ERO Enterprise Effectiveness Survey Update
Kristin Iwanechko, Associate Director, Regional and Stakeholder Relations Member Representatives Committee Meeting November 5, 2019
ERO Enterprise Effectiveness Survey Update Kristin Iwanechko, - - PowerPoint PPT Presentation
ERO Enterprise Effectiveness Survey Update Kristin Iwanechko, Associate Director, Regional and Stakeholder Relations Member Representatives Committee Meeting November 5, 2019 Background Survey issued July 2018 Report of results and
ERO Enterprise Effectiveness Survey Update
Kristin Iwanechko, Associate Director, Regional and Stakeholder Relations Member Representatives Committee Meeting November 5, 2019
RELI ABI LI TY | ACCOUNTABI LI TY 2
Background
RELI ABI LI TY | ACCOUNTABI LI TY 3
ensuring efficiencies and minimizing duplication (e.g., Align, availability data systems, stakeholder engagement efforts)
centers of excellence around certain practice areas
Monitoring and Enforcement action plans
ERO Enterprise Principles
RELI ABI LI TY | ACCOUNTABI LI TY 4
grading metric, and public comment periods during standard drafting
comprehensive compliance and enforcement cost-impact measures into the PR template or team analysis
Reliability Standards Development
RELI ABI LI TY | ACCOUNTABI LI TY 5
Compliance Monitoring
summaries and the CMEP Implementation Plan
upcoming workshops
Compliance Monitoring and Enforcement
RELI ABI LI TY | ACCOUNTABI LI TY 6
Compliance Enforcement
completion
Compliance Monitoring and Enforcement (continued)
RELI ABI LI TY | ACCOUNTABI LI TY 7
degrees of required details or assistance
controls around information sharing to improve trust
portal
E-I SAC
RELI ABI LI TY | ACCOUNTABI LI TY 8
Executive Committee
Next Survey
RELI ABI LI TY | ACCOUNTABI LI TY 9
RELI ABI LI TY | RESI LI ENCE | SECURI TY
Reliability and Security Technical Committee
Jennifer Sterling, MRC Vice Chair MRC Meeting November 5, 2019
RELI ABI LI TY | RESI LI ENCE | SECURI TY 2
Technical Committee (RSTC)
and task forces and eliminate or combine those without recurring responsibilities Potential Committee Structures – Option 2
NERC Board
Operating Committee OC Subcommittees, Working Groups, Task Forces Planning Committee Critical Infrastructure Protection Committee PC Subcommittees, Working Groups, Task Forces CIPC Subcommittees, Working Groups, Task ForcesNERC Board
OC Subcommittees, Working Groups, Task Forces Reliability and Security Technical Committee PC Subcommittees, Working Groups, Task Forces CIPC Subcommittees, Working Groups, Task ForcesRELI ABI LI TY | RESI LI ENCE | SECURI TY 3
vice chair for appointment by the Board (November meeting). Both are for two-year terms
the annual election, any unfilled seats will become At Large until the term expires
Large Nominating process with Nominating Subcomittee as shown in proposal document (above)
Revisions to Proposal
RELI ABI LI TY | RESI LI ENCE | SECURI TY 4
approximately half of the members for two-year terms and half for a three-year term
approximately half of Sector and At Large terms expiring annually
membership at the first RSTC meeting
each RE’s area and each Interconnection
from the RSTC membership Revisions to Proposal
RELI ABI LI TY | RESI LI ENCE | SECURI TY 5
Participation Model - Revised
Name Voting Members Sectors 1-10, and 12 22 At Large 10 Chair and Vice Chair 2 Total 34 Non-Voting Member Number of Members NERC Secretary 1 U.S. Federal Government 2 Canadian Federal Government 1 Provincial Government 1 Total 5
RELI ABI LI TY | RESI LI ENCE | SECURI TY 6
Transition Plan Highlights
Transition Plan; if approved, appoints chair and vice chair
will conduct Sector elections, if necessary, by December 20, 2019
by At Large members
At Large nominees for presentation to the Board
RELI ABI LI TY | RESI LI ENCE | SECURI TY 7
Transition Plan Highlights
Large). Terms will expire in June of alternating years following the initial terms with the initial term being two or three years, and thereafter two year terms
work plans for RSTC and subcommittees
The RSTC will meet March 4, 2020 for the inaugural RSTC meeting
approvals and to complete any other approvals. The RSTC will hold initial regular meeting with subcommittee reports and other agenda items
RELI ABI LI TY | RESI LI ENCE | SECURI TY 8
Future Work
Policy Input for potential implementation plan enhancements
leadership on transition plan details
RELI ABI LI TY | RESI LI ENCE | SECURI TY 9
RELI ABI LI TY | RESI LI ENCE | SECURI TY
ERO Enterprise Long-Term Strategy Update
Jim Robb, President and CEO Member Representatives Committee Meeting November 5, 2019
RELI ABI LI TY | RESI LI ENCE | SECURI TY 2
ARE WE
HERE?
