT NXT Other Constraints
5
Resource costs are typically quoted in either upfront capital costs ($/kW) or levelized costs ($/MWh) that are indicative of likely PPA prices for renewables Levelized costs include several other cost factors and assumptions beyond the project’s upfront capital cost
average capacity factor, is a major driver of LCOE
In this research phase, E3 has focused on capital costs, which are more comparable across data sources and suitable for benchmarking
6
Resource costs vary significantly from project to project due to a variety of local and project- specific factors
forested vs. desert
interconnection
developer economies of scale, etc.
These factors explain the wide range of reported costs that E3 has observed In this initial capital cost report, E3 has identified a reference cost for each technology associated with an average project in WECC
factors can be generalized a state-by-state basis
Average Wind Speed Forest Cover High-Voltage Transmission
7
NREL
Q1 2018
Storage System Costs Benchmark
LBNL
Lazard
IRENA
2017
APS – 2017 IRP Avista – 2017 IRP Idaho Power Company – 2017 IRP Pacificorp – 2017 IRP Update Puget Sound Energy – 2017 IRP
8
the time they are published
9
by single component (e.g. PV modules), but difficult to apply to soft costs and
IRPs 2018 2040 2020 2016 NREL PPAs
Market price Historical price Forecast price
11
construction costs: Bureau of Labor Statistics (BLS)
Way Schedule
12
are made on a county level basis based on census data and can change with each release
BLM Zone Land Costs BLM Zone Number 2015 Per Acre Rent ($/acre-year) 2018 Per Acre Rent ($/acre-year) % Change 1 9 8
2 17 16
3 34 32
4 52 48
5 69 66
6 103 95
7 172 133
8 345 85
9 690 457
10 1,035 1,402 36% 11 1,724 2,805 63% 12 3,449 7,011 103% 13 14,023 14 21,034 15 28,045
13
Tx Cost Component Weighting 2012-2018 inflation 2012-2018 CAGR Sources Materials 50% 5.6% 0.9% BLS Metals PPI, FRED Aluminum and Steel Labor 35% 16.3% 2.6% BLS PPI Construction-Industrial General 15% 13.3% 2.1% BLS CPI-West Total 100% 10.5% 1.7%
14
Metals prices have been volatile, declining in 2015-2016 before increasing again in 2017-2018
15
2012 2013 2014 2015 2016 2017 2018 Cost per mile
$927,000 $914,126 $929,502 $904,570 $888,709 $948,316 $1,024,611
Source B&V 2012 study E3 E3 E3 E3 E3 E3
Calculated Capital Cost per Mile for 230 kV Single Circuit Line (Nominal $)
2012 2013 2014 2015 2016 2017 2018 Cost per mile
$1,011,538 $983,538 $1,007,301 $958,996 $924,612 $967,282 $1,024,611
Source B&V 2012 study E3 E3 E3 E3 E3 E3
Calculated Capital Cost per Mile for 230 kV Single Circuit Line (Real 2018 $)
16
completed in 2015 or expected to be completed within next 4 years
Project name Description Approx. cost (EEI) E3 updated B&V estimate Path 42 15 miles of 230 kV reconductor, including substation upgrades and incorporation of a 230 kV, 48 MVAR capacitor bank, spanning from Devers to Mirage Substation. Completed in 2015 31 MM$ 28 MM$ Sun Valley- Trilby Wash – Palm Valley 30 miles of new, double circuit capable, 230 kV lines through the western Phoenix Metropolitan
transformer is included. Went into service in 2016. 75 MM$ 72 MM$ Palo Verde–Delaney– SunValley–Morgan– Pinnacle Peak 110 miles of new 500 kV lines connecting northeast Phoenix to southwest Phoenix in 4
