ESSNUSB REQUIREMENTS ON ESS LINAC
Mamad Eshraqi 2017 Sep 28 NuFACT
1
ESS NU SB R EQUIREMENTS ON ESS LINAC Mamad Eshraqi 2017 Sep 28 - - PowerPoint PPT Presentation
ESS NU SB R EQUIREMENTS ON ESS LINAC Mamad Eshraqi 2017 Sep 28 NuFACT 1 T OP L EVEL P ARAMETERS Key Linac parameters: Design Drivers: Energy 2.0 GeV High average beam power 5MW Current 62.5 mA High peak beam power 125 MW
Mamad Eshraqi 2017 Sep 28 NuFACT
1
NuFACT 2017 Uppsala 2017 Sep 28
Design Drivers: High average beam power 5MW High peak beam power 125 MW High availability >95 % Key Linac parameters: Energy 2.0 GeV Current 62.5 mA Repetition rate 14 Hz Pulse length 2.86 ms Losses <1W/m Ions p Flexible/Upgradable design Minimize energy consumption
Spokes Medium β High β DTL MEBT RFQ LEBT Source
HEBT & Contingency
Target
2.4 m 4.6 m 3.8 m 39 m 56 m 77 m 179 m
75 keV 3.6 MeV 90 MeV 216 MeV 571 MeV 2000 MeV
352.21 MHz 704.42 MHz
First proton beams ready in 2019, User operation planned for 2023
NuFACT 2017 Uppsala 2017 Sep 28
NuFACT 2017 Uppsala 2017 Sep 28
NuFACT 2017 Uppsala 2017 Sep 28
NuFACT 2017 Uppsala 2017 Sep 28
4.6 m 4.0 m
L E B T
Source
2.4 m
75 keV
MEBT RFQ
3.6 MeV LEBT
Source DTL
39 m
90 MeV
DTL
39 m
90 MeV
4.0 m MEBT 4.6 m
LEBT Source
2.4 m
75 keV
RFQ
MEBT
RFQ
3.6 MeV
LEBT Source
X.X keV
NuFACT 2017 Uppsala 2017 Sep 28
Spokes Medium β High β DTL MEBT RFQ LEBT Source
HEBT & Contingency
Target
2.4 m 4.6 m 3.8 m 39 m 56 m 77 m 179 m
75 keV 3.6 MeV 90 MeV 216 MeV 561 MeV 2000 MeV
352.21 MHz 704.42 MHz
Proton beam shape H- beam shape
entrance/exit).
NuFACT 2017 Uppsala 2017 Sep 28
CERN LINAC4) with a maximum duty cycle of 10%.
10% would permit using the same DTL.
for increased duty cycle
limit.
NuFACT 2017 Uppsala 2017 Sep 28
13 × Spoke
ESS Spoke cryomodule with two double spoke cavities, and two power couplers
NuFACT 2017 Uppsala 2017 Sep 28
ESS elliptical cryomodule with four 6-cell cavities and four power couplers for up to ~1.1 MW peak RF power.
59 mm
9 × Mβ 21 × Hβ
NuFACT 2017 Uppsala 2017 Sep 28
rates (maybe not?).
Cryo line
Wave guide
possibility of active cooling Sized for cool-down
NuFACT 2017 Uppsala 2017 Sep 28
Capacitors and transformers
High voltage
power by increasing the size of capacitor charger.
add the extra capacitor chargers.
additional capacitor chargers in the gallery.
Thanks to Carlos Martins
NuFACT 2017 Uppsala 2017 Sep 28
(Klystrons could? be operated at a maximum of 10% RF DC).
This requires early knowledge of such a need.
increased pressure.
utility restrictions
NuFACT 2017 Uppsala 2017 Sep 28
HEBT, Magnet doublets are designed and built in Elettra. 12 periods, identical length to HB cryomodules A2T (DogLeg), Magnets are designed and built in Elettra. 6 periods, achromat. A2T Quadrupoles doublets are designed and built in Elettra, and Raster magnets are designed and built in Aarhus University
12 × Contingency
NuFACT 2017 Uppsala 2017 Sep 28
HB2016 TUAM3Y01 PRL 108, 114801 (2012)
NuFACT 2017 Uppsala 2017 Sep 28
ring requires a high frequency chopping in the linac, which could excite HOMs in the SC cavities.
NuFACT 2017 Uppsala 2017 Sep 28
P P H- H- P P
H- H-
28 Hz
H-
56 Hz
P P
56 Hz
H
H- H- H-
P P
28 Hz (rf)
H
but still much shorter than the filling time of cavities
NuFACT 2017 Uppsala 2017 Sep 28
being discussed for the additional 5 MW:
๏ 28 Hz:
✴
14 Hz for neutron production + 14 Hz for neutrino production (5 MW to each destination)
๏ 56 Hz:
✴
14 Hz for neutron production + 42 Hz for neutrino production (5 MW to each destination)
๏ With the energy upgrade to 2.5 GeV the increase of average power needed from the nominal Radio Frequency (RF)
stations is ~60%, which looks feasible within the existing RF gallery space.
๏ An energy upgrade to 3 GeV would further decrease the need for higher RF power from the existing stations to
~30%.
8%:
๏ 28 Hz yields an RF duty cycle of 8.4% ๏ 56 Hz yields an RF duty cycle of 9.45%
Extracted from the report by Frank Gerigk and Eric Montesinos, CERN-ADD-NOTE-2016-0050
NuFACT 2017 Uppsala 2017 Sep 28
Spokes Medium β High β DTL MEBT RFQ LEBT Source
HEBT & Contingency
Target
2.4 m 4.6 m 3.8 m 39 m 56 m 77 m 179 m
75 keV 3.6 MeV 90 MeV 216 MeV 571 MeV 2000 MeV
352.21 MHz 704.42 MHz
RF (Modulators, SSA, Tubes), LLRF Beam physics (Halo, losses) SC cavities (couplers, cavities)
H- source
Operations, Reliability, Availability
NuFACT 2017 Uppsala 2017 Sep 28
IS+LEBT RFQ MEBT DTL Spoke Medium beta High beta New device
New ~New ~New — — — —
Cooling
— Additional Additional Additional Additional Additional Additional
Tunnel
Device capacity / pipes / temperature Cryo-line/Cryomodule/Coupler/Waveguide
Gallery
Cooling skids / Klystron cooling / pipes Klystron cooling / pipes / skids?
RF
— Additional Additional Additional Additional Additional Additional Klystron Amplifier Klystron Klystrons / Tubes/LLRF Modulator PC Modulator Modulator / Power converters
Cryo
— — — — Additional Additional Additional Cryoline / Cryo plant
NuFACT 2017 Uppsala 2017 Sep 28
repetition rate and higher beam energy are (in no particular order):
New HV cables between the substations and the modulators in the RF gallery.
the modular design developed in-house is adopted.
addition of 5 MW H- acceleration capability in the current state of the ESS linac.
Extracted from the report by Frank Gerigk and Eric Montesinos, CERN-ADD-NOTE-2016-0050