Flexible Operation - Challenges for Thermal Power Plants K B Batra - - PowerPoint PPT Presentation

flexible operation challenges for thermal
SMART_READER_LITE
LIVE PREVIEW

Flexible Operation - Challenges for Thermal Power Plants K B Batra - - PowerPoint PPT Presentation

Flexible Operation - Challenges for Thermal Power Plants K B Batra Technical Services, Noida Total Installed Capacity of India (309244MW) As on 30.11.2016( Source: CEA and MNRE) RES**(MNRE) 15% Nuclear 2% Hydro(Renewable) 14% Coal Oil


slide-1
SLIDE 1

Flexible Operation - Challenges for Thermal Power Plants

K B Batra Technical Services, Noida

slide-2
SLIDE 2

Total Installed Capacity of India (309244MW) As on 30.11.2016( Source: CEA and MNRE)

Coal 61% Gas 8% Oil 0% Hydro(Renewable) 14% Nuclear 2% RES**(MNRE) 15%

Coal Gas Oil Hydro(Renewable) Nuclear RES**(MNRE)

2 16th Dec 2016

slide-3
SLIDE 3

BHEL’s Contribution In Indian Power Sector

20000 40000 60000 80000 100000 120000 140000 160000 180000 200000 Thermal Nuclear CCPP Diesel Hydro RE All India 187802.88 5780 25282.13 918.89 43133.43 46326.82 BHEL 113264 3340 7560.13 199.42 20149.41 175 187802.88 5780 25282.13 918.89 43133.43 46326.82 MW CAPACITY TYPE OF POWER PLANTS All India BHEL

16th Dec 2016 3

slide-4
SLIDE 4

Indian Renewable Energy Sector (46326.82 MW) Source: MNRE

Wind Power 62% Small Hydro 11% Biomass/Cogneneration 9% Solar Power 18% Waste to Power 0%

Wind Power Small Hydro Biomass/Cogneneration Solar Power Waste to Power 4 16th Dec 2016

slide-5
SLIDE 5

Installed RE Capacity Vs. Revised RE Targets A Long Way To Go…..

8727.64 MW 28279.4 MW 4882.33 MW 4323.37 MW 100000 MW 60000 MW 10000 MW 5000 MW 20000 40000 60000 80000 100000 120000 Solar Power Wind Power Biomass Small Hydro

Installed Capacity (October 2016) Revised Targets(Till 2022)

5 16th Dec 2016

slide-6
SLIDE 6

Share of RE in Future Energy Mix Source: MNRE

6 16th Dec 2016

slide-7
SLIDE 7

7

Renewable Generation - Challenges

 Intermittent and variable  Season and Weather dependent  Location and time of day dependent  Does not match the load demand curve  Wind generation is unpredictable  Solar generation is predictable but non controllable

16th Dec 2016

slide-8
SLIDE 8

8

Integration of Renewable Energy in Grid

 Balancing by conventional energy sources (large part of which is

thermal) is required

 Greater the penetration of RE in Grid greater is the requirement

  • f balancing

16th Dec 2016

slide-9
SLIDE 9

Expected All India Duck curve with 20GW Solar Power in Grid

9 16th Dec 2016

slide-10
SLIDE 10

10

Expectation from Thermal plants

 Backing down and cyclic loading  Frequent start/stops may be required  Higher ramping rates during loading and unloading

But base load conventional plants are not designed for such cyclic loading.

16th Dec 2016

slide-11
SLIDE 11

11

Start-up of Steam turbines (BHEL make)

Start type Outage hours Mean HP Rotor temperature (deg C) Start-up time (Rolling to full load in min. approx) Cold Start 190 hr 150 deg C 255 Warm Start 48 hr 380 deg C 155 Hot Start 8 hr 500 deg C 55

Normal Mode : 2000-2200 starts Slow Mode : 8000 starts Fast Mode : 800 starts

16th Dec 2016

slide-12
SLIDE 12

Effect of Load Cycling on Power Plant Components

12

Creep – Slow and continuous deformation of materials due to high temperature exposure even at constant load Thermal Fatigue – Failure of metal when subjected to repeated or fluctuating stresses due to thermal cycling of components Components affected – HP/IP rotors, Blades, Casings, Valves, Header, Y-Piece, T-piece, MS/HRH Pipelines

16th Dec 2016

slide-13
SLIDE 13

13

Life Expenditure of Components

Operating Steam Pressure Life Time Consumption Creep Damage Stress Fatigue Damage Creep Rupture Strength Mechanical Stress Thermal Stress Type of Material Operating Stress Operating Steam temperature Steam Pressure inside a thick – walled component Physical properties of a material Geometrical Dimensions of a thick walled components Temperature Difference inside a thick –walled component

16th Dec 2016

slide-14
SLIDE 14

14

Life Expenditure Computation

The consumed life of a component is the sum of the life consumed by Creep & Low Cycle Fatigue MINER SUM MC IS INDICATOR OF THE LIFE EXPENDED DUE TO CREEP

&

MINER SUM MF IS INDICATOR OF THE LIFE EXPENDED DUE TO LOW CYCLE FATIGUE

16th Dec 2016

slide-15
SLIDE 15

15

FOR STATIONARY COMPONENTS : M = MC + MF = 1 WARNING POINT FOR ROTATING COMPONENTS : M = M C + MF = 0.5 WARNING POINT Approaching the Warning Point of Effective Miner Sum indicates that the life of the component has reached its limit.