312 MM$ 330 MM$
17
Input assumptions to E3 updated B&V Tx cost calculator
Select Transmission Projects Path 42 Sun Valley - Trilby Wash - Palm Valley Palo Verde - Delaney - Sun Valley - Morgan - Pinnacle Peak Voltage Class 230 kV Double Circuit 230 kV Double Circuit 500 kV Single Circuit Conductor Type ACSR ACSR ACSR Structure Lattice Lattice Lattice Length Category > 10 miles > 10 miles > 10 miles New or Re-conductor? Re-conductor New New Average Terrain Multiplier 1 1 1 Desert/Barren Land 12 25 80 Rolling Hills (2-8% Slope) 3 5 30 6 95 7 30 15 8 9 15 Voltage 230 kV Substation 230 kV Substation 500 kV Substation New or Existing Site? Existing New Existing Circuit Breaker Type Breaker and a Half Breaker and a Half Breaker and a Half # of Line/XFMR Positions 3 3 3 HVDC Converter No No No Transformer Type 115/230 kV XFMR 138/230 kV XFMR 230/500 kV XFMR MVA Rating Per Transformer 200 200 200 # of Transformers 1 1 3 SVC MVAR Rating Shunt Reactor MVAR Rating Series Capacitor MVAR Rating 48 AFUDC/Overhead Cost 17.5% 17.5% 17.5% BLM Zone Terrain Type Substation Project Inputs
18
20
competitive were filtered out (e.g. single-axis tracking solar is now more economic than fixed-tilt solar and is employed on all new grid-scale projects in WECC, thus fixed-tilt was removed from study)
PPA prices in recent WECC-area RFPs
21
Solar PV
Wind
associated with wind quality, etc. to be handled in more detail in next phase
Energy Storage
– Utility-scale, with and without paired solar – Costs broken out by capacity (kW) and energy (kWh)
Distributed energy resources (DERs)
– Costs broken out by capacity (kW) and energy (kWh)
Gas
without CCS
Other renewables
Other thermal
23
Capital cost 2012 E3 2014 E3 2016 E3 2018 E3*
<20 MW >20 MW <20 MW >20 MW <20 MW >20 MW <20 MW >20 MW
Tracking solar ($/kW-dc) $3,700 $3,250 $3,200 $2,800 $1,700 $1,500 $1,100 Tracking solar ($/kW-ac) $4,400 $3,800 $4,200 $3,600 $2,200 $1,900 $1,450
Recommended Capital Cost, Real 2018$ Capital Cost Estimate by Source
24
PPA Summary Project Name Build Year PPA Price (2020 $/MWh) Location CF (%) Xcel RFP: CO Median RFP bids 2020 29.50 CO 28 AZ Solar 1 2020 24.99 Salome, AZ 32 NV PUC: Eagle Shadow Solar 2021 23.29 Clark County, NV 35 NV PUC: Copper Mountain 5 2021 21.13 Boulder City, NV 33 NV PUC: Techren V 2020 29.98 Boulder City, NV 32 PNM: Route 66 PPA 2021 29.39 Albuquerque, NM 33
25
PPA implied capital cost, 2020 COD NREL ATB 2020 forecast Low Median High Low Mid High Capital cost (2018 $/kW-dc) $778 $935 $1,265 $886 $1,003 $1,198 Capital cost (2018 $/kW-ac) $1,047 $1,262 $1,708 $1,171 $1,325 $1,582
26
Utility-Scale Solar PV Capital Cost Forecast
PPA benchmarking implied 2020 costs E3 2018 recommended cost
27
Capacity Factor LCOE (2018 $/MWh) 27% CF 31.05 30% CF 27.94 33% CF 25.40
Solar PV Levelized Cost Forecast Scenarios
2018 Levelized Cost Estimates – Mid Scenario
29
Capital cost 2012 WECC 2014 E3 2016 E3 2019 E3* Onshore wind ($/kW) $2,300 $2,250 $2,100 $1,650
Recommended Capital Cost, Real 2018$ Capital Cost Estimate by Source
30
PPA Summary Project Name Build Year PPA Price (2020 $/MWh) Location CF (%) Xcel RFP: CO Median RFP bids 2020 18.10 CO 45 PNM: La Joya 2020 27.92 Estancia, NM 47
31
32
