FBC LID 7 Update

NTRCA Annual Meeting

January 21, 2019 Directors Jim Grotte, Cindy Picazo, Gerald Kazmierczak, Jeff Hanig & Michael Pincomb

slide-2
SLIDE 2

FBC LID 7

Projects

 Brazos River

Erosion

 Expanded Pump

Station

 Expanded Internal

Detention

 North Levee

Enclosure

 External Channel

Erosion

slide-3
SLIDE 3

Brazos River Erosion

Est Cost: $60 MM Est Grant: $45 MM* Est LID 7: $15 MM Est Completion: 2021-22 *Approved at TX State level. FEMA approval required.

slide-4
SLIDE 4

Expanded Detention & Pumpage

Detention

Est Cost: $5-10 MM Timing: 2020-22

Pumpage

Est Cost: $5-10 MM Timing: 2019-20

Design protection to 71.5 ft * (Lowest home foundations 73.0) ft) (Peak Harvey 73.3 ft)

* True elevation **Diagram from Costello Internal Drainage System Hydrologic and Hydraulic Analysis

slide-5
SLIDE 5

2018 Accomplishments

 FEMA Brazos River Funding

  • Received Texas Division of Emergency Management (TDEM) approval for up to $45 MM

Federal Hazard Mitigation Grant funding for Brazos River erosion project. Major milestone, though still requires FEMA technical review and approval.

 Internal Drainage System Hydrologic and Hydraulic Analysis (Costello)

  • 508 Acre-ft internal existing detention.
  • Additional 150 acre-ft required to protect for Harvey type event.
  • Additional 160,000 GPM required to protect for Harvey type event.
  • Purchased five 10,000 GPM gator pumps for short-term protection.

 Interviewing New District Engineering Firms

  • Interviewing two candidate firms.

 Regional Coordination

  • On-going discussions with FBC on joint flood protection for 90/99 intersection.
  • On-going discussions with City of Sugar Land on land acquisition required for Brazos River

access, pump station expansion and external channel erosion control.

  • Coordinating with US Army Corp of Engineers on permitting and river

boundaries for Brazos River project.

slide-6
SLIDE 6

2019 Goals

 Select new District Engineer (1st Qtr 2019)  Hire outside General Manager (1st Qtr 2019)  Assist with project coordination & contract negotiation

  • Shift work load from legal team.

 Brazos River Erosion

  • Complete FEMA funding approval process (3 months).
  • Complete 30% design.
  • Seek passage of bill in 2019 State legislative session allowing for Design-Build project procurement.
  • Finalize design and plan for construction (late 2019).

 Expanded Pumpage & Detention

  • Finalize detention approach (3 options under consideration).
  • Begin detention excavation (late 2019 – early 2020).
  • Complete 160,000 GPM pump station expansion design.
  • Begin pump station construction (late 2019 – early 2020).

 North Levee

  • Evaluate options.
  • Seek outside financial support.
slide-7
SLIDE 7

Financials

 Developed Cash Flow Proforma

  • Forecasts required for project funds over 18 month horizon.

 Strong Cash Position

  • $2.5 MM liquid cash balance.

 Sold $12.15 MM in bonds

  • Provides initial funding for Brazos River project.
  • Provides initial funding for expanded internal detention and pumpage.

 Identified low cost bond funding available through Texas Water Development Board