FEASIBILITY STUDY
South Montgomery Community School Corporation
June 13, 2016
Board Meeting Presentation
FEASIBILITY STUDY South Montgomery Community School Corporation - - PowerPoint PPT Presentation
Board Meeting Presentation FEASIBILITY STUDY South Montgomery Community School Corporation June 13, 2016 SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Data Collection December Board Meeting- Update
South Montgomery Community School Corporation
June 13, 2016
Board Meeting Presentation
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
2015 November Data Collection December Board Meeting- Update 2016 January Elementary School visitations February JH/HS and other facility visitations March Board Meeting- Update April 12 New Market ES Community Meeting 20 Ladoga ES Community Meeting 26 Walnut ES Community Meeting May Finance review June 13 Board Meeting- Summary Presentation
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Evaluate School Facilities for the following: * Site/Circulation * Safety/Security * Building Envelope * Building Environment * Building Interior/Systems ***Consider 6th Grade Location
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Interior/Systems
improvements
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Site/Circulation
parking (not simultaneous)
camera coverage
equipment replacement to improve accessibility
treatment plant
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Envelope
and windows
entry vestibule for security and wind screen for students that are transferring between buses
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Interior/Systems
vestibule
function
with 6th grade relocation
skills classroom
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Site/Circulation
drop-off/pick-up
flooding that occurs during large rainfall events
loading
equipment replacement/ to improve accessibility
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Envelope
and windows
and 2009 gym roofs
entry
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Interior/Systems
1. Provide new secure entry vestibule 2. Relocate administrative offices to larger/more functional location 3. Repurpose existing office for small group/other 4. Improve restroom ADA compliance 5. Improve flexibility for team collaboration 6. Selective kitchen equipment replacement 7. Replace seating handrails/stage curtain 8. Would gain one classroom with 6th grade relocation * Generally improve acoustics in all classrooms
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Site/Circulation
lot
loading to parking
drop-off/pick-up
equipment replacement/ improve accessibility
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Envelope
roof and 1999 shingle roof
problems
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Interior/Systems
vestibule
waiting
restrooms
flow/ replace seating
classrooms with 6th grade relocation
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Interior/Systems
to accommodate 6th Grade
for JH wrestling
classroom
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Interior/Systems
needed/incorporate electronic access
JH gym roofs
to, Career and Technical Education
1. Advanced manufacturing 2. Engineering and Technology 3. Fire Science 4. Law Enforcement 5. Culinary Arts
Ag./Hort. , and associated spaces
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Administrative Offices
at JH/HS Campus Transportation Center
JH/HS Campus Administrative Offices
connections from three elementary schools JH/HS Campus
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Site/Circ. Safety/Sec. Building Env. Building Int. Building Sys. Total
High School 5,696,500 95,000 487,200 $2,679,500 $8,958,200 Junior High School 45,000 281,350 326,350 Walnut ES 300,000 102,066 993,396 1,063,995 1,313,369 3,772,826 Ladoga ES $350,000 520,956 673,692 860,736 1,292,306 3,697,690 New Market ES 207,500 313,154 1,369,809 1,066,770 2,082,440 5,039,673 Administrative Offices 1,476,000 Transportation Center 3,731,250 District-wide Needs 926,640 Construction Costs 6,554,000 1,076,176 3,524,097 5,952,351 4,688,115 $27,928,629 Soft Costs $6,982,157 Total Project Costs
$34,910,787
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Phasing Considerations
Protect future improvements
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Phasing Considerations
Protect future improvements
Reroof work will eliminate leaks and the accompanying damage to current and
future improvements
