garden grove freeway garden grove freeway sr 22 project
play

Garden Grove Freeway Garden Grove Freeway (SR-22) Project Update - PowerPoint PPT Presentation

Garden Grove Freeway Garden Grove Freeway (SR-22) Project Update (SR-22) Project Update OCTA Board of Directors OCTA Board of Directors March 14, 2005 March 14, 2005 Days Worked = 174 Days Worked = 174 Days Remaining = 626 Days Remaining


  1. Garden Grove Freeway Garden Grove Freeway (SR-22) Project Update (SR-22) Project Update OCTA Board of Directors OCTA Board of Directors March 14, 2005 March 14, 2005

  2. Days Worked = 174 Days Worked = 174 Days Remaining = 626 Days Remaining = 626

  3. A Little History A Little History • Partnership between OCTA, Caltrans, FHWA, Cities • Partnership between OCTA, Caltrans, FHWA, Cities of Orange, Santa Ana, Garden Grove, Westminster, of Orange, Santa Ana, Garden Grove, Westminster, Seal Beach and Los Alamitos. Seal Beach and Los Alamitos. • OCTA Board Approved Design-Build Oct 2001 • OCTA Board Approved Design-Build Oct 2001 • Request for Qualifications Issued July 2002 • Request for Qualifications Issued July 2002 • Environmental Clearance Mar 2003 • Environmental Clearance Mar 2003 • Request for Proposals Issued Sept 2003 • Request for Proposals Issued Sept 2003 • BAFO Received May 2004 • BAFO Received May 2004 • Contract Award Aug 2004 • Contract Award Aug 2004 • Begin Work Sept 2004 • Begin Work Sept 2004 • Roadway Improvements Complete Nov 2006 • Roadway Improvements Complete Nov 2006

  4. Measure M Makes It Happen Measure M Makes It Happen Measure M $321.4 M CMAQ 21% CMAQ $101.3 M Measure M TCRP $ 56.3 M 66% Cities $ 11.0 M TCRP Total $490.0 M 11% Cities 2%

  5. Project Partners Project Partners Parsons

  6. OCTA SR-22 Organization OCTA SR-22 Organization OCTA Board of Directors RPAH Committee CEO Exec. Dir. Const and Eng SR-22 Program Manager

  7. OCTA SR-22 Project Organization OCTA SR-22 Project Organization Program Manager Safety Manager External Freeway Project Design Const Const Affairs ROW Contracts Service Controls Oversight Seg 1 Seg 2 Manager Patrol Acquisition Utilities Environ.

  8. Project Improvements Project Improvements • HOV lane in each direction • Auxiliary lanes between various interchanges • Continuous Aux lane between City Dr and Beach Blvd • Separate structure from SR-57 connector W/B SR-22 • A collector-distributor road on E/B SR-22 at City Drive • Various interchange improvements, construction of additional soundwalls, replacement planting, and aesthetic enhancements.

  9. Project Details Project Details • 35 bridges to wide, build or replace • 88 retaining walls (640,000 SF) • Import 700,000 tons select backfill • 240,000 cy Concrete Pavement • 60,000 lf new drainage pipe/culverts • 170,000 tons new asphalt pavement

  10. Project Segments Project Segments Segment 1 Segment 2 Segment 1 Segment 2 Segment Segment Segment Segment Segment 1A Segment 1B Segment 1A Segment 1B 2A 2C 2A 2C Segment Segment 2B 2B

  11. Typical Section Typical Section Existing 3 Lanes Each Direction

  12. CITY DRIVE

  13. CITY DRIVE Re-Aligned Local Steet and Ramps New Freeway Connector Elimination of Critical Weave

  14. BEACH BLVD.

  15. BEACH BLVD.

  16. Schedule Control Schedule Control

  17. Schedule Control Schedule Control

  18. Project Status Project Status • Geotechnical Investigation Complete • Right-of-Way Activities Nearly Complete • Design 50% complete • Early work underway – Metropolitan Improvements – Vegetation removal – Excavation/embankment – Material fabrication – Utility relocation – Bridge Demo • Wall and bridge work started last month • Public Outreach in full swing

  19. Project Challenges Project Challenges • 1 ST Design-Build on an active freeway • Working together w/ different entities and agencies • Working together w/ satellite entities • Recognizing the pace of the project • Weather this fall/winter • Resources in this extremely active region • Minimize disruptions

  20. Public Awareness Effort Public Awareness Effort • Construction alerts delivered to 7,000 residents and businesses to date • SR-22 Webpage established – 5,000 hits monthly • Received/answered 120 Helpline calls • More than 1,800 contacts in our database • First “100-day” postcard mailed to 32,000 residents • 6 Open Houses held • Collateral pieces developed • 25 Neighborhood Meetings held since November

  21. Upcoming Board Items Upcoming Board Items April 11 • Approval of maintenance work contained in specifications • Consideration for adding deleted aesthetic treatments back into project April 25 • Review of staff plans for project subcontracts

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend