DHARA CAPITAL PROJECT UPDATE & PROPOSAL CAPITAL PROJECT OVERVIEW Community House Egress Project Remove the aging wooden fire escape from the back of the clubhouse and create a new egress in the front of the building. This will serve
CAPITAL PROJECT OVERVIEW
Community House Egress Project
- Remove the aging wooden fire escape from the back of the clubhouse and create a
new egress in the front of the building.
- This will serve to significantly improve safety and also bring our facility up to
current fire code and ADA standards.
Bathhouse Renovation
- Fully renovate the men’s and women’s bathrooms to improve aesthetics and resolve
significant drainage and ventilation issues.
The board believes both of these projects are necessary and will serve to improve both the safety and overall usability of our clubhouse. The board has engaged Ritter Norton Architect Firm for initial plans
EXISTING CONDITIONS PLAN
CURRENT EGRESS
PROPOSED PLAN
PROPOSED EGRESS
PROPOSED INTERIOR EGRESS
EXISTING CONDITIONS PLAN
DHARA BATHHOUSE RENOVATION PROJECT GOALS & RECENT ACTIVITIES
Primary Goals
- Improve floor drainage and grade to eliminate standing water
- Operable windows to improve airflow
- Improve overall ventilation/replace HVAC system
- Replace hot water system
- Minimize horizontal surfaces, corners, grout/tile joints where dust, grime,
bacteria, mold, or mildew growth may collect
- Replace lockers, sinks, toilets, etc.
- Improve overall bathroom aesthetics
UPDATED CONCEPT PLAN
FINANCE OPTIONS
DHARA FUNDING SOURCE OPTIONS
Capital Reserves Bank Loan Capital Assessment
Financing solution will likely include some mix of these three sources
Capital Reserves Ten Year Bank Loan Capital Assessment Total Project Outlay
Option #1
Overall $220,000 $0 $400,000 $620,000 Per Member Impact No increase in annual dues Two $400 payments for each member Impact on Membership Share Value $800 increase; DHARA members would receive $1,650 upon sale of pool membership
Option #2
Overall $220,000 $300,000 $100,000 $620,000 Per Member Impact Annual dues would increase ~$80 per year for each member to repay loan over the ten-year life of loan One payment of $200 for each member Impact on Membership Share Value $200 increase; DHARA members would receive $1,050 upon sale of pool membership
Option #3
Overall $220,000 $150,000 $250,000 $620,000 Per Member Impact Annual dues would increase ~$40 per year for each member to repay loan over the ten-year life of loan One payment of $500 for each member Impact on Membership Share Value $500 increase; DHARA members would receive $1,350 upon sale of pool membership
BATHHOUSE PROJECT FUNDING OPTIONS
DHARA CAPITAL PROJECTS NEXT STEPS
- Requesting approval of the membership to proceed.
- 30 day membership feedback period
- Questions, comments and suggestions can be emailed or posted in Facebook
- We will plan to have another meeting in May
- Purpose of this meeting will be to have two votes.
- The first will be requesting approval to move forward with the next phase of the
project.
- The second vote will be to request approval of the finance plan.
- Once membership approvals are in place, we will aggressively work to
get full architectural drawings, permits and contractors lined up.
- The goal will be to begin construction shortly after the pool closes