16th Dec 2016

Life Expenditure Computation

slide-16
SLIDE 16

16

Impact of Cycling on Equipment and Operation

 Critical components are subjected to thermal stresses which are

cyclic in nature

 Higher fatigue rates leading to shorter life of components  Advanced ageing of Generator insulation system due to increased

thermal stresses

 Efficiency degradation at part loads  More wear and tear of components  Damage to equipment if not replaced/attended in time  Shorter inspection periods  Increased fuel cost due to frequent start-ups  Increased O&M cost

16th Dec 2016

slide-17
SLIDE 17

17

Other Operational Risks

 Ventilation in HP and LP Turbine at lower loads  Droplet erosion of LP blades  Excitation of LP blades due to ventilation  Frequent start/stop of major auxiliaries (PA/FD/ID fans, BFP)

reduces their reliability

 Increased risk for pre-fatigued components

16th Dec 2016

slide-18
SLIDE 18

Age of Thermal Power Plants In India (in Years)

5000 10000 15000 20000 25000 30000 35000 40000 45000 0-5 years 6-10 years 10-15 years 15-20 years 20-25 years > 25years 43357 MW 22610 MW 8359 MW 7780 MW 5630 MW > 25years, 29549 MW MW CAPACITY AGE GROUP

slide-19
SLIDE 19

19

Assumed Load Demand Curve on Thermal Machines

16th Dec 2016

20 40 60 80 100 120

55% 80% 100% 80% 2%/min 3%/min

slide-20
SLIDE 20

20

Impact Assessment of Load Cycling

  • Impact of cyclic operation on BHEL supplied equipment with

assumed load curve has been investigated.

  • Lower load is limited to 55% of rated and a ramp down rate of

2%/min and ramp up rate of 3%/ min. is considered.

  • It is assumed that main steam and HRH temperatures are kept

constant and Unit is operated in sliding pressure mode.

16th Dec 2016

slide-21
SLIDE 21

Cyclic Operation - Findings

 Preliminary studies indicate that load backing from 100%-55%

load at a ramp rate of 2%-3% per minute will not have significant impact on life consumption of Turbine, Boiler, Generator & ESP.

 However this mode of operation will have additional cost in

terms of lower efficiency at part loads.

16th Dec 2016 20

 Backing down below 55% load and/or increase in ramp rates will

have effect on the fatigue life of the equipment.

 Backing down below 55% load will also have other negative

impacts on the equipment as discussed earlier and need further investigation in detail.

slide-22
SLIDE 22

22

Mitigating the Effect of Cycling

 Additional Condition monitoring systems/ Sensors  Improved design of Boiler and Turbine to allow faster ramping

and increased number of cycles

 Adaptation of Control System  Low cycling regime for older plants (may require RLA)  Replacement of fatigued/ worn-out components  Shorter inspection period

16th Dec 2016

slide-23
SLIDE 23

23

Condition Monitoring for Flexible operation

 Complete operation data is available  Continuous online consumption of life expenditure  Detection of highly stressed parts for inspection  Scheduling of RLA  Exploring the margins available for optimization of operating

modes

 Online monitoring of Generator components as early warning

system

16th Dec 2016

slide-24
SLIDE 24

24

Condition Monitoring Systems

 Turbine Stress Controller (TSC)  Boiler Stress Monitoring System (BOSMON)  Blade Vibration Monitoring System (BVMS)  Stator End Winding Vibration Monitoring  Rotor Flux Monitoring  Partial Discharge Monitoring  Additional sensors for health monitoring

16th Dec 2016

slide-25
SLIDE 25

25

Renewables integration - Overall impact

Thus increased penetration of renewables will lead to

 Increased cost due to cycling resulting in higher tariff from

conventional sources

 Reduced equipment life and thus earlier replacement of

plants

slide-26
SLIDE 26

26

Renewables integration - Overall impact

Thus increased penetration of renewables will lead to

 Increased cost due to cycling resulting in higher tariff from

conventional sources

 Reduced equipment life and thus earlier replacement of plants  Increased CO emissions, partly offsetting the gains from

renewables

16th Dec 2016