NREL 2018 ATB: Onshore Wind Capital Cost Forecast
E3 2018 recommended cost PPA benchmarking implied 2020 costs
33
Capacity Factor LCOE (2018 $/MWh) 35% CF $33.93 40% CF $29.50 45% CF $21.98
Onshore Wind Levelized Cost Forecast Scenarios Preliminary
2018 Levelized Cost Estimates- Mid Scenario
34
Capital cost 2012 WECC 2014 E3 2016 E3 2018 E3* Offshore wind – fixed base ($/kW) $7,000 $6,700 $4,800 $3,500 Offshore wind – floating ($/kW) $6,500
Recommended Capital Cost, Real 2018$ Capital Cost Estimate by Source Floating base offshore wind added to represent potential future west coast projects. Fixed base offshore wind is not viable in most of WECC given seafloor depth off WA/OR/CA
35
Floating Base Offshore Wind – TRG 10 Capital Cost Forecast
36
Onshore Wind Levelized Cost Forecast Scenarios
Lack of large-scale floating offshore wind projects to date adds significant uncertainty to cost forecasts
38
Battery costs vary significantly by system specifications For modeling purposes, costs are commonly broken into two categories
quoted in $/kW
quoted in $/kWh
Battery modules are the largest and best understood component of system cost and the one that scales most linearly with duration
today, but is declining rapidly
Fixed capacity cost including inverter and interconnection varies significantly by report
may be minimal
Utility-scale 4-hr Battery Cost by Component Utility-scale Battery Cost by Duration
39
Capital cost 2012 WECC 2014 E3 2016 E3 2018 E3* Li-ion battery capacity ($/kW)
$75
$200 Li-ion battery energy ($/kWh) $325 Li-ion battery, 4-hr ($/kW)
n/a $5,059 $3,200 $1,375
n/a $5,059 $3,200 $1,500
Recommended Capital Cost Capital Cost Estimate by Source
To benchmark against recent storage PPA prices, E3 examined solar+storage prices in three recent RFPs TEP - 2017
Xcel - 2017
generation and capacity, presumably with utility dispatch
– All three storage projects selected are solar hybrid plants
NV Energy - 2018
– NextEra: Dodge Flats 200 MW/50 MW/4-hr – NextEra: Fish Springs 100 MW/25 MW/4-hr – Cypress Creek: 101 MW/25 MW/4-hr Crescent Valley project (Battle Mountain Solar)
40
NextEra claims storage adds a premium of $15/MWh for solar projects completed in 2017-2018
In recent RFPs, this premium has fallen to $6-$7/MWh for projects with COD in 2021-22
NextEra projects storage premium will fall to $5/MWh by mid-2020s, or under $60/kW-yr with typical sizing ratio 41
Levelized cost of storage when paired with solar – E3 vs NextEra Gross CONE in 2018 $/kW-yr
Current hybrid storage bids reflect aggressive price decline assumptions, capture of the ITC, and other cost savings from pairing with solar such as reduced interconnection costs Result? Discount of 25% to 40% versus standalone storage levelized costs
Recent NV Energy RFP winners
42
ancillary services such as frequency regulation or spinning reserves
43
Capital cost 2012 WECC 2014 E3 2016 E3 2018 E3* Flow battery, 4-hr ($/kW) n/a $5,350 $3,200 $2,000
Recommended Capital Cost Capital Cost Estimate by Source
Flow battery estimated costs have declined nearly as rapidly as Li-ion, but limited commercial experience adds significant uncertainty. No major utility-scale PPAs have been signed for flow batteries in the US to date
45
upon roof size and accessibility, mounting options, etc.
