FACILITIES AND CAPITAL PROJECTS UPDATE Board of Education Meeting - - PowerPoint PPT Presentation
FACILITIES AND CAPITAL PROJECTS UPDATE Board of Education Meeting - - PowerPoint PPT Presentation
FACILITIES AND CAPITAL PROJECTS UPDATE Board of Education Meeting March 15, 2018 PROJECT PRIORITIZATION Access to Efficiencies Prioritization Building Summer School Bidding Life Safety closures considerations Strategic Plan
Prioritization
- Life Safety
- Strategic Plan
- Age/Need of
Facility
- Impact on
Students/ Instructional Program
Access to Building
- Summer School
closures
- Impact on
students
- Duration of
projects
Efficiencies
- Bidding
considerations
- Access to
facilities
- Construction
scheduling
PROJECT PRIORITIZATION
Financial Considerations
STRATEGIC PLAN TIMELINE
Year 1 Year 2 Years 3-5
Assess/ Determine Facility Needs Conduct Outdoor Facility Study Identify Auditorium Needs Develop 10-Year Improvement Plan Finalize Plan for FHS/CHS Outdoor Facilities Replace Stadium Turf Create Plan for Bathrooms/ Locker Rooms Conduct Review of Potential Energy Efficiencies Identify Timeline of Life Safety Study Implement Plan for Learning Space Renovations Identify Parking Lot, Traffic Flow, Pedestrian Safety Needs Identify Flexible Facility Needs
Organizational Effectiveness: Facility Quality
CAPITAL IMPROVEMENT PROJECT LOCATION AGE/CONDITION
Roof Repairs and Replacement P , F, C, S, H Approximately 40% of total roof square footage nearing life expectancy by 2021 Mechanical Equipment Replacement P , F, C, S, H 25-40 years old; many systems
- riginal to buildings
Bathroom/ Locker Room Renovations P , F, C, H Original to buildings; inadequate exhaust and plumbing; ADA accessibility Artificial Turf Carpet/Track Replacement P , F, C, S, H Surpassing life expectancy Classroom Renovations P , F, C, S, H 21st century classrooms to transform educational space from traditional to collaborative Kitchen Renovations F 20+ years old with inadequate equipment, serving space, and plumbing
STRATEGIC PLAN PRIORITIES
2017-2018 FACILITY IMPROVEMENT UPDATE
SHS Cafeteria FHS Media Center SHS Locker Rooms SHS Restrooms CHS Foods Lab FHS Athletic Fields
OUTDOOR FACILITY STUDY
- Based upon field observations and study results, the following is a recommended
ranking of the school’s facilities that require the most attention ranked from most needed to least needed.
School Tennis Courts Athletic Track Turf Field Schaumburg Demolition of existing asphalt, re-surface Complete Demo and Rebuild Complete Demo and Rebuild Fremd Demolition of existing asphalt, re-surface Complete Demo and Rebuild Complete Demo and Rebuild Palatine Demolition of existing asphalt, re-surface Complete Demo and Rebuild Remove and Replace Carpet Hoffman Estates Demolition of existing asphalt, re-surface Resurface Remove and Replace Carpet Conant Demolition of existing asphalt, re-surface Resurface Remove and Replace Carpet
SUMMER 2018: LIFE SAFETY PROJECT
- Final 2010 life safety
project
- Fremd HS – Auditorium
chiller replacement and primary plant consolidation
- Cooling redundancy for
building
- Increased energy
efficiency
SUMMER 2018: CONANT HIGH SCHOOL WASHROOM RENOVATIONS
- Renovation to all student
washroom restrooms while school is closed
- Replacement of domestic
plumbing
- Updates to washroom electric
and exhaust
- ADA Compliance
- Addition of fire suppression
system
SUMMER 2018: CONANT HIGH SCHOOL ROOF REPLACEMENT
- Roof area over
cafeteria/ main hallway
- 30+ years old
SUMMER 2018: FREMD HIGH SCHOOL ROOF REPLACEMENT
- Roof replacement over
auditorium in conjunction with life safety chiller replacement
- 25+ years old
STADIUM TURF AND TRACK REPLACEMENTS
- Replacement of stadium turf
and track at Schaumburg High School and Fremd High School
- Replacement of original turf
carpet (10+ years old)
- Replacement of drainage
medium under stadium
- Reuse existing EPDM rubber
fill in stadium
- Replace existing track
- Anticipated timeline: May 15-
September 15
SUMMER 2018: PHASE I HOFFMAN ESTATES PARKING LOT RENOVATION
- Redesign primary student
drop-off locations for greater efficiency, safety, and traffic flow
- Defined lanes for buses
and cars
- Permanent curbing at main
entrance
- Designated parent drop-off
locations
- Phase II to include student
lot, west lot, and integration with Higgins Education Center lot
2018-2019: HEHS MEDIA CENTER
- Renovation to portion of
media center
- Collaborative work areas
- T
echnology integration and support desks
- Study/lab spaces for individual
student and classroom use
SUMMER 2018: TENNIS COURT REPAIRS
- T
ennis Court repairs due to excessive cracking and joint separation
- Resurface all existing
courts
- Add additional layer of
asphalt to improve insulation to courts
2018 MECHANICAL UPGRADES
School Mechanical Equipment Unit Date Installed Domestic Water Heater 1980 Air‐Handling Equipment Upgrades 1977 Control Systems Generator Auditorium Mech Renovation 1975 Air‐Handling Equipment Upgrades 1970 Generator Control Systems Air‐Handling Equipment Upgrades 1965 Generator Control Systems Chiller Upgrades 1995 Gym/Locker Rm Domestic WH 1976 Air‐Handling Equipment Upgrades 1976 Control Systems Generator Air‐Handling Equipment Upgrades 1990 Control Systems Generator Palatine Fremd Conant Schaumburg Hoffman
CHS ATHLETIC FIELDS
- Install underground water
drainage system
- Re-grade all playing surfaces
- Reposition playing fields to
provide additional practice field space
- Walking path for use by
physical education classes and improved access to athletic fields
- Recommendation for
renovation under review with timeline and bid recommendation date to be determined
LIFE SAFETY STUDY UPDATE
- Possible items identified on 2018/2019 survey:
- Mechanical equipment replacement
- Roof replacements
- Door/window replacements
- Generator/ emergency power upgrade
- Elevators
- Additional system integration into fire alarm
system
- Intercom AV System
Life Safety Process Anticipated Timeline L/S Study Commenced Underway L/S Study Completed Fall 2018 L/S Study Submitted to ISBE Fall 2018 L/S Approval by ISBE Spring 2019
- Roof replacements
- Mechanical equipment replacement
- Phase II-HEHS Parking Lot
- Security camera/system upgrades
- LED lighting upgrades
- Flexible classroom updates
- Life cycle replacement (equipment, carpet, etc.)
5-YEAR OUTLOOK: O/M FUND
Additional capital projects reviewed annually due to age, condition, & building needs
- Continuation of 2018 identified Life Safety projects
- Continuation of mechanical equipment upgrades
- Continuation of roof replacements
- Continuation of restroom and locker room renovations
- Continuation of items from strategic plan based upon
identified needs (auditoriums, outdoor facilities, etc.)
- Continued life cycle replacements and energy efficiency
updates in O/M
- Continuation of flexible classroom updates
CAPITAL PROJECT PLANNING: 2022-2026
2018-2019 FACILITY IMPROVEMENTS BY FUND
Operations and Maintenance Fund
- T
ennis Court Repairs
- Parking Lot
Paving Work
- Roof
Replacement
- Abatement of
CHS washrooms
- Equipment
Replacement Capital Projects Funds
- Washroom
Renovations
- Stadium
renovations
- Media Center
Renovation
- Outdoor Field
Renovations Life Safety Fund
- Chiller
replacement
- Future project
allocation under 2018 study
Estimated Cost: $3 million Estimated Cost: $8.7 million (exclusive of CHS Field renovations – cost TBD) Estimated Cost: $4 million
FY18 Operating Fund Budget Plan T
- tal Revenue
$249.3 mil T
- tal Expenses
$241.1 mil
- Op. Fund Budget Balance
$8.2 mil
FINANCIAL PLANNING
FY19 Estimated Transfer Amounts Life Safety Fund $3.0 mil Capital Projects Fund* $10.0 mil T
- tal Transfers
$13.0 mil
Inter-fund transfers will be comprised of the FY18 operating budget surplus as well as existing reserves. Inter-fund transfers will fund future capital and life safety projects without need to issue debt.
*Pending CHS athletic field review
AnticipatedTimeline Action March 15, 2018 Bid Approval (Turf/Track,Washrooms, Roofs, Paving) April/May 2018 Bid Approval (Paving, Media Centers, Field Renovations-TBD) April 2018 Financial Projection Update Presentation April-August 2018 Budget Development (Operating Funds)
UPCOMING FINANCIAL SEQUENCE
Future Budget Considerations:
- Ending Budget Position in Current and Future
Years
- Newly identified Life Safety Projects/ Estimated Costs
- Continued budget efficiencies
- Legislative Changes