Why We Exist
RELI ABI LI TY | RESI LI ENCE | SECURI TY 3
The ERO Enterprise Golden Circle
RELI ABI LI TY | RESI LI ENCE | SECURI TY 4
Strategic Focus Areas 1. Expand risk-based focus in all Standards, Compliance Monitoring, and Enforcement programs 2. Assess and catalyze steps to mitigate known and emerging risks to reliability and security 3. Build a strong, E-ISAC-based security capability 4. Strengthen engagement and collaboration across the reliability and security ecosystem in North America 5. Capture effectiveness, efficiency, and continuous improvement opportunities
RELI ABI LI TY | RESI LI ENCE | SECURI TY 5
Stakeholder Comments
report
resilience
RELI ABI LI TY | RESI LI ENCE | SECURI TY 6
Next Steps
additional inputs from ERO Enterprise leadership
input and support
December 14, 2019, conference call
RELI ABI LI TY | RESI LI ENCE | SECURI TY 7
RELI ABI LI TY | RESI LI ENCE | SECURI TY
Supply Chain Risk Assessment
Howard Gugel, Vice President of Engineering and Standards Member Representatives Committee Meeting November 5, 2019
RELI ABI LI TY | RESI LI ENCE | SECURI TY 2
transition)
Board Resolution
RELI ABI LI TY | RESI LI ENCE | SECURI TY 3
System (BES) Cyber Systems
Recommendations from Study
RELI ABI LI TY | RESI LI ENCE | SECURI TY 4
Data Request I ssued
RELI ABI LI TY | RESI LI ENCE | SECURI TY 5
BES Cyber Assets
*
* ERC = External Routable Connectivity
RELI ABI LI TY | RESI LI ENCE | SECURI TY 6
BES Cyber Assets
RELI ABI LI TY | RESI LI ENCE | SECURI TY 7
BES Cyber Assets with Medium and High
RELI ABI LI TY | RESI LI ENCE | SECURI TY 8
BES Cyber Assets with Lows Only
RELI ABI LI TY | RESI LI ENCE | SECURI TY 9
BES Cyber Assets with Medium and High
RELI ABI LI TY | RESI LI ENCE | SECURI TY 10
BES Cyber Assets with Lows Only
RELI ABI LI TY | RESI LI ENCE | SECURI TY 11
BES Cyber Assets with Medium and High
RELI ABI LI TY | RESI LI ENCE | SECURI TY 12
BES Cyber Assets with Lows Only
RELI ABI LI TY | RESI LI ENCE | SECURI TY 13
impact assets
access
substations allow third party access Observations
RELI ABI LI TY | RESI LI ENCE | SECURI TY 14
ERCOT Summer 2019 Update
DeAnn Walker Chairman Public Utility Commission of Texas Bill Magness President & CEO ERCOT November 5, 2019
2
The interconnected electrical system serving most of Texas, with limited external connections
load; 75% of Texas land
August 12, 2019
transmission lines
(excluding PUNs)
ERCOT connections to other grids are limited to ~1,250 MW of direct current (DC) ties, which allow control over flow of electricity
The ERCOT Interconnection
Western Interconnection Includes El Paso and Far West Texas Eastern Interconnection Includes portions of East Texas and the Panhandle region 600 MW with SPP 30 MW with CENACE at Eagle Pass 100 MW with CENACE at Laredo 300 MW with CENACE at McAllen 220 MW with SPP ERCOT InterconnectionUnique Aspects of the ERCOT Interconnection
reliability (through NERC) and state policy for market design and resource adequacy.
by the Texas Legislature; implemented and enforced by the Public Utility Commission of Texas (PUCT).
common interest among the regions in Texas.
settled rules. For a colorful history, see: Richard D. Cudahy, “The Second Battle of the Alamo: The Midnight Connection,” Natural Resources & Environment (American Bar Association) (Summer 1995).
3
Market Structure in ERCOT
merchant competitors companies (except for municipal and cooperative units
serve load
distribution lines and related facilities are owned and
utilities.
regulated by PUCT.
recovered on “postage stamp” basis
consumers’ electric load in ~75% of state (except 25% in municipal and cooperative utility areas)
The ERCOT market operates based on a structure established by 1999 Texas legislation:
4
Resource Adequacy in the ERCOT Market
– Reserve margins may fluctuate significantly based on market entry and exit – PUCT and ERCOT are studying methods of measuring reserve margins that take into account market dynamics
– ERCOT’s energy-only market includes a $9,000 MWh offer cap, along with an Operating Reserve Demand Curve (ORDC) triggered by scarcity conditions
– The economic consequences of scarcity pricing provide extremely strong incentives for generator performance – Price-responsive demand is key to the optimal functioning of the market
5
Market Design: Energy-Only Nodal Market
Ancillary Services procured in DAM and co-
minutes, using generation with the lowest offers to serve the load
– Supply and demand-side reserves – Reliability-Must-Run contracts for retirements that threaten system reliability
.
