Environment Louise Kleynhans KOPANANG MINE CONTINUOUS REAL TIME - - PowerPoint PPT Presentation

environment
SMART_READER_LITE
LIVE PREVIEW

Environment Louise Kleynhans KOPANANG MINE CONTINUOUS REAL TIME - - PowerPoint PPT Presentation

Occupational Environment Louise Kleynhans KOPANANG MINE CONTINUOUS REAL TIME MONITORING 1 2 Contents Background Description of practice Effectiveness of engineering controls Schematic layout The monitor Project phases


slide-1
SLIDE 1

CONTINUOUS REAL TIME MONITORING KOPANANG MINE

Occupational Environment Louise Kleynhans

1

slide-2
SLIDE 2

2

Contents

 Background  Description of practice  Effectiveness of engineering controls  Schematic layout  The monitor  Project phases  The problem area  Results before and after  Pre- and post strategy  Benefits/Advantages  Key lessons learnt  Introduction of Dust Task Team  Vision

slide-3
SLIDE 3

3

  • In 2011 Kopanang Gold Mine was selected as the SOURCE

MINE for Continuous Real time Monitoring of Airborne Pollutant Engineering Controls

  • The project was a huge success and documented as the

“MOSH Leading Practice that will make a difference”

  • Kopanang Mine is still using this practice daily to monitor the

effectiveness our of Engineering Controls

Background

slide-4
SLIDE 4

4

  • Following an identification process on the shaft, continuous

monitors were placed on the intake air and direct return air side of an engineering control.

Baseline

  • The ambient air condition is then monitored continuously in

real-time and transmitted to a surface control room.

Monitor

  • Should a “dust alarm” occur the control room operator will

initiate a call out procedure to investigate the alarm.

Alarm

  • Following investigation, an action log will be put in place to

rectify the condition thereby preventing people to be over- exposed to harmful dust concentrations.

Action

Description of practice

slide-5
SLIDE 5

5

Engineering controls - effectiveness

Efficiency

The efficiency of engineering controls are normally dependant on the human factor

The strategy indicated a need to:

  • test the effectiveness of the engineering controls
  • determine whether current engineering controls are

effective

Other needs identified

A need was identified for continuous dust monitoring to get an overview on exposure of dust on employees working underground

Installation of instruments

14 Instruments were installed in a ventilation district underground

slide-6
SLIDE 6

6

Schematic layout (phase 1)

18 x/cut 9 x/cut 9 x/cut 44 Level 47 Level 50 Level Stn Tips Stn Tips Stn Tips Downcast Shaft Up-cast Shaft 6A x/cut Bank KOP1 Ventilation District

  • Installations were done in the following areas:
  • Surface, the downcast shaft
  • Before and after various tipping areas
  • Haulages and at the entrance to a development end.
  • This was done to measure the effectiveness of current engineering systems installed underground.
slide-7
SLIDE 7

7

The real-time monitor

AMS THERMO PDR1100 DUST LEVEL TRANSMITTER

slide-8
SLIDE 8

8

Project phases Phase 1

  • Sensors installed in Kopanang Upper Mine
  • Trends analysed from the real time sampling instruments proofed that engineering controls in

that ventilation district is sufficient for the dust load

Phase 2

  • Workers on 59 level complained about excessive dust during tipping operations
  • With engineering controls installed, the dust problem persisted .
  • Monitors were moved to 59 Level to assist with identifying the cause and source of the dust

problems.

  • Immediately after installation the trends indicated that although high dust readings were
  • btained during tipping, the main cause of dust was during the transfer between levels .
  • It was decided that the transfer time should be moved to late afternoon, after the shift, thus

reducing the employees exposure to dust

  • All engineering controls were automated
  • With the above process complete, the dust problem is effectively managed
slide-9
SLIDE 9

9

59-Level station diagram

Tips Tips Tips

59 Level

slide-10
SLIDE 10

10

Sensor results - Before

slide-11
SLIDE 11

11

Sensor results - After

slide-12
SLIDE 12

12

Pre-strategy

80% 20%

Problem finding vs monitoring

Trouble shooting Dust Management

slide-13
SLIDE 13

13

Post-strategy

80% 20%

Problem finding vs monitoring

Dust Management Trouble shooting

slide-14
SLIDE 14

14

Benefits/Advantages

Fast reaction time possible Manage effectiveness

  • f engineering control

installed underground Can monitor the whole mine simultaneously and continuously You get the real picture of happenings underground in real time No consumables and low maintenance Move away from reactive management mode into a proactive approach

Real-time Monitoring

slide-15
SLIDE 15

15

Lessons learnt

1

  • Buy-in from multiple departments and stakeholders

needed for this program to succeed. (Ventilation, Engineering, Mining etc) 2

  • Proper training required ( Installation, operation and

maintenance of instruments) 3

  • Awareness campaign a necessity

4

  • Spare instruments should be available

5

  • The System will only work if it is properly and timeously

maintained 6

  • Establishing the Kopanang Dust task team, proved to be

very beneficial to the success of this practise

slide-16
SLIDE 16

16

Previous Dust Task Team

W Blaai V Lengisi E Semoeng V Msi T Bulwa

We are committed to make a D I F F E R E N C E

Success story

slide-17
SLIDE 17

17

Dust Task Team

K Merahe G Tladi E Semoeng S Sanqu S Makanda

We are committed to make a D I F F E R E N C E

Success story

Z Malingo

slide-18
SLIDE 18

18

Our vision

  • To monitor the whole mine

simultaneously and continuously

1

  • Continuous improvement towards

zero harm from silica dust and

  • ther airborne pollutants

2

  • Improved identification of problem

areas – by getting the real picture in real time on activities as it is happening underground

3

slide-19
SLIDE 19

19

Closure With Real-time Monitoring these days are gone FOREVER!!!

Thank You