and potential for T&D deferral
46
Capital cost 2012 WECC 2014 E3 2016 E3 2018 E3 Residential solar ($/kW-dc) $6,150 $5,100 $3,100 $2,700 Residential solar ($/kW-ac) $7,250 $6,200 $3,700 $3,250
Recommended Capital Cost, Real 2018$ Capital Cost Estimate by Source
47
Capital cost 2012 WECC 2014 E3 2016 E3 2018 E3* Commercial solar ($/kW-dc) $5,200 $4,300 $2,750 $1,850 Commercial solar ($/kW-ac) $6,100 $5,100 $3,300 $2,200
Recommended Capital Cost, Real 2018$ Capital Cost Estimate by Source
48
Capital cost 2012 WECC 2014 E3 2016 E3 2018 E3* Li-ion battery capacity ($/kW)
Li-ion battery energy ($/kWh)
Li-ion battery, 2-hr ($/kW)
modeling purposes, though some DR programs (e.g. CA DRAM) have contracted with BTM storage
50
Capital cost ($/kW) 2012 WECC 2014 E3 2016 E3 2018 E3* Gas CT—Aero $1,300 $1,300 $1,250 $1,300 Gas CT—Frame $900 $900 $850 $800 Gas CCGT—Conventional (Wet) $1,300 $1,200 $1,200 $1,200 Gas CCGT—Conventional (Dry) $1,400 $1,300 $1,250 $1,250 Gas CCGT—Advanced (Wet) $1,400 $1,300 $1,300 $1,250 Gas CCGT—Advanced (Dry) $1,500 $1,400 $1,350 $1,300 Gas CCGT—Advanced w/ CCS n/a n/a n/a +$1,200 Reciprocating Engine n/a $1,400 $1,350 $1,350 Recommended Capital Cost
increased heat rates (lower efficiency), decreased flexibility (no daily cycling), and variable costs that incorporate the value of tax credits for CCS
52
Capital cost ($/kW) 2012 WECC 2014 E3 2016 E3 2018 E3* Geothermal—Binary $6,400 $6,300 $5,300 $6,100 Geothermal—Binary, enhanced n/a $10,700 $10,600 $13,600 Geothermal—Flash $6,400 $6,300 $5,300 $5,100 Geothermal—Flash, enhanced n/a $10,700 $10,600 $9,000 Hydro—small $4,100 $4,800 $4,200 $4,200 Biomass $4,900 $4,600 $4,550 $4,400 Biogas - Landfill $3,200 $3,000 $2,950 Biogas – Other $6,400 $6,000 $5,900 Solar thermal $5,700-$8,200 $5,500-$8,000 $6,300-$6,900 $5,600-$8,300 Recommended Capital Cost
Cost reports reviewed by E3 show relatively minor changes since prior study Biomass and biogas technologies were combined into single category
project-specific cost considerations, rather than technological differences
53
CHP was combined into single technology due to limited cost data that differentiated between small and large systems Coal IGCC with CCS and small modular nuclear costs are based on public reports and IRPs, but minimal commercial data exists for these technologies
Large scale nuclear costs were increased to $10,000/kW to reflect the latest cost estimates for Vogtle, which may total $27B ($12,000/kW)
Capital cost ($/kW) 2012 WECC 2014 E3 2016 E3 2018 E3* CHP – Small $4,300 $4,100 $4,000 $2,200 CHP – Large $1,850 $1,800 $1,750 Coal – PC no CCS $4,200 $3,950 $3,900 $3,900 Coal – IGCC with CCS $9,300 $8,800 $8,700 $6,700 Nuclear—Large $8,700 $8,200 $8,450 $10,000-$12,000 Nuclear—Small modular n/a n/a n/a $6,200 Recommended Capital Cost
55
such as local labor costs and taxes
Arne Olson, Sr. Partner, arne@ethree.com Nick Schlag, Director, nick@ethree.com Sandy Hull, Sr. Consultant, sandy@ethree.com Vivian Li, Consultant, vivian@ethree.com Femi Sawyerr, Consultant, femi@ethree.com