6
Texas Consumes More Electricity Than Any State
7
Consistent Load Growth in ERCOT (2008-2018)
8
Current Demand Records
9
Peak Demand Record: 74,666 megawatts (MW)*
Weekend Peak Demand Record: 71,915 MW*
Winter Peak Demand Record:
65,915 MW
Monthly Peak Demand Records
January: 65,915 MW (Jan. 17, 2018) February: 57,265 MW (Feb. 10, 2011) March: 60,756 MW (March 5, 2019) April: 53,486 MW (April 28,2017) May: 67,265 MW (May 29, 2018) June: 69,123 MW (June 27, 2018) July: 73,473 MW (July 19, 2018) August: 74,666 MW (Aug. 12, 2019)* September: 68,817 MW (Sept. 6, 2019)* October: 65,066 MW (Oct. 2, 2019) November: 56,317 MW (Nov. 14, 2018) December: 57,932 MW (Dec. 19, 2016)
*New records are preliminary, subject to change in final settlementERCOT Installed Capacity (1999-2018)
10
Wind and solar values are based on nameplate capacity (not adjusted for peak capacity contribution) 4.8% 51.6% 0.3% 35.4% 12.1% 21.4%The Summer 2019 Seasonal Assessment of Resource Adequacy (SARA) Values vs. Actuals at Peak Demand
11
Largest absolute difference2019 Actual Peak Demand (8/12/19) Final 2019 Summer SARA* Difference
Total Resources, MW 80,098 78,930 1,168 Thermal and Hydro 64,401 65,526 (1,125) Private Use Networks, Net to Grid 3,203 3,437 (234) Switchable Generation Resources 2,837 2,726 111 Wind Capacity Contribution 7,447 4,898 2,549 Solar Capacity Contribution 1,394 1,405 (11) Non-Synchronous Ties 816 938 (122) Peak Demand, MW 74,666 74,853 (187) Reserve Capacity, MW 5,432 4,077 1,355 Total Outages, MW 3,972 4,226 (254) Capacity Available for Operating Reserves, MW 1,460 (149) 1,609
**11
Source: Final 2019 Summer SARA *The totals for the Final 2019 Summer SARA column combine multiple rows into a single row in some cases. (E.g., already in-service Thermal and Hydro Resources with planned Thermal and Hydro Resources). **The outage information in this table was extracted on Sept. 16, 2019.Closer Look at Peak Demand Day of Aug. 12
12
2 4 6 8 10 12 14 16 18 10 20 30 40 50 60 70 80 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Wind Output (GW) Power (GW) Delivery Hour Nuclear Coal Gas Traditional Simple Cycle Combined Cycle Wind Solar Diesel Hydro Renewables Total Dispatch Wind Output
ERCOT “Peak” HoursTiming of Peak Load and Peak Net Load (Load - IRR)
13
12:00 13:00 14:00 15:00 16:00 17:00 18:00 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 June July August Hour Max Load Time Max Net Load TimeLoad, Wind, and Outage Differences – 8/12-8/13
14
Outages Shown are non-IRR Outages 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 10,000 65,000 66,000 67,000 68,000 69,000 70,000 71,000 72,000 73,000 74,000 75,000 8/12/2019 8/13/2019 8/14/2019 8/15/2019 8/16/2019 Wind and Outages (MW) Load (MW) Load Wind OutagesAt Time of Lowest Reserves
14:51 15:14 17:47 15:20 15:18Load, Wind, and Outage Differences – 8/12-8/15
15
1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 10,000 65,000 66,000 67,000 68,000 69,000 70,000 71,000 72,000 73,000 74,000 75,000 8/12/2019 8/13/2019 8/14/2019 8/15/2019 8/16/2019 Wind and Outages (MW) Load (MW) Load Wind OutagesAt time of lowest reserves
15:20 14:51 15:14 15:18 17:47 Outages shown are non-IRR outagesLoad Patterns – 13:00-20:00 on 8/12-8/16
16
8/12 (Peak) 8/13 (EEA) 8/14 8/15 (EEA) 8/16 64000 66000 68000 70000 72000 74000 76000 12 13 14 15 16 17 18 19 MW Hour 8/12 (Peak) 8/13 (EEA) 8/14 8/15 (EEA) 8/16Deployment
17 Deployment Instruction Recall Instruction Start Sustained Response Period
Peak Week: Wholesale Prices and Load (2 to 6 p.m.)
18
64000 66000 68000 70000 72000 74000 76000 $- $1,000 $2,000 $3,000 $4,000 $5,000 $6,000 $7,000 $8,000 $9,000 $10,000 8/12/2019 14:00:13 8/12/2019 14:25:08 8/12/2019 14:45:09 8/12/2019 15:10:12 8/12/2019 15:35:13 8/12/2019 16:00:16 8/12/2019 16:17:19 8/12/2019 16:40:12 8/12/2019 17:05:13 8/12/2019 17:30:12 8/12/2019 17:55:13 8/13/2019 14:20:12 8/13/2019 14:40:12 8/13/2019 15:05:11 8/13/2019 15:30:14 8/13/2019 15:55:13 8/13/2019 16:20:14 8/13/2019 16:45:15 8/13/2019 17:10:14 8/13/2019 17:35:14 8/14/2019 14:00:15 8/14/2019 14:25:11 8/14/2019 14:50:10 8/14/2019 15:15:09 8/14/2019 15:40:14 8/14/2019 16:05:12 8/14/2019 16:30:14 8/14/2019 16:55:13 8/14/2019 17:20:12 8/14/2019 17:40:11 8/15/2019 14:05:09 8/15/2019 14:30:10 8/15/2019 14:50:12 8/15/2019 15:10:11 8/15/2019 15:30:15 8/15/2019 15:55:14 8/15/2019 16:20:13 8/15/2019 16:37:11 8/15/2019 16:55:13 8/15/2019 17:20:13 8/15/2019 17:45:12 8/16/2019 14:10:12 8/16/2019 14:35:12 8/16/2019 15:00:16 8/16/2019 15:25:12 8/16/2019 15:50:14 8/16/2019 16:15:12 8/16/2019 16:40:11 8/16/2019 17:05:12 8/16/2019 17:30:13 8/16/2019 17:55:13 Wholesale Market Price Load EEA Level 1Operating Notices Issued in June – September 2019
19
– 2 request during August EEAs and 1 for Operating Days 9/5 and 9/6
– 2 system-wide notices, for Operating Days 8/13-8/21 and Operating Days for 9/5-9/6 – 1 notice for Permian Basin units for Operating Days beginning 9/25
6/01 6/03 6/05 6/07 6/09 6/11 6/13 6/15 6/17 6/19 6/21 6/23 6/25 6/27 6/29 7/01 7/03 7/05 7/07 7/09 7/11 7/13 7/15 7/17 7/19 7/21 7/23 7/25 7/27 7/29 7/31 8/02 8/04 8/06 8/08 8/10 8/12 8/14 8/16 8/18 8/20 8/22 8/24 8/26 8/28 8/30 9/01 9/03 9/05 9/07 9/09 9/11 9/13 9/15 9/17 9/19 9/21 9/23 9/25 9/27 9/29Operating Notices in June - September
Conservation PRC < 2500 OCN PRC < 3000 TCEQ EEA1EEA1Key Observations for Summer 2019
September was well above normal. Based on mean temperature, June – September 2019 ranks as the 4th hottest summer on record in Texas.
peak demand (the peak net load).
patterns.
20
Andy Dodge Director, Office of Electric Reliability Federal Energy Regulatory Commission November 5, 2019
The views expressed in this presentation are my own and do not represent those of the Commission or any individual CommissionerStaff Report on Lessons Learned from Commission-Led CIP Reliability Audits
entities that completed in fiscal year 2019
compliance with CIP Reliability Standards as well as their overall cybersecurity posture
bulk electric system cyber systems associated with transmission facilities;
required training and that the training records are properly maintained
firewall access control rules in use
2
FERC/NERC Staff White Paper on CIP Standards Notices of Penalties
information in NOPs for violations of CIP standards
Reliability Standards while protecting sensitive information, White Paper proposes that:
were violated, and amount of penalties assessed
and potential vulnerabilities to cyber system
3
Technical Conference on Managing Transmission Line Ratings
headquarters
dynamic line ratings (DLRs) and ambient-adjusted line ratings (AARs), exploring which transmission line rating and related practices might constitute best practices, and what, if any, Commission action in these areas might be appropriate
4
Observations from Transmission Line Ratings Tech Conference
November 16
5
Grid-Enhancing Technologies Workshop
headquarters
neutral and should account for both hardware and software that increases the capacity of the transmission system, apart from a new transmission line or substation
transmission facilities
equipment, storage technologies, and advanced line rating methodologies
6
Compliance Filings on Storage Rule
PJM and SPP generally complied with the rule by:
services in the same manner as other resources
resources
within 60 days
run-time requirements for resource adequacy and capacity, with filings due no later than 45 days after publication in Federal Register
7
8