flexible operation
play

Flexible Operation Integrating thermal power with Renewable Energy - PowerPoint PPT Presentation

Flexible Operation Integrating thermal power with Renewable Energy & Challenges Y M Babu 1 Technical Services, Noida Why Flexible Operation? Limitations with Renewable generation has called for flexible operation: Intermittent and


  1. Flexible Operation Integrating thermal power with Renewable Energy & Challenges Y M Babu 1 Technical Services, Noida

  2. Why Flexible Operation? Limitations with Renewable generation has called for flexible operation:  Intermittent and variable  Season and Weather dependent  Location and time of day dependent  Does not match the load demand curve  Wind generation is unpredictable  Solar generation is predictable but non controllable 2 30 th Nov 2018

  3. Integration of Renewable Energy in Grid  Balancing by conventional energy sources (large part of which is thermal) is required.  Greater the penetration of RE in grid, greater is the requirement of balancing. 3 30 th Nov 2018

  4. Expectation from Thermal plants  Backing down and cyclic loading  Frequent start/stops may be required  Higher ramping rates during loading and unloading But base load conventional plants are not designed for such cyclic loading. 4 30 th Nov 2018

  5. Start-up of Steam turbines (BHEL make) Start type Outage hours Mean HP Rotor Start-up time temperature (Rolling to full (deg C) load in min. approx) Cold Start 190 hr 150 deg C 255 Warm Start 48 hr 380 deg C 155 Hot Start 8 hr 500 deg C 55 Normal Mode : 2000-2200 starts Slow Mode : 8000 starts Fast Mode : 800 starts 5 30 th Nov 2018

  6. Effect of Load Cycling on Power Plant Components Creep – Slow and continuous deformation of materials due to high temperature exposure even at constant load Thermal Fatigue – Failure of metal when subjected to repeated or fluctuating stresses due to thermal cycling of components Components affected – HP/IP rotors, Blades, Casings, Valves, Header, Y-Piece, T-piece, MS/HRH Pipelines and pressure parts. 6 30 th Nov 2018

  7. Life Expenditure of Components Life Time Consumption Fatigue Damage Creep Damage Stress Creep Rupture Strength Operating Steam Operating Type of Mechanical Stress Thermal Stress temperature Stress Material Temperature Steam Pressure Operating Steam Difference inside a inside a thick – thick – walled Pressure walled component component Geometrical Physical properties of a Dimensions of a thick material walled components 7 30 th Nov 2018

  8. Life Expenditure Computation The consumed life of a component is the sum of the life consumed by Creep & Low Cycle Fatigue MINER SUM M C IS INDICATOR OF THE LIFE EXPENDED DUE TO CREEP & MINER SUM M F IS INDICATOR OF THE LIFE EXPENDED DUE TO LOW CYCLE FATIGUE 8 30 th Nov 2018

  9. Life Expenditure Computation FOR STATIONARY COMPONENTS : M = MC + MF = 1 WARNING POINT FOR ROTATING COMPONENTS : M = M C + MF = 0.5 WARNING POINT Approaching the Warning Point of Effective Miner Sum indicates that the life of the component has reached its limit. 9 30 th Nov 2018

  10. Impact of Cycling on Equipment and Operation  Critical components are subjected to thermal stresses which are cyclic in nature  Higher fatigue rates leading to shorter life of components  Advanced ageing of Generator insulation system due to increased thermal stresses  Efficiency degradation at part loads  More wear and tear of components  Damage to equipment if not replaced/attended in time  Shorter inspection periods  Increased fuel cost due to frequent start-ups  Increased O&M cost 10 30 th Nov 2018

  11. Other Operational Risks  Ventilation in HP and LP Turbine at lower loads  Droplet erosion of LP blades  Excitation of LP blades due to ventilation  Frequent start/stop of major auxiliaries (PA/FD/ID fans, BFP) reduces their reliability.  Increased risk for pre-fatigued components.  Drop in efficiency & high Auxiliary Power Consumption (APC) at partial loads 30 th Nov 2018 11

  12. Age of Thermal Power Plants In India (in Years) Number of Sets 43357 MW 45000 40000 35000 > 25years, 29549 MW 30000 MW CAPACITY 22610 MW 25000 20000 15000 8359 MW 7780 MW 10000 5630 MW 5000 0 0-5 years 6-10 years 10-15 years 15-20 years 20-25 years > 25years AGE GROUP 30 th Nov 2018

  13. Assumed Load Demand Curve on Thermal Machines 120 100% 100 80 % 80% 80 2% / min 3% / min 60 40% 40 20 0 13 30 th Nov 2018

  14. Impact Assessment of Load Cycling  Impact of cyclic operation on BHEL supplied equipment with assumed load curve has been investigated.  Lower load upto 55% of rated and a ramp down rate of 2%/min and ramp up rate of 3%/ min. has been established.  Studies are being conducted to assess the impact on component life with loads as low as 40% of the rated load.  It is assumed that main steam and HRH temperatures are kept constant and Unit is operated in sliding pressure mode. 14 30 th Nov 2018

  15. Cyclic Operation - Findings  Preliminary studies indicate that load backing from 100%-55% load at a ramp rate of 2%-3% per minute will not have significant impact on life consumption of Turbine, Boiler, Generator & ESP.  However this mode of operation will have additional cost in terms of lower efficiency at part loads.  Backing down below 55% load and/or increase in ramp rates will have effect on the fatigue life of the equipment.  Backing down below 55% load will also have other negative impacts on the equipment as discussed earlier and need further investigation in detail. 20 30 th Nov 2018

  16. Mitigating the Effect of Cycling  Additional Condition monitoring systems/ Sensors  Improved design of Boiler and Turbine to allow faster ramping and increased number of cycles  Adaptation of Control System  Older plants may require RLA to assess the cycling impact on already fatigued components.  Replacement of fatigued/ worn-out components  Shorter inspection period 16 30 th Nov 2018

  17. Condition Monitoring for Flexible operation  Complete operation data is available.  Scheduling of RLA.  Continuous online consumption of life expenditure.  Detection of highly stressed parts for inspection.  Exploring the margins available for optimization of operating modes.  Online monitoring of Generator components as early warning system. 17 30 th Nov 2018

  18. Condition Monitoring Systems  Turbine Stress Controller (TSC)  Boiler Stress Monitoring System (BOSMON)  Blade Vibration Monitoring System (BVMS)  Stator End Winding Vibration Monitoring  Rotor Flux Monitoring  Partial Discharge Monitoring  Additional sensors for health monitoring 18 30 th Nov 2018

  19. Primary frequency control by regulating turbine extraction  Frequency control technique, allowing for fast response even though boiler response is slow  Reducing the flow through extractions helps in raising the load as steam is forced through turbines  Feed forward command given to boiler master for increasing boiler load for further sustaining the load increase.  Load increase up to 7% is achievable on case to case basis 19 30 th Nov 2018

  20. Model based Predictive Control (MPC) Existing PID Controller Philosophy MPC Philosophy 20 30 th Nov 2018

  21. Model based Predictive Control (MPC) Advanced type controller primarily for steam temperature control for both SH & RH:  Consists of predictor & controller  Predictor creates models based on past operating data and then predicts the parameters in future course  Based on the prediction, the controller regulates the spray control valves.  Continuous communication between MPC & DCS.  Automatic updation of models. 21 30 th Nov 2018

  22. Model based Predictive Control (MPC) Switching scheme for MPC During training of MPC Relevant DPU in MAX DCS Inputs to PID Controller Conventional PID Control PID Output to DESH Inputs to MPC Software MPC Software spray control valve runs in Workstation PID Selection from HMI Station 22 30 th Nov 2018

  23. Model based Predictive Control (MPC) Switching scheme for MPC During running of MPC Relevant DPU in MAX DCS Inputs to PID Controller Conventional PID Control MPC Output to DESH Inputs to MPC Software MPC Software spray control valve runs in Workstation Selection from HMI Station 23 30 th Nov 2018

  24. Online Coal Analyzer Key Aspects Coal Flow Coal & Ash Sieve Analysis Measurement Characterisation  Experiments with different loading rates are being conducted.  The online coal analyser is under development stage. 24 30 th Nov 2018

  25. Online Coal Analyzer (Contd.)  Coal flow & fineness through each pipe can be measured  Better control over air/ fuel ratio  Better control over fineness  Better control over burner performance  Combustion and temperature profiles within the furnace can be improved.  Slagging & fouling issues can be reduced 25 30 th Nov 2018

  26. Flame Scanners  Key requirements:  Reliability for detecting flame of coals with low VM.  Reliability at low load operation.  Reliability for fuel flexible operation. 26 30 th Nov 2018

  27. Flue Gas Temperature Control  Minimum flue gas temperature to be achieved using SCAPH to meet air heating requirements.  Avoid acid corrosion in APH baskets and downstream equipment. 27 30 th Nov 2018

  28. Renewables integration – Overall impact Thus increased penetration of renewables will lead to  Increased cost due to cycling resulting in higher tariff from conventional sources  Reduced equipment life and thus earlier replacement of plants 30 th Nov 2018 28

  29. 29

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend