energy networks association
play

Energy Networks Association TSO-DSO Project Advisory Group 27 th - PowerPoint PPT Presentation

The Voice of the Networks Energy Networks Association TSO-DSO Project Advisory Group 27 th April 2017 Welcome & Introductions Nigel Turvey ENA TSO DSO Project Steering Group and Advisory Group Chair 2 Introduction Address


  1. The Voice of the Networks Energy Networks Association TSO-DSO Project – Advisory Group 27 th April 2017

  2. Welcome & Introductions Nigel Turvey – ENA TSO DSO Project Steering Group and Advisory Group Chair 2

  3. Introduction Address David Smith – ENA Chief Executive 3

  4. TSO-DSO Project – Goals & Communications Plan Jason Brogden – TSO DSO Project Director 4

  5. TSO-DSO Project Introduction • In December Energy Networks Futures Group & ENA Board (Business Leaders) gave their commitment to a long-term project to be led by ENA to progress the transition of DNOs to DSOs, provide clarity to the interface between DSOs & TSOs and improve the customer experience. • First Phase to deliver in 2017 • Expect Second Phase in 2018 and then beyond to ED2/T2 End Phase 1 Phase 2 Phase 3 Phase 4 2017 Definition of T-D Impact Assessment of Processes, Customer Experience, DNO to Options and Preferred Regulatory Enactment Design, Build and Test DSO Transition & Design Charging The Voice of the Networks 5

  6. TSO-DSO Project Objectives The objectives of the TSO-DSO Project for the first phase of work in 2017 are to: 1. Develop improved T-D processes around connections, planning, shared TSO/DSO services and operation 2. Assess the gaps between the experience our customers currently receive and what they would like and identify any further changes to close the gaps within the context of ‘level playing field’ and common T & D approach 3. Develop a more detailed view of the required transition from DNO to DSO including the impacts on existing organisation capability 4. Consider the charging requirements of enduring electricity transmission/distribution systems The Voice of the Networks 6

  7. Governance and Hierarchy ENA Board ENFG inform TSO-DSO Project inform New TSO-DSO Project Steering ERG Advisory Group advise COG Workstream 2: Workstream 3: Workstream 1: Workstream 4: Customer DNO to DSO Charging T-D Process Experience Transition The Voice of the Networks 7

  8. TDI WG to TSO DSO Project 2. Customer Statement of 1. T-D Process HV Experience Works ENA Transmission TSO-DSO and Distribution Shared Active Interface Project Services Network Steering Group Working Management Group Group 3. DNO to DSO 4. Charging Charging Transition Task Group The Voice of the Networks 8

  9. Project Workstreams 2. 3. DSO 1. T-D Workstreams 4. Charging Customer Transition Process Experience Stakeholder Engagement / Transparency / Programme Management Regulatory and Policy Considerations – inc. EU packages Commercial Considerations Smart Grid Forum WS6 Actions and Outcomes The Voice of the Networks 9

  10. Proposed Development and Workstream (WS) structure Products WS2 – Products Products WS3 – DNO to WS4 - Products WS1 – TD Customer DSO Transition Charging Process Experience • SME1 •SME1 •SME1 •SME1 1 • SME2 Lead / Chair: Lead / Chair: Lead / Chair: 1 •SME2 Lead / Chair: 1 •SME2 •SME2 • SME3 1 Mark Drye (NpG) Stewart Reid Paul McGimpsey •SME3 Sotiris •SME3 •SME3 (SSE) (SPEN) Georgiopoulos • SME1 (UKPN) 2 • SME2 •SME1 + + + • SME3 2 •SME2 •SME1 •SME1 + •SME3 2 •SME2 •SME2 2 Member Member Member • SME1 •SME3 •SME3 Representatives Representatives Representatives Member 3 • SME2 •SME1 • SME3 Representatives 3 •SME2 •SME3 •SME1 •SME1 • SME1 4 3 •SME2 •SME2 3 • SME2 •SME3 •SME3 •SME1 4 •SME2 • SME1 5 • SME2 •SME1 •SME1 4 … •SME2 •SME2 •SME1 5 • SME1 •SME2 6 • SME2 • SME3 •SME1 •SME1 •SME1 5 x • SME1 •SME2 •SME2 6 •SME2 7 • SME2 •SME3 • The Work Stream Group will steer the development of the products • The Work Stream Member Chairs should sit on the steering group • Member representatives can also be SME’s for particular products The Voice of the Networks 10

