Board Work Session FEASIBILITY STUDY South Montgomery Community School Corporation January 11, 2016 SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Outline Alignment with 2015-2016 Board Goals- discussion Initial Facility Review Findings


slide-1
SLIDE 1

FEASIBILITY STUDY

South Montgomery Community School Corporation

January 11, 2016

Board Work Session

slide-2
SLIDE 2

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Outline

 Alignment with 2015-2016 Board

Goals- discussion

 Initial Facility Review Findings  Process Schedule

slide-3
SLIDE 3

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Alignment with 2015-2016 Board Goals- discussion

 Student Achievement  Programming & Facilities  Communication  Governance & Fiscal Stability

slide-4
SLIDE 4

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Alignment with 2015-2016 Board Goals- discussion

 Student Achievement

 Improve Test Scores and

Graduation Rates

 Culture of use/integration of

technology

 Plan for the use of personal

technology devices

slide-5
SLIDE 5

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Alignment with 2015-2016 Board Goals- discussion

 Programming & Facilities

 Junior/Senior High School

 Site Master Plan  CTE Programs  Infrastructure improvements  Technology needs

slide-6
SLIDE 6

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Alignment with 2015-2016 Board Goals- discussion

 Programming & Facilities

 Elementary Schools

 Site Master Plan  Infrastructure improvements  Technology needs

slide-7
SLIDE 7

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Alignment with 2015-2016 Board Goals- discussion

 Programming & Facilities

 Grade Reconfiguration

slide-8
SLIDE 8

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Alignment with 2015-2016 Board Goals- discussion

 Communication

 Maintain communications that

is timely and informative to stakeholders and promotes the school corporation

 Use [electronic media] in this

effort

slide-9
SLIDE 9

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Alignment with 2015-2016 Board Goals- discussion

 Governance & Fiscal Stability

 Explore cost savings strategies

within the current corporation footprint

 Ensure the long-term viability

  • f the corporation through

sound, strategic and responsible financial panning

slide-10
SLIDE 10

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Initial Facility Review Findings Ladoga Elementary School

 Grades K-6  224 Enrollment  42,978 Square Feet  Construction Plans

 1976

 Renovations/Additions

 1996

 Renovations

slide-11
SLIDE 11

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Ladoga Elementary School

 Site

 Vehicular congestion  Playground access  Drainage

slide-12
SLIDE 12

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Ladoga Elementary School

 Building

 Roof needs replaced  Secure entrance with curb appeal  Interior finishes need replaced  HVAC system needs replaced  Improve electrical power and

technology access/reliability

slide-13
SLIDE 13

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Initial Facility Review Findings Walnut Elementary School

 Grades K-6  181 Enrollment  51,033 Square Feet  Construction Plans

 1989

 Renovation/Addition

 2008

 Renovation/Addition

slide-14
SLIDE 14

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Walnut Elementary School

 Site

 Replace on-site sewage

treatment plant or provide connection to nearby municipal facility

slide-15
SLIDE 15

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Walnut Elementary School

 Building

 Roof repairs needed  Secure entrance with curb appeal  Interior finishes need updated  HVAC system needs replaced  Improve technology

access/reliability

slide-16
SLIDE 16

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Initial Facility Review Findings New Market Elementary School

 Grades K-6  500 Enrollment  80,577 Square Feet  Construction Plans

 1989

 Additions/Renovation

slide-17
SLIDE 17

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

New Market Elementary School

 Site

 Vehicular congestion  Remove portable

slide-18
SLIDE 18

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

New Market Elementary School

 Building

 Roof needs replaced  Improve entrance security  Interior finishes need

replaced

 Consider additional rest

room facilities

 HVAC system needs

replaced

 Improve electrical power and

technology access/reliability

slide-19
SLIDE 19

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Initial Facility Review Findings Waveland School Facility

 Estimate $258,000 for total

demolition

 Partial demolition, with

gym/support spaces remaining will cost more

slide-20
SLIDE 20

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Initial Facility Review Findings Junior/Senior High School

 Grades 7-8/9-12  277/519 Enrollment  282,184 Square Feet  Construction Plans

 1969  Renovation/Addition 1989  Renovation/Addition 2004

slide-21
SLIDE 21

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Junior/Senior High School

 Site

 Master Plan

 Expanded athletic facilities

 Soccer  Baseball  Softball  Football-practice  Parking  Support facilities

 Future district support facilities

slide-22
SLIDE 22

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Junior/Senior High School

 Building

 Security/zoning  CTE entrance and facilities  Collaborative learning spaces  Specific infrastructure improvements

 Roof repairs/replacement  Plumbing  Elevator(s)  JH bleachers  Doors/hardware

slide-23
SLIDE 23

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Initial Facility Review Findings District Support Facilities

 District-wide needs

 WAN fiber improvements  New transportation

support building

 Additional areas for

evaluation will be identified in this process

slide-24
SLIDE 24

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Process going forward Develop conceptual plans to illustrate proposed renovations/new construction:

 Junior/Senior High School

 Campus Master Plan  Floor plans

 Elementary School

 Floor plans

slide-25
SLIDE 25

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Process

 Community Outreach

 Presentation at each School site

slide-26
SLIDE 26

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Process going forward

 Document proposed

improvements that may become part of a District-wide facilities initiative

 Correlate improvements to

available funding

 Prioritize project improvements

  • ver a phased timeline
slide-27
SLIDE 27

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Process going forward

 Final Report

 Executive Summary  Documented findings as

noted above

 Recommended Option(s):

 Timeline  Cost  Funding

slide-28
SLIDE 28

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Schedule/Major Milestones

2015 November Kick-off Meeting Data Collection begins Building Visitations Board Meeting- Study Overview 2016 January Board Work Session February Board Review- initial concepts March Community Meetings April Draft Study Review May Board Meeting- Final Study Presentation

slide-29
SLIDE 29

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Feasibility Study