Garden Grove Freeway Garden Grove Freeway (SR-22) Project Update - - PowerPoint PPT Presentation

garden grove freeway garden grove freeway sr 22 project
SMART_READER_LITE
LIVE PREVIEW

Garden Grove Freeway Garden Grove Freeway (SR-22) Project Update - - PowerPoint PPT Presentation

Garden Grove Freeway Garden Grove Freeway (SR-22) Project Update (SR-22) Project Update OCTA Board of Directors OCTA Board of Directors March 14, 2005 March 14, 2005 Days Worked = 174 Days Worked = 174 Days Remaining = 626 Days Remaining


slide-1
SLIDE 1

Garden Grove Freeway (SR-22) Project Update Garden Grove Freeway (SR-22) Project Update

OCTA Board of Directors March 14, 2005 OCTA Board of Directors March 14, 2005

slide-2
SLIDE 2

Days Worked = 174 Days Remaining = 626 Days Worked = 174 Days Remaining = 626

slide-3
SLIDE 3

A Little History A Little History

  • Partnership between OCTA, Caltrans, FHWA, Cities
  • f Orange, Santa Ana, Garden Grove, Westminster,

Seal Beach and Los Alamitos.

  • OCTA Board Approved Design-Build

Oct 2001

  • Request for Qualifications Issued

July 2002

  • Environmental Clearance

Mar 2003

  • Request for Proposals Issued

Sept 2003

  • BAFO Received

May 2004

  • Contract Award

Aug 2004

  • Begin Work

Sept 2004

  • Roadway Improvements Complete

Nov 2006

  • Partnership between OCTA, Caltrans, FHWA, Cities
  • f Orange, Santa Ana, Garden Grove, Westminster,

Seal Beach and Los Alamitos.

  • OCTA Board Approved Design-Build

Oct 2001

  • Request for Qualifications Issued

July 2002

  • Environmental Clearance

Mar 2003

  • Request for Proposals Issued

Sept 2003

  • BAFO Received

May 2004

  • Contract Award

Aug 2004

  • Begin Work

Sept 2004

  • Roadway Improvements Complete

Nov 2006

slide-4
SLIDE 4

Measure M Makes It Happen Measure M Makes It Happen

Measure M $321.4 M CMAQ $101.3 M TCRP $ 56.3 M Cities $ 11.0 M Total $490.0 M Measure M 66% CMAQ 21% TCRP 11% Cities 2%

slide-5
SLIDE 5

Project Partners Project Partners

Parsons

slide-6
SLIDE 6

OCTA SR-22 Organization OCTA SR-22 Organization

OCTA Board of Directors CEO

  • Exec. Dir. Const and Eng

SR-22 Program Manager RPAH Committee

slide-7
SLIDE 7

OCTA SR-22 Project Organization OCTA SR-22 Project Organization

Program Manager External Affairs Manager ROW Contracts Project Controls Design Oversight Const Seg 1 Const Seg 2 Freeway Service Patrol Safety Manager Acquisition Utilities Environ.

slide-8
SLIDE 8

Project Improvements Project Improvements

  • HOV lane in each direction
  • Auxiliary lanes between various interchanges
  • Continuous Aux lane between City Dr and Beach Blvd
  • Separate structure from SR-57 connector W/B SR-22
  • A collector-distributor road on E/B SR-22 at City Drive
  • Various interchange improvements, construction of

additional soundwalls, replacement planting, and aesthetic enhancements.

slide-9
SLIDE 9

Project Details Project Details

  • 35 bridges to wide, build or replace
  • 88 retaining walls (640,000 SF)
  • Import 700,000 tons select backfill
  • 240,000 cy Concrete Pavement
  • 60,000 lf new drainage pipe/culverts
  • 170,000 tons new asphalt pavement
slide-10
SLIDE 10

Project Segments Project Segments

Segment 1 Segment 1 Segment 2 Segment 2

Segment 1A Segment 1A Segment 1B Segment 1B Segment 2A Segment 2A Segment 2C Segment 2C Segment 2B Segment 2B

slide-11
SLIDE 11

Typical Section Typical Section

Existing 3 Lanes Each Direction

slide-12
SLIDE 12

CITY DRIVE

slide-13
SLIDE 13

New Freeway Connector Re-Aligned Local Steet and Ramps Elimination of Critical Weave

CITY DRIVE

slide-14
SLIDE 14

BEACH BLVD.

slide-15
SLIDE 15

BEACH BLVD.

slide-16
SLIDE 16

Schedule Control Schedule Control

slide-17
SLIDE 17

Schedule Control Schedule Control

slide-18
SLIDE 18

Project Status Project Status

  • Geotechnical Investigation Complete
  • Right-of-Way Activities Nearly Complete
  • Design 50% complete
  • Early work underway

– Metropolitan Improvements – Vegetation removal – Excavation/embankment – Material fabrication – Utility relocation – Bridge Demo

  • Wall and bridge work started last month
  • Public Outreach in full swing
slide-19
SLIDE 19

Project Challenges Project Challenges

  • 1ST Design-Build on an active freeway
  • Working together w/ different entities and

agencies

  • Working together w/ satellite entities
  • Recognizing the pace of the project
  • Weather this fall/winter
  • Resources in this extremely active region
  • Minimize disruptions
slide-20
SLIDE 20

Public Awareness Effort Public Awareness Effort

  • Construction alerts delivered to 7,000

residents and businesses to date

  • SR-22 Webpage established – 5,000 hits

monthly

  • Received/answered 120 Helpline calls
  • More than 1,800 contacts in our database
  • First “100-day” postcard mailed to 32,000

residents

  • 6 Open Houses held
  • Collateral pieces developed
  • 25 Neighborhood Meetings held since

November

slide-21
SLIDE 21

Upcoming Board Items Upcoming Board Items

April 11

  • Approval of maintenance work contained in

specifications

  • Consideration for adding deleted aesthetic

treatments back into project April 25

  • Review of staff plans for project subcontracts
slide-22
SLIDE 22
slide-23
SLIDE 23
slide-24
SLIDE 24