  11. Workstream 1: T-D Process Scope • Investment Planning processes (processes that result in either capital or opex investment decisions for network businesses) • Operational Planning processes (capturing operational planning, real time, balancing and settlement) • Develop whole system investment and operational Planning Processes/models • Review development of ancillary services across GB • Develop approach for the co-ordination of transmission and distribution constraints in an operational timeframe • Develop whole system commercial agreements for Active Network Management with distributed generators • Review and update SoW to take into account TSO DSO project scope and developments The Voice of the Networks 11

  12. Workstream 2: Customer Experience Scope • Customer Journey Maps for Connections & Service Provision • Short Term Improvements –make early improvements to processes for connection and service provision. • Updated Connection Arrangements - Agree and implement changes to network access arrangements (Bilateral Connection Agreements) for DER. Explain the different connection offers available to customers and the impact that these can have on them • Service Provision Improvements • Customer Journey Maps for Changes to Legacy Arrangements • Emergency Events Customer Journey Maps • Customer Information Requirements –improvements to the information that is provided to support network access and service provision. • Ensure that agreed improvements to customer experience are taken forward in other workstreams. • Complete ongoing work to improve Statement of Works process. The Voice of the Networks 12

  13. Workstream 3: DNO to DSO Transition Scope 1. DSO Transition Roadmap - a roadmap to deliver transition to DSO in the short, medium and long term 2. DSO Functional Requirements 3. Model for DSO - model for DSO with some options set out for governance models which will allocate DSO functions to system roles and responsibilities 4. DSO Market Model Options Comparison & Evaluation - an assessment of the risks/benefits for power system users, customers and industry participants 5. Trials to Support DSO Definition – if necessary definition and initiation of trials to test different market models and/or any gaps in the existing evidence base to support decisions to define market models (across different regions and Network Operators) The Voice of the Networks 13

  14. Workstream 4: Charging Scope Short-term – by June 2017 1. Identify problems caused for customers through the interaction of current charging arrangements across Transmission and Distribution on customers 2. Capture the root causes of these problems. 3. Establish the level of commonality that might be required to resolve identified root causes and deliver project and workstream objectives/goals. 4. Develop recommendations including - overview of current industry charging reviews, proposals to solve issues identified, implications to existing arrangements and steps needed to implement, recommendations for a charging framework (focused on connection and Use of System charging), identification of quick wins. Medium-term – by December 2017 5. Recommendations to Ofgem : Smart tariffs, flexible connection services, ancillary services pricing; identify requirement for (cross sector/industry) working groups to progress long- term deliverables. Long-term Products potentially 2018-2020 6. Strategic Review – Whole System Pricing 7. Consider proposals to change the governance around changes to the methodologies The Voice of the Networks 14

  15. Communications Plan & Engagement Regular collaborative meetings with BEIS, Ofgem and the Advisory Group Promotion of our project to stakeholders and influencers by demonstrating: • tangible benefits to consumers, businesses and the UK economy • how the project delivers the vision of a wider ‘Smart Grid’ and a smarter, flexible energy system • a transparent approach that encourages industry engagement We have a list of interested parties to keep informed We have a TSO DSO Project page on the ENA website and we will continue to publish output: http://www.energynetworks.org/electricity/futures/tso-dso- project/overview/ The Voice of the Networks 15

  16. Address from the ENA Chair Basil Scarsella – CEO UKPN 16

  17. Advisory Group Terms of Reference Nigel Turvey – Advisory Group Chair 17

  18. Purpose The Advisory Group is essential to our project to: • Ensure stakeholders are aware and taking the Project into account in their work • Request input from stakeholders to improve the quality of our products • Increase awareness about project risks & issues, ask for views on risks & issues and collaboratively resolve where appropriate It will provide input to: • Steering Group on project scope, progress, risks & issues • Workstreams with deliverable comments/feedback We will seek to send information in advance of meetings to ensure that views can be sought by trade associations in advance • Easter timings with early workstream meetings meant that we couldn’t get information out as early as we wished this time The Voice of the Networks 18

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend