FEASIBILITY STUDY

BLIND BROOK-RYE UNION FREE SCHOOL DISTRICT

slide-2
SLIDE 2

Presenters

CS Arch Architecture | E ngineering | Construction Management

Thomas M. Ritzenthaler AIA – Vice President / Principal-in-Charge Heather Fagans

Chaze azen En Engin gineer eering, PC

George Cronk, PE – Project Manager

slide-3
SLIDE 3

AGENDA FEASIBILITY STUDY SAFETY & SECURITY SITE LIGHTING CAPITAL PROJ ECTS NEXT STEPS

  • Feasibility Study Review
  • Safety & Security Upgrades
  • Site Lighting
  • Capital Projects
  • Next Steps

Agenda

slide-4
SLIDE 4

Feasibility study

slide-5
SLIDE 5

AGENDA FEASIBILITY STUDY SAFETY & SECURITY SITE LIGHTING CAPITAL PROJ ECTS NEXT STEPS

BMP Ridge Street School

slide-6
SLIDE 6

AGENDA FEASIBILITY STUDY SAFETY & SECURITY SITE LIGHTING CAPITAL PROJ ECTS NEXT STEPS

Middle / High School

slide-7
SLIDE 7

Safety & Security

slide-8
SLIDE 8

AGENDA FEASIBILITY STUDY SAFETY & SECURITY SITE LIGHTING CAPITAL PROJ ECTS NEXT STEPS

Security Vestibules

  • Creation of “Man T

rap” to provide secure location to screen visitors

  • S

eparate security office for the safety of security personnel

  • Access control door hardware
  • Visitor identification program
  • Video intercom to exterior
slide-9
SLIDE 9

AGENDA FEASIBILITY STUDY SAFETY & SECURITY SITE LIGHTING CAPITAL PROJ ECTS NEXT STEPS

Security Vestibules

  • BMP Ridge S

treet S chool

Existing Entry and Main Office Proposed Entry and Main Office Estimated Project Cost: $117,911

slide-10
SLIDE 10

AGENDA FEASIBILITY STUDY SAFETY & SECURITY SITE LIGHTING CAPITAL PROJ ECTS NEXT STEPS

Security Vestibules

  • Middle / High S

chool

Existing Entry and Main Office Proposed Entry and Main Office Estimated Project Cost: $61,200

slide-11
SLIDE 11

Site Lighting Recommendations

slide-12
SLIDE 12

AGENDA FEASIBILITY STUDY SAFETY & SECURITY SITE LIGHTING CAPITAL PROJ ECTS NEXT STEPS

Site Lighting Plan

  • Initial installation cost, LED vs. HID
slide-13
SLIDE 13

AGENDA FEASIBILITY STUDY SAFETY & SECURITY SITE LIGHTING CAPITAL PROJ ECTS NEXT STEPS

Site Lighting Plan

  • Initial installation cost, LED vs. HID
slide-14
SLIDE 14

AGENDA FEASIBILITY STUDY SAFETY & SECURITY SITE LIGHTING CAPITAL PROJ ECTS NEXT STEPS

LED vs. HID Site Lighting

slide-15
SLIDE 15

AGENDA FEASIBILITY STUDY SAFETY & SECURITY SITE LIGHTING CAPITAL PROJ ECTS NEXT STEPS

15 Year Life Cycle Analysis

  • Initial installation cost, LE

D vs. HID

slide-16
SLIDE 16

AGENDA FEASIBILITY STUDY SAFETY & SECURITY SITE LIGHTING CAPITAL PROJ ECTS NEXT STEPS

15 Year Life Cycle Analysis

  • Maintenance Cost
slide-17
SLIDE 17

AGENDA FEASIBILITY STUDY SAFETY & SECURITY SITE LIGHTING CAPITAL PROJ ECTS NEXT STEPS

15 Year Life Cycle Analysis

  • Operational Cost
slide-18
SLIDE 18

AGENDA FEASIBILITY STUDY SAFETY & SECURITY SITE LIGHTING CAPITAL PROJ ECTS NEXT STEPS

15 Year Life Cycle Analysis

  • Cost S

ummary

slide-19
SLIDE 19

Capital Projects

slide-20
SLIDE 20

AGENDA FEASIBILITY STUDY SAFETY & SECURITY SITE LIGHTING CAPITAL PROJ ECTS NEXT STEPS

Middle / High School

  • Additional Classrooms at second floor
  • Previously constructed for future second floor
  • Relatively inaccessible for large equipment
  • Additional Classrooms at existing storage
  • Large enough for use as classrooms
  • Need floor, ceiling, and wall finishes
  • Need to add second means of emergency egress
slide-21
SLIDE 21

AGENDA FEASIBILITY STUDY SAFETY & SECURITY SITE LIGHTING CAPITAL PROJ ECTS NEXT STEPS

Middle / High School

  • Additional Classrooms at second floor

ADDIT ITIO ION – SEC SECOND FLO FLOOR

(2) NE W CLAS S ROOMS (1) NE W S TAIR TOWE R AND RE NOVATE D CORRIDOR Total S

  • Q. FT.: 2,750
  • Approx. Total Project Cost: $982,000
slide-22
SLIDE 22

AGENDA FEASIBILITY STUDY SAFETY & SECURITY SITE LIGHTING CAPITAL PROJ ECTS NEXT STEPS

Middle / High School

  • Additional Classrooms at existing storage

CLAS S RO S S ROOM R RETROFI FIT

CONVE RT E XIS TING S TORAGE TO (2) CLAS S ROOMS (APPROX. 2070 S Q FT) E XCAVATE AND E XTE ND E XIS TING COURTYARD FOR E ME RGE NCY E GRE S S (APPROX. 3750 S Q FT)

  • Approx. Total Project Cost: $680,000
slide-23
SLIDE 23

Next Steps