ESSAR OIL VADINAR REFINERY Mega Turnaround Sept-Oct 2011 A Bench - - PowerPoint PPT Presentation

essar oil vadinar refinery
SMART_READER_LITE
LIVE PREVIEW

ESSAR OIL VADINAR REFINERY Mega Turnaround Sept-Oct 2011 A Bench - - PowerPoint PPT Presentation

ESSAR OIL VADINAR REFINERY Mega Turnaround Sept-Oct 2011 A Bench Mark in the Refining sector looking at the large Work-scope which was completed with compressed engineering days and then fast track start-up of the units Turnaround Maintenance


slide-1
SLIDE 1

ESSAR OIL VADINAR REFINERY Mega Turnaround Sept-Oct 2011

A Bench Mark in the Refining sector looking at the large Work-scope which was completed with compressed engineering days and then fast track start-up of the units

slide-2
SLIDE 2

Definition :

In petroleum refining , turnaround means a scheduled large-scale maintenance activity wherein an entire process unit is taken off stream for an extended period for comprehensive revamp and

  • renewal. This operation involves a lot of preparations

and requires many precautions, especially at during startup.

Turnaround Maintenance

slide-3
SLIDE 3

Contents

  • Turnaround Maintenance

+ Objective / Purpose + Process / Procedure + Strategy Followed + Organogram + Key Achievement/Highlights + Key Learning + What made it happen & final success + Major Counts at a glance + Sep’11 Cost : Budget Vs Actual + Duration Schedule Vs Actual

slide-4
SLIDE 4
  • Aligned with business goals
  • Clear, unambiguous and prioritized
  • Measurable, objective and monitored
  • Based on experience , scope, knowledge and

data

  • Aggressive but achievable
  • Deliberated and agreed to key stakeholders

Criteria for T/A Objectives

slide-5
SLIDE 5

+ Make plant safe to operate till next outage. + Improve efficiency & throughput of plant by suitable modification. + Reduce routine maintenance costs + Perform Regulatory Inspection + Increase reliability / availability of equipment during operation + Re-establish Plant Capacity . + Upgrade technology by introducing modern equipment &

Technology

+ Complete corrective /preventive maintenance & project work

Turnaround Objective / Purpose

slide-6
SLIDE 6

Turnaround Objective / Purpose

+ To execute the turnaround with the highest possible

safety record.

+ To achieve the best quality of workman ship. + To complete the turnaround in the shortest possible time. + To complete the turnaround at the lowest possible cost.

+ Revamp Jobs for Refinery capacity augmentation from 14 MMTPA to 18 MMTPA.

  • CDU/VDU/SGU Revamp
  • FCCU Revamp
  • VBU to CDU Conversion Tie-ins.
  • SRU Revamp
  • Train: I integration Tie-ins.
slide-7
SLIDE 7

Turnaround Organization - September 2011

Sr.No. Function Name

1 Head-Refinery C Manoharan 2 Chief Turnaround Manager Narada Singh 3 Overall Operation Co-Ordinator KC Swain 4 Tech.Services Co-Ordinator Satheesan V N 5 Construction Co-Ordinator G G Mehta (EPIL) 6 HSEF Dr Gopal Jayaraman 7 Turnaround manager P Rambabu 8 Turnaround planning Co-Ordinator D D Chaudhari / Jayanti Vagdoda 9 Turnaround-MIS-Co-Ordinator Hembala Dixit 10 Operation Co-Ordinator ISBL: SKM Rahman/Utility: Chitti Babu/PIT/COT: Ajay Veer 11 Engineering & Inspection Ramesh Kumar 12 Revamp/Expansion Project Manager Ramakrishna Paramhans (EPMCL) 13 Revamp/Expansion Execution Manager Sudhir Porichha (EPIL) 14 Overall Tie-ins Co-Ordinator Rakesh Kumar 15 Instrumentation

  • S. Laxminarayan

16 Electrical Rajeev Kumar 17 Civil Ashok Srivastava 18 EPS Dhaval Doshi 19 Security

  • Cmdt. Raghuraman

20 Admin Geojo Paul

21

Reliability/Rotary/ Workshop

Amit Kumar N

22 Commercial J K Jani 23 RSM RSM

slide-8
SLIDE 8

Turnaround Optimisation Program

TR - 0 TR - 1 TR - 2 TR - 3 TR - 4

Strategic Site Turnaround Review Turnaround Work Scope Optimization Planning, Scheduling, and Integrated Plan Basis Integrated Plan Execution Techniques, T/A Management Post Turnaround Review

slide-9
SLIDE 9

.

Turnaround Optimisation Program

TOPTM Overview

Scope Cost Schedule Preparedness Strategic Review Workscope Review Execution Review Preparedness Rev. Close Out Review Ideal Timing Run Cycle (2)

  • 9 months
  • 6 months
  • 3 months

+1 months

slide-10
SLIDE 10

Mission for Shutdown From Chief Turnaround Manager

{S R T C}

  • SAFETY
  • RELIABILITY
  • TIME-BOUND
  • COST-EFFECTIVE
slide-11
SLIDE 11

Turnaround Process / Procedure

+ Collection of all inputs such as previous reports, procurement lead times, job lists, own and contractor resources availability etc + Gathering information from the previous turnaround by way of group discussions, reviewing previous plans and turnaround reports + Finalization of job list and freezed after challenging by experience multi disciplinary Challenging Team + Setting of turnaround run lengths and approximate turnaround duration + Preparation of work scope for next turnaround + Critical review of work scope + Breakdown jobs into specific activities + Review implementation option and resource requirement + Prepare an achievable plan and well integrated level I, II, III schedule

slide-12
SLIDE 12

Turnaround Process / Procedure

+ Procurement of material + Split between the jobs to be carried out by Company personnel and contractor + Contract Planning + Resources for running units + Check the jobs for pre-requisites such as scaffolding, insulation removal, blinds, etc + Pre-shutdown fabrication + Progressive hand over of the execution portion to the field co-ordinators, planners, field engineers, contractor supervisors + Ensure availability of tools and construction equipment + Ensure adequate infrastructure facilities like, labour colony, canteen / space for eating for workman, medical facilities, transportation, drinking water, toilet facility etc…

slide-13
SLIDE 13

Turnaround Process / Procedure

+ Administrative arrangements + Security arrangements + Implementation plans + Monitoring of jobs during execution + Contingency plan for Additional resources required during turnaround + Turnaround close-out

slide-14
SLIDE 14

Pre Shutdown Preparation

+Keep end blinds /spectacles near line flanges as per positive isolation plans indicating required date for readiness on tags. +Keep adequate numbers of Testing Spools, temporary Connections for connecting pressure gauges & drains/vents for testing of Heat Exchangers (Both Shell & Tube side) +Fabrication of Spool Pieces for Heater Pigging Jobs. +Erection of scaffolding wherever possible e.g. For Heat Exchanger, inaccessible Blind locations, control Valve s, safety valves, etc. +Lifting and shifting arrangement for control valves , Safety Valves, etc. +Provision of Power supply points at planned locations e.g. laying of additional cable if any for welding, Hydro jetting and Hydro testing M/C. + Arrangement of temp. lift and Dehumidification at defined locations.

slide-15
SLIDE 15

+Detailing of Scope of work for all S/D Jobs +Preparation of Maintenance Execution Procedure & Work Pack for all

S/D Jobs

+Preparation of TBRA for all Critical S/D activities e.g. Hot jobs,

Modification job, work at height or any other confined space jobs

+Assignment of specific job responsibilities to a group of cross

functional team e.g. team involving Maintenance, Operation, Process, Safety and Inspection

+Engaging Quality & experienced contractors having good track record

  • f executing S/D Jobs in other Refineries to the maximum extent.

Preparedness for Safe & Effective Execution

slide-16
SLIDE 16

+Inclusion of Contract Safety System in Contractor Scope +Arrangement for Pre S/D Training to Contract Manpower +Use of only Certified Tools & Tackles +Use of Flame Arrestor for all Vehicles,Trailors, Crane & Hydra +Tool Box Talk by Engineer to Contract Manpower +Strict Compliance of Safety Work Permit System +Use of General & Specific PPE’s e.g. Life line belt, Fall Arrestor

+Certified Lifting plan for heavy lift

+Certification of Scaffolds & use of “Safe to use” Tag

Preparedness for Safe & Effective Execution

slide-17
SLIDE 17

Facilities and Services (F & S)

1) Contractor office space / working area – Space for contractor’s offices have been provided in the S/D yard. Some of the contractors will have to be located inside the units (from logistic point of view). 2) Canteen facilities for contractor

  • SAB : Own arrangement – Space will be provided by EOL.
  • ECIL : Own arrangement – Space will be provided by EOL.
  • Other contractors: Tea will be served at work place as free of charge to all

the contract labour at 01.00 hr, 4.00 hrs, 7.00 hrs, 10.30 hrs, 15.30 hrs, 16.30 hrs (incl W/s & utility)

  • Two sheds are being constructed. One at shutdown yard, & another tent in old

parking area (tent by admin along with lighting. Power supply by EOL).

  • Required tables, chairs, etc will be arranged by Admin.
  • Lighting arrangement in tin sheds will be provided by elect dept.

3) Canteen facilities for officers:.

  • Location will be at area in between CCB & LAB.
  • Tables, chairs, carpet & lighting is being organized by Admin and power supply

by electrical dept.

slide-18
SLIDE 18

Facilities and Services (F & S)

4) Drinking Water Facilities : 5) Shutdown office: 6) Urinals & Toilets:

  • Sufficient no of toilets and urinals have been constructed in shutdown yard.

7) Resting Place :

  • Separate tents arranged for Dining and Rest room for different contract manpower as well

as for engineer. Near Shutdown yard to avoid manpower movement. 8) First Aid office:

  • Central first aid tent will be located in front of Lab near E-W road. It will be supplemented by

paramedic officer / doctor on round the clock basis and one ambulance. 9) Accommodation for Labour / Transport.

  • Accommodation for 10000 Labours have been booked in Labour colony.
  • For transporting Labours from labour colony to refinery, our trailers will be used and

necessary railing arrangement is being done in our workshop for safety. In addition to this permission will be given for walking from labour gate to workplace on the fixed route. 10) Office space for foreign expatriates: 11 Timing: Working time: 08.00 to 20.00 & 20.00 to 8.00 hrs. Lunch time: 12.30- 13.30 hrs in two batches (30 min break) Dinner: 22.00 to 23.00 hrs In two batches Radiography timing: It will be declared on time to time & followed

slide-19
SLIDE 19

Detailed Shutdown Planning

+Planning started with setting of Milestones for Planning activities +Compilation, discussion and finalization of Job list +Cost Estimation of S/D Jobs, Detail technical study and BOM

preparation for S/D activities, material procurement action

+Preparation of detail scope for awarding the contract +Preparation

  • f

Work packs by

  • perations

and standard maintenance procedures by maintenance

+Finalization of resources, Heavy Equipments, Inspection Plans,

identifying service requirements of technical specialist & expatriate

+Organization of S/D meetings for review, micro detailing and

finalization of overall S/D schedule

slide-20
SLIDE 20

Turnaround Organization - September 2011

Sr.

  • No. Function

Name

1 Head-Refinery C Manoharan 2 Chief Turnaround Manager Narada Singh 3 Overall Operation Co-Ordinator KC Swain 4 Tech.Services Co-Ordinator Satheesan V N 5 Construction Co-Ordinator G G Mehta (EPIL) 6 HSEF Dr Gopal Jayaraman 7 Turnaround manager P Rambabu 8 Turnaround planning Co-Ordinator D D Chaudhari / Jayanti Vagdoda 9 Turnaround-MIS-Co-Ordinator Hembala Dixit 10 Operation Co-Ordinator ISBL: SKM Rahman Utility: Chitti Babu PIT/COT: Ajay Veer 11 Engineering & Inspection Ramesh Kumar 12 Revamp/Expansion Project Manager Ramakrishna Paramhans (EPMCL) 13 Revamp/Expansion Execution Manager Sudhir Porichha (EPIL) 14 Overall Tie-ins Co-Ordinator Rakesh Kumar 15 Instrumentation

  • S. Laxminarayan

16 Electrical Rajeev Kumar 17 Civil Ashok Srivastava 18 EPS Dhaval Doshi 19 Security

  • Cmdt. Raghuraman

20 Admin Geojo Paul 21 Commercial J K Jani 22 RSM RSM

slide-21
SLIDE 21

+ 35 days Turnaround Completed Safely ON SCHEDULE + Turnaround Cost within Budget as per plan. Few

variances due to major exigencies during the Turnaround period.

+ Tie - ins of Train - I new units & facilities with existing

refinery : ISOM, HMU, DHDT, VGO- HT, ARU, SWS, SRU, DCU, & all OSBL/offsite tankages facilities

+ Revamp of existing units for capacity Augmentation has

been completed : CDU & VDU (18MMTPA) & consistently will be able to process high TAN crudes , FCCU (3.7MMTPA) & FCC operation on hydro treated feed, SRU (To Improve the sulphur recovery from 99 to 99.9 wt%). Accomplishments of Turnaround which was completed on schedule in spite of lot of challenges

slide-22
SLIDE 22

+ Total Revamp (modification & reinstallation) completed in

28 engineering days; + World tallest single crude distillation column revamped (77 trays,

90 meter height)

+ Vacuum distillation column revamped (4 bed, 60 meter height &

new vapour horn installation)

+ Major piping modifications & replacement in existing units i.e. CDU

& FCC (dismantling 75,424 inch meter & erection of 85,098 inch meter)

+ Revamp completed- 36 Nos. Exchangers - Modifications/New

exchangers, 7 nos. columns & 6 nos. vessels modification, 6 nos. new ejectors erected in VDU, 29 nos. pumps modification complete & boxed-up, 4 nos. Filters modification, CDU Heater A & B, VDU Heater- A & B revamp/ modifications

Accomplishments of Turnaround which was completed on schedule in spite of lot of challenges

slide-23
SLIDE 23

Turnaround Key Achievement/Highlights

+ FCCU all revamp job completed within schedule without any

incident, this includes Reactor-Riser 2 nos additional Feed nozzle installation, Tie Ins Job 141 nos , Additional Exchanger installation 2 nos along with piping, 6 nos Vessels & 4 nos Pumps modification

+ All Major M & I Job completed within 21 days duration, 36

Column, DHDS reactor catalyst replacement, CCR/NHT Reactor catalyst replacement, FCCU- 6 nos. bellows replacement, Flue gas boiler tube banks replacement, MAB Surface condenser replacement, SRU MCC-1 & 2 major refractory repair, UCT & PCT 10 nos. pumps discharge line replacement, 236 Exchangers, 199 Vessels, All 6 heaters pigging, 16 Heaters maintenance, 102 PCNs (GRM & Reliability related schemes), PCN-Total INCH DIA :28624,Total INCH MTR: 32500,Steel Structure: 103MT

slide-24
SLIDE 24

Turnaround Key Achievement/Highlights

+ 52 Fin fan coolers, Major overhauling of over 50 Compressor/ Turbine/ Pumps. Overhauling of 297 control valves and 551 pressure safety valves, + DCS/ESD up gradation in all the units, + Capital overhauling of 145 motors, 14 Power Transformers, 45 VACUUM circuit Breakers (33 kV), 201 Vacuum circuit Breakers (6.6Kv) 198 LT Circuit Breakers. 108 obsolete relays replaced with High speed Numerical relays, + Bus bar differential protection scheme commissioned at Utility, CCR, FCCU and CDU Electrical Substations, New 33kV switchboard and 6.6 KV switchboard commissioned in CDU and Utility Substations. + Implementation of Fast Bus Transfer scheme at CDU, CCR, FCCU, DHDS, and Utility substations and many other important jobs

slide-25
SLIDE 25

Turnaround Key Learning

  • Temporary Lift was installed at CDU & VDU column,

for movement of light weight materials as well as workmen from ground to column and Vice Versa which remarkably reduced required time frame of execution from 45 days to 35 days and all jobs were smoothly completed in scheduled timeframe. Temporary Lift, installed at CDU / VDU column

slide-26
SLIDE 26

Turnaround Key Learning

  • Dehumidification system provided in CDU & VDU column was

very effective for maintaining comfortable atmosphere inside column for workmen, by maintaining temperature between 28 to 32 deg C & Relative humidity was less than 65% inside the

  • columns. This facility has remarkably contributed in reducing

the time mainly for huge quantum of welding / hot work inside the column. Dehumidification System in CDU & VDU column Dehumidification System for Reactor-Riser

slide-27
SLIDE 27

Turnaround Key Learning

  • New idea of Exchanger cleaning bay has resulted in huge time

saving by providing central Point for Cleaning of all Tube Bundles with advance Hydro jetting machines i.e. Inside/Outside Robotic machines and Inspection (Visual & Eddy Current Testing) was also carried out at same place which helped in good housekeeping and keeping ISBL unit free from Oil, Coking & Sludge and Further reduced House Keeping Job also.

Exchanger Cleaning Bay

slide-28
SLIDE 28

Turnaround Key Learning

  • Robotic Hydrojetting machine made available at exchanger

cleaning bay for Heat Exchangers Tube bundle cleaning, Machine operating with multi jet nozzles–5 nos working simultaneously which took 1/5th times of ordinary manually tube bundle cleaning process, max pressure of 20000 PSI, due to high pressure & mobility of machines the exchanger tube bundle cleaning process was very fast and effective, and hard deposit was removed very easily, thus saving huge time in cleaning huge number of tube bundles

Robotic Tube bundle cleaning Machine

slide-29
SLIDE 29

What made it happen(from 45 to 35 Days

  • Decisive Leadership and on spot decisions.
  • Micro level Turnaround planning started well in advance before 18 months for

man, material , machines, job list and its work pack.

  • Defined all critical jobs :

1. CDU/VDU column Revamping. a. We treat contract manpower as our employee and provide all the facilities like Accommodations/Food/Transport/Medical/Water/Tea-Snacks at site

  • nly.

b. Use of new concepts and modernized gadgets e.g. providing lifts as high as 90 Meters, Dehumidification /AC, Chemical decontamination etc. c. Maximizing the pre turnaround activities e.g. 90% scaffolding, issuing of 100% bulk material/ spares and its prefabrication/ machining and placing in position. d. Daily Review and making rolling plan for speedy execution. e. Timely supply of equipment and logistics arrangements

slide-30
SLIDE 30

What made it happen(from 45 to 35 Days)

2. CDU/VDU Heater Modification. a. Optimise the use of Pigging machines in such a way that critical Heater handed over with in minimum possible durations. b. Use of new concepts and modernized gadgets e.g.SAF RAD Radiographic machines so that other jobs can be continued. c. Heater jobs divided in multiple zones so that welding jobs can be performed at maximum locations at a time and saved lot of time. d. Keep standby manpower for critical activities so that job shuld not suffer at any cost. 3. FCCU Reactor Refractory repairing:

  • a. Providing of Dehumidification /AC.
  • b. Using SAF RAD Radiographic machines,Diamond cutter for refractory,

electrical and instrument testing equipment etc. c. Using of skilled manpower and guidance from Refractory experts. d. Ensures Support services like inspection/process availability 24X7 on the job.

slide-31
SLIDE 31

What made it happen(from 45 to 35 Days)

  • Decisive Leadership and on spot decisions.
  • Micro level Turnaround planning started well in advance before 18 months for

man, material , machines, job list and its work pack.

  • Defined all critical jobs :

1. CDU/VDU column Revamping. a. We treat contract manpower as our employee and provide all the facilities like Accommodations/Food/Transport/Medical/Water/Tea-Snacks at site

  • nly.

b. Use of new concepts and modernized gadgets e.g. providing lifts as high as 90 Meters, Dehumidification /AC, Chemical decontamination, Inside/Outside Robotic Hydro jetting, SAF RAD Radiographic machines, powered torqueing/tensioning machines, Diamond cutter for refractory, Ultra-modern rotary laser based condition monitoring, electrical and instrument testing equipment etc. c. Maximizing the pre turnaround activities e.g. 90% scaffolding, issuing of 100% bulk material/ spares and its prefabrication/ machining and placing in position. d. Timely supply of equipment and logistics arrangements

slide-32
SLIDE 32
  • Engaged best contractor and resources and skilled/ specialized man
  • power. Optimum deployment & effective utilization of resources
  • Organization of Turnaround meetings for review, micro detailing and

finalization of overall Turnaround schedule.

  • Compliance of Systems and Procedures, Strong belief in team work,

motivation and support from Top Management.

  • Caring of the Employees and Workmen resulted in excellent overall

productivity.

  • All disciplines viz- Maintenance, Operation, TS/Process, Inspection,

Expansion, HSEF, Security, Project/Engg, HR, CRG, IT, Warehouse, Commercial, Finance and Administration have demonstrated tireless effort and cohesive work culture towards achieving Turnaround goal.

What made it happen(from 45 to 35 Days)

slide-33
SLIDE 33

The Success : 100% Planned jobs completed along with last minute surprises

  • It is worth highlighting that not only 100% planned jobs

have been completed effectively but many important jobs came at last moment which could be also completed within this Turnaround period.

  • Last minute surprises and exigencies were also handled

effectively- CCR Recycle gas compressor major maintenance due to high vibrations, DHDS Recycle gas compressor unplanned overhauling due to coking in rotor, Damage of 4th Bed layers of packing in VDU column, Shifting of HP steam line from support, Last moment receipt

  • f CDU/VDU heater tubes & prefabrication, Cracks in CDU

Heater supports and many more……., created a huge pressure.

slide-34
SLIDE 34

Turnaround Sep’11 : Major counts at a Glance

Total Turnaround duration 35 days Total engineering duration 26 days Total no of blinds provided for plant handover 3924 Nos Turnaround Budget 74.66 Cr Turnaround Expenditure 74.69 Cr Major Contractor involved 70 Nos Turnaround Manpower (Officer + Workman+ OEM Experts) 15000 Nos Essar Officers (In 12hrs Shift Rota) 846 Nos OEM & Expatriate 20 & 5 Nos Cranes (250T,200T,150T ,135T,130T,120T,110T,100T& 60T) 57 Nos Hydra 39 Nos Fork Lift 10 Nos Trailer 33 Nos Exchanger tube bundle pullers 05 nos Hydro-jetting machines 26 Nos Hydro-testing machines 50 Insitu Machining sets 12 Rotomol cleaning machine 2 Stress relieving machine 20 Air compressors 09 Nos Pigging machine 06 Nos Hydraulic torque tightening m/c 12 Transformer oil filtration machine 3 Heating oven for motors 2 nos Transformer oil heating and vacuum m/c 3 Mobile lighting tower 2 nos Fire Blankets 3500 Nos Total no. of Revamp Major jobs executed 1618 Nos Total no. of Major M&I jobs executed 2492 Nos

slide-35
SLIDE 35

Turnaround Sep’11 Cost : Budget Vs Actual

Sr. No. Description Budget- Material cost Budget- Service cost Total Budget ( Material+ Service) cost

Actual Material Cost

Actual Service s Cost Total ( Actual)

Justification

A Mechanical/Operations (Sub total) 15.86 40.10 55.96

18.49 35.79

54.63 B Electrical 2.52 2.22 4.74

2.01 1.90 3.91

C Instrument 2.99 0.99 3.98

1.64 1.26 2.90

D Civil 0.50 2.99 3.49

1.70 5.58 7.27

Additional Job of Sea water intake well inside painting, Repairing and Chemical resisting coating in pump house basin of Sea water supply reservoir, CDU /VDU heater main flue gas duct to stack cleaning & inspection, Insulation, Scaffolding

E Inspection 1.80 1.80

0.00 1.53 1.53

F Fire & Safety 0.30 0.35 0.65

0.37 0.18 0.55

G Admin & Canteen facilities, Vehicles, OHC & IT 0.00 1.51 1.51

0.09 2.34 2.43

H Maintenance supervisor/Engineers hiring 0.00 2.53 2.53

0.00 1.47 1.47 Total shutdown Budget (in

crores). (Addition of A to H)

22.17 52.48 74.66 24.30 50.04 74.69 TOTAL COST (Rs in Cr.)

74.66 73.96

Rs in Cr.

slide-36
SLIDE 36

Turnaround Duration Schedule Vs Actual

UNIT PLANNED STOPPAGE DATE & TIME ACTUAL FEED CUT OFF STOPPAGE DATE & TIME PLANNED START- UP DATE & TIME ACTUAL FEED CUT IN START UP DATE & TIME CDU/VDU/S GU

18/09/11 & 08:00 hrs 18/09/11 & 04:45 hrs 23/10/11 & 08:00 hrs 24/10/11 & 11:08 hrs

VBU

19/09/11 & 02:00 hrs 19/09/11 & 00:30 hrs 24/10/11 & 08:00 hrs 24/10/11 & 19:15 hrs

TREATERS

20/09/11 & 08:00 hrs 19/09/11 & 00:30 hrs 23/10/11 & 08:00 hrs 23/10/11 & 18:00 hrs

FCCU

19/09/11 & 08:00 hrs 19/09/11 & 09:10 hrs 23/10/11 & 08:00 hrs 23/10/11 & 10:25 hrs

NHT

18/09/11 & 20:00 hrs 18/09/11 & 21:15 hrs 22/10/11 & 08:00 hrs 23/10/11 & 16:35 hrs

CCR

18/09/11 & 20:00 hrs 18/09/11 & 21:35 hrs 21/10/11 & 08:00 hrs 27/10/11 & 05:25 hrs

DHDS

18/09/11 & 20:00 hrs 18/09/11 & 20:00 hrs 24/10/11 & 08:00 hrs 29/10/11 & 16.00 hrs

ARU

21/09/11 & 08:00 hrs 19/09/11 & 09:00 hrs 23/10/11 & 08:00 hrs 23/10/11 & 21:00 hrs

SWS

21/09/11 & 12:00 hrs 21/09/11 & 08:15 hrs 23/10/11 & 08:00 hrs 24/10/11 & 04:00 hrs

SRU train-1 20/09/11 & 08:00 hrs 19/09/11 & 06:45 hrs

23/10/11 & 08:00 hrs 28/10/11 & 19:10 hrs

SRU train-2 20/09/11 & 08:00 hrs 18/09/11 & 09:00 hrs

23/10/11 & 08:00 hrs 31/10/11 & 12:00 hrs

UTILITY- UCT

29/09/11 & 08:00 hrs 27/09/11 & 17:00 hrs 11/10/11 & 08:00 hrs 13/10/11 & 16:00 hrs

UTILITY- PCT

26/09/11 & 08:00 hrs 25/09/11 & 00:00 hrs 13/10/11 & 08:00 hrs 15/10/11 & 10:00 hrs

H2S Flare

26/09/11 & 08:00 hrs 26/09/11 & 11:30 hrs 14/10/11 & 08:00 hrs 15.10.11 & 18.45 Hrs

HC Flare

30/09/11 & 08:00 hrs 26/09/11 &11:30 hrs 15/10/11 & 08:00 hrs 12/10/11 & 20:30 hrs

N2 Plant

01/10/11 & 08:00 hrs 06/10/11 &18:00 hrs 05/10/11 & 08:00 hrs 15/10/11 & 06:00 hrs

Steam

01/10/11 & 08:00 hrs 04/10/11 &08:30 hrs 05/10/11 & 08:00 hrs 10/10/11 & 09:00 hrs

slide-37
SLIDE 37

THANK K YOU OU