Garden Grove Freeway Garden Grove Freeway (SR-22) Project Update - - PowerPoint PPT Presentation
Garden Grove Freeway Garden Grove Freeway (SR-22) Project Update - - PowerPoint PPT Presentation
Garden Grove Freeway Garden Grove Freeway (SR-22) Project Update (SR-22) Project Update OCTA Board of Directors OCTA Board of Directors March 14, 2005 March 14, 2005 Days Worked = 174 Days Worked = 174 Days Remaining = 626 Days Remaining
Days Worked = 174 Days Remaining = 626 Days Worked = 174 Days Remaining = 626
A Little History A Little History
- Partnership between OCTA, Caltrans, FHWA, Cities
- f Orange, Santa Ana, Garden Grove, Westminster,
Seal Beach and Los Alamitos.
- OCTA Board Approved Design-Build
Oct 2001
- Request for Qualifications Issued
July 2002
- Environmental Clearance
Mar 2003
- Request for Proposals Issued
Sept 2003
- BAFO Received
May 2004
- Contract Award
Aug 2004
- Begin Work
Sept 2004
- Roadway Improvements Complete
Nov 2006
- Partnership between OCTA, Caltrans, FHWA, Cities
- f Orange, Santa Ana, Garden Grove, Westminster,
Seal Beach and Los Alamitos.
- OCTA Board Approved Design-Build
Oct 2001
- Request for Qualifications Issued
July 2002
- Environmental Clearance
Mar 2003
- Request for Proposals Issued
Sept 2003
- BAFO Received
May 2004
- Contract Award
Aug 2004
- Begin Work
Sept 2004
- Roadway Improvements Complete
Nov 2006
Measure M Makes It Happen Measure M Makes It Happen
Measure M $321.4 M CMAQ $101.3 M TCRP $ 56.3 M Cities $ 11.0 M Total $490.0 M Measure M 66% CMAQ 21% TCRP 11% Cities 2%
Project Partners Project Partners
Parsons
OCTA SR-22 Organization OCTA SR-22 Organization
OCTA Board of Directors CEO
- Exec. Dir. Const and Eng
SR-22 Program Manager RPAH Committee
OCTA SR-22 Project Organization OCTA SR-22 Project Organization
Program Manager External Affairs Manager ROW Contracts Project Controls Design Oversight Const Seg 1 Const Seg 2 Freeway Service Patrol Safety Manager Acquisition Utilities Environ.
Project Improvements Project Improvements
- HOV lane in each direction
- Auxiliary lanes between various interchanges
- Continuous Aux lane between City Dr and Beach Blvd
- Separate structure from SR-57 connector W/B SR-22
- A collector-distributor road on E/B SR-22 at City Drive
- Various interchange improvements, construction of
additional soundwalls, replacement planting, and aesthetic enhancements.
Project Details Project Details
- 35 bridges to wide, build or replace
- 88 retaining walls (640,000 SF)
- Import 700,000 tons select backfill
- 240,000 cy Concrete Pavement
- 60,000 lf new drainage pipe/culverts
- 170,000 tons new asphalt pavement
Project Segments Project Segments
Segment 1 Segment 1 Segment 2 Segment 2
Segment 1A Segment 1A Segment 1B Segment 1B Segment 2A Segment 2A Segment 2C Segment 2C Segment 2B Segment 2B
Typical Section Typical Section
Existing 3 Lanes Each Direction
CITY DRIVE
New Freeway Connector Re-Aligned Local Steet and Ramps Elimination of Critical Weave
CITY DRIVE
BEACH BLVD.
BEACH BLVD.
Schedule Control Schedule Control
Schedule Control Schedule Control
Project Status Project Status
- Geotechnical Investigation Complete
- Right-of-Way Activities Nearly Complete
- Design 50% complete
- Early work underway
– Metropolitan Improvements – Vegetation removal – Excavation/embankment – Material fabrication – Utility relocation – Bridge Demo
- Wall and bridge work started last month
- Public Outreach in full swing
Project Challenges Project Challenges
- 1ST Design-Build on an active freeway
- Working together w/ different entities and
agencies
- Working together w/ satellite entities
- Recognizing the pace of the project
- Weather this fall/winter
- Resources in this extremely active region
- Minimize disruptions
Public Awareness Effort Public Awareness Effort
- Construction alerts delivered to 7,000
residents and businesses to date
- SR-22 Webpage established – 5,000 hits
monthly
- Received/answered 120 Helpline calls
- More than 1,800 contacts in our database
- First “100-day” postcard mailed to 32,000
residents
- 6 Open Houses held
- Collateral pieces developed
- 25 Neighborhood Meetings held since
November
Upcoming Board Items Upcoming Board Items
April 11
- Approval of maintenance work contained in
specifications
- Consideration for adding deleted aesthetic
treatments back into project April 25
- Review of staff plans for project subcontracts