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Envelope
roof and 1999 shingle roof
problems
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Phasing Considerations
Protect future improvements
Reroof work will eliminate leaks and the accompanying damage to building
interiors
Consider timing of work to avoid conflicts with school functions
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Phasing Considerations
Protect future improvements
Reroof work will eliminate leaks and the accompanying damage to building
interiors
Consider timing of work to avoid conflicts with school functions
Either schedule work to be completed over summer break, or provide an
alternative program location while work is being completed
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Interior/Systems
1. Provide new secure entry vestibule 2. Relocate administrative offices to larger/more functional location 3. Repurpose existing office for small group/other 4. Improve restroom ADA compliance 5. Improve flexibility for team collaboration 6. Selective kitchen equipment replacement 7. Replace seating handrails/stage curtain 8. Would gain one classroom with 6th grade relocation * Generally improve acoustics in all classrooms
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Phasing Considerations
Protect future improvements
Reroof work will eliminate leaks and the accompanying damage to building
interiors
Consider timing of work to avoid conflicts with school functions
Either plan work to be completed over summer break, or provide an
alternative location while work is being completed
Avoid re-doing work following completion
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Phasing Considerations
Protect future improvements
Reroof work will eliminate leaks and the accompanying damage to building
interiors
Consider timing of work to avoid conflicts with school functions
Either plan work to be completed over summer break, or provide an
alternative location while work is being completed
Avoid re-doing work following completion
Include all work in a room or rooms to avoid returning and potentially
damaging improvements
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Interior/Systems
needed/incorporate electronic access
JH gym roofs
to, Career and Technical Education
1. Advanced manufacturing 2. Engineering and Technology 3. Fire Science 4. Law Enforcement 5. Culinary Arts
Ag./Hort. , and associated spaces
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Phasing Considerations
Protect future improvements
Reroof work will eliminate leaks and the accompanying damage to building
interiors
Consider timing of work to avoid conflicts with school functions
Either plan work to be completed over summer break, or provide an
alternative location while work is being completed
Avoid re-doing work following completion
Include all work in a room or rooms to avoid returning and potentially
damaging improvements
Group similar kinds of work
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Phasing Considerations
Protect future improvements
Reroof work will eliminate leaks and the accompanying damage to building
interiors
Consider timing of work to avoid conflicts with school functions
Either plan work to be completed over summer break, or provide an
alternative location wile work is being completed
Avoid re-doing work following completion
Include all work in a room or rooms to avoid returning and potentially
damaging improvements
Group similar kinds of work
A poor grouping would be HVAC replacement and pavement repair
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Site/Circulation
lot
loading to parking
equipment replacement to improve accessibility
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Much of the work must take advantage of summer months Summer is the busiest construction period The most favorable pricing (bids) is received in January-March in
That will require design work to commence no later than
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Site/ Circulation Safety/ Security Building Envelop Building Interior Building Systems Total High School 5,696,500 95,000 487,200 $2,679,500 $8,958,200 Junior High School 45,000 281,350 326,350 Walnut ES 300,000 102,066 993,396 1,063,995 1,313,369 3,772,826 Ladoga ES $350,000 520,956 673,692 860,736 1,292,306 3,697,690 New Market ES 207,500 313,154 1,369,809 1,066,770 2,082,440 5,039,673 Administrative Offices 1,476,000 Transportation Center 3,731,250 District-wide Needs 926,640 Construction Costs 6,554,000 1,076,176 3,524,097 5,952,351 4,688,115 $27,928,629 Soft Costs $6,982,157 Total Project Costs
$34,910,787
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Site/Circulation PE/Athletics
Baseball complex $ 925,000 Softball complex $ 625,000 BB/SB Support Building $ 756,250 Soccer complex $ 210,000 Practice Football complex $ 180,000 Stadium synthetic turf $ 850,000 Stadium team building $ 1,375,000
Parking
Soccer parking $ 240,000 Football parking $ 187,500 BB/SB parking $ 123,750 Drive New North Drive $ 224,000 SUBTOTAL $ 5,696,500
Safety/Security
Replace hardware as needed $ 70,000 New digital cameras $ 25,000 SUBTOTAL $ 95,000
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Envelope
Reroof Main Gym $ 268,800 Reroof Junior High Gym $ 218,400 SUBTOTAL
$ 487,200
Building Interior Spaces
Career/Tech Ed. Improvements Remodeling $ 795,000 New Construction $ 1,269,000 Woods Lab Improvement $ 80,500 Ag/Horticulture Improvements Lab/classrooms $ 280,000 Greenhouses $ 150,000 Culinary Arts Lab Finishes Remodeling $ 105,000 SUBTOTAL $ 2,679,500
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Safety/Security Install new doors/gates to secure corridor
Near cafeteria $ 30,000 Digital cameras $ 15,000 SUBTOTAL $ 45,000
Building Interior Spaces
Repurpose Corp. Admin. for 6th grade wing $ 130,000 Repurpose lower level storage for JH wrestling $ 150,000 Add Time-Out Room at SE classroom $ 1,350 SUBTOTAL $ 281,350
Site/Circulation Included with High School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Site/Circulation
New sewage treatment plant $ 250,000 Playground equipment Improvements $ 50,000 SUBTOTAL $ 300,000
Safety/Security
New digital camera system $ 102,066 SUBTOTAL $ 102,066
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Envelope
Reroof entire building $ 612,396 Replace exterior windows/doors $ 153,000 Provide new entry vestibule
$ 228,000
SUBTOTAL $ 993,396
Building Interior Spaces
Remodel office $ 180,000 Repurpose music room $ 58,500 Remodel finishes $ 765,495 Install new marker boards $ 20,000 Renovate restrooms (north group) $ 40,000 SUBTOTAL
$ 1,063,995
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Systems
HVAC systems replacement $ 1,224,792 Replace PA system $ 41,626 Add phones in all rooms $ 46,950 SUBTOTAL $ 1,313,369
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Site/Circulation
Taylor Street Improvements $ 200,000 Drainage Improvements $ 75,000 Playground equip. Improvements $ 50,000 Increase west sidewalk width $ 25,000 SUBTOTAL $ 350,000
Safety/Security
New secure main entrance/admin. $ 435,000 New Digital camera system $ 85,956 SUBTOTAL $ 520,956
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Envelope
Reroof entire building $ 601,692 Replace exterior windows/doors $ 72,000 SUBTOTAL $ 673,692
Building Interior Spaces
Repurpose existing office area $ 90,000 Improve classroom acoustics $ 20,000 Repurpose music room $ 20,000 Remodel finishes $ 515,736 Install new marker boards $ 20,000 Remodel group restrooms $ 60,000 Selective kitchen equip. replacement $ 75,000 Gym railings/curtain replacement $ 60,000 SUBTOTAL $ 860,736
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Systems
HVAC systems replacement $ 1,031,472 Provide new sprinkler system $ 171,912 Replace PA system $ 34,382 Add phones in all rooms $ 39,540 Improve wireless coverage $ 15,000 SUBTOTAL $ 1,292,306
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Site/Circulation
New bus drop-off/pick-up lot $ 112,500 Repurpose existing drop-off pick-up lot $ 20,000 Playground equip. improvements $ 50,000 Provide additional walks at playgrounds $ 25,000 SUBTOTAL $ 207,500
Safety/Security
Expand secure vestibule and office entrance $ 152,000 New digital camera system $ 161,154 SUBTOTAL
$ 313,154
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Envelope
Reroof entire building $ 1,208,655 Resolve soffit/venting issues $ 161,154 SUBTOTAL $ 1,369,809
Building Interior Spaces
Add second set of group restrooms $ 135,000 Update staff lounge $ 20,000 Replace gym bleachers $ 75,000 Remodel finishes $ 805,770 Install new marker boards $ 20,000 Add stepped story areas in 2 Kindergarten rooms $ 11,000 SUBTOTAL $ 1,066,770
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Building Systems
HVAC systems replacement $ 1,933,848 Replace PA system $ 64,462 Add phones in all rooms $ 74,131 Replace gym sound system $ 10,000
HVAC
SUBTOTAL $ 2,082,440