Energy Conservation Award Nomination: By Dr.M.S.Kele ,Chief Engineer (Commercial),Mumbai
1
Energy Conservation Award Nomination: By Dr.M.S.Kele , Chief - - PowerPoint PPT Presentation
Energy Conservation Award Nomination: By Dr.M.S.Kele , Chief Engineer (Commercial),Mumbai 1 0 Power Sector In Maharashtra MSEDCL At A Glance Current Installed Capacity In Maharashtra Yearly Average Peak Demand & Availability
1
murharikele@gmail.com 2
Maharashtra State : Supplied Electricity through Four Power Distribution Utilities.
murharikele@gmail.com 3
Area: 3.08 Lakh Sq. km; Villages: 41095; Towns : 457 Consumers: 1.94 Cr. (Agricultural: 34 Lakhs /Residential: 143 Lakhs) Sub-stations & Switching Stations: 2514 (33/11 & 22/11 kV) HT & LT Lines: 8.70Lakh ckts km , Distribution Transformers: 3.90 Lakh Monthly Revenue : Rs 3100Cr (Approx) Average Cost of Supply: Rs. 5.56 per unit Zones: 14/ Circles: 43/ Divisions: 138/ Sub Divisions: 629 / Section Offices: 3294 Employees: 77,109 Departmental & 10,335 Outsourced
murharikele@gmail.com 4
KOYNA HYDRO 1956 MW SMALL HYDRO 629 MW URAN GTPS 672 MW
MSPGCL HYDRO 2585 MW & MSPGCL GAS 672 MW
Total MSPGCL installed Capacity 10487 MW
MSPGCL Installed Capacity 10487MW CENTRAL SECTOR +GoM Hydro 4487 MW
RGPPL (1967 MW) +NCE (3354 MW)+ IPPs (780 MW)+Dodson Hydro 46 MW
TATA & RELIANCE 2527 MW
23648 MW
Maharashtra State Thermal 7230 Gas 2639 Hydro 2631 Central +GOM Hydro+TATA 7014 NCE 3354 CPP / IPP (Major) 780 Total (MW) 23648
Paras 500 Khaparkh eda 840 Koradi 620 Nasik 880 Bhusaval 920 Parali 1130 Chandrap ur 2340
Total MSPGCL Thermal=7230 MW murharikele@gmail.com 5
5000 10000 15000 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13
Shortfall Availability Demand Supply Gap Reduced: MSEDCL is near about to Power Surplus Position
YEAR 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13
MW MW MW MW MW MW MW MW
Demand 12404 12797 13137 12507 12624 13157 14043 14173 Availability 9212 9638 10130 10203 10921 11917 12841 13286 Shortfall 3192 3159 3007 2304 1703 1240 1202 886
murharikele@gmail.com 6
0%1% 7% 73% 18% 1%
HT (Ind) LT (Ind) Comm (LT+HT) Residential Agri.(LT+ HT) Others
32% 6% 6% 16% 27% 13%
HT (Ind) LT (Ind) Comm (LT+HT) Residential Agri.(LT+ HT) Others
41% 8% 11% 15% 5% 20%
HT (Ind) LT (Ind) Comm (LT+HT) Residential Agri.(LT+ HT) Others
murharikele@gmail.com 7
MSEB-2005 MSEDCL-2013 % Change Installed capacity in 9856.MW
Shortage of power 4025.MW
Annual Turnover 15072 Crs
Distribution Losses: 31.72 %
AT & C losses
Collection efficiency: 85.19 %
Billing Efficiency 68.86 %
Transformer failure rate 18.52 %
Agriculture connections 23.24,Lackhs
murharikele@gmail.com 8
murharikele@gmail.com 9
Generation Efficiency
( PLF 30%)
Step up Station 400kV
(99.5%)
EHV Transmission Stn 400kV
(99%)
Meter Side Appliances Side Energy Realized
HV Transmission Stn (220kV)
97.5%
Sub Transmission at 132kv/66kV
(96%)
Step Down Level at 33
(95.5%)
Distribution Level 33kv & 11kV
(95%) Efficiency at Gen to End User
(87%)
Consumer Door Step
(87%) Supply Side Efficiency (1% Loss) Transmission Side Efficiency (4.5% Loss) Demand Side Efficiency (13% Loss) Consumer Side Efficiency (18 % & More)
murharikele@gmail.com 10
– Total Power Purchase =1,00,000 MUs/Yr – 1% Loss of MSEDCL= 1000 Mus – Av. Cost of Supply= Rs.5.56/Unit – Revenue Loss for 1% Loss=556 Crs/Yr – Present AT & C Loss of MSEDCL= 18.41 % – Permissible loss for such utility= 13.5 % – Yearly We are loosing revenue of Rs. 2700 Crs (Approx)/Yr
– Allied Issues:
murharikele@gmail.com 11
Energy Input (Units) Energy consumption (Units) Energy Billed to Consumers (Units) Amount Billed to Consumers (Units) Amount Recovered (Units) Energy Realized (Units)
Billing Gap Recovery Gap
AT &C Loss
AT&C Loss (%)=(Energy Input-Energy realized) x 100/ Energy input Energy realized= Energy billed x Collection efficiency Collection Efficiency(%)= Amount realized x100/ Amount billed Average tariff = Amount billed / Units Billed Energy Realized = Amount recovered / Average tariff
murharikele@gmail.com 12
Universal Service Obligation Large scale rural electrification Ad-hoc expansion without proper planning Old technology & fragile infrastructure Too many transformation stages Low power factor Improper load management Improper location of DTC Substandard material Poor construction methods
Theft – hooking Tampering of meter Old/electromechanical meters Nature & Locations of meters
Inaccurate Reading Methodology of billing Average/in accessible cons. Improper tariff & Wrong calculations
Payment mode & facilities Non-effective disconnection
Loss of opportunity by any reason, to serve consumers is biggest loss of utility
murharikele@gmail.com 13
Particulars 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12
Input ( MUs) 64847 69813 73400 74559 80526 86170 95433 Sale ( MUs) 44279 49148 55716 58171 63941 71279 80132
20568 20655 17684 16388 16585 14891 15301 % Dist. Loss 31.72 29.6 24.09 21.98 20.6 17.28 16.03 % AT & C Loss 34.72 33.98 26.08 24.62 21.41 18.45 18.41 % Coll. efficiency 85.19 94.07 97.8 96.61 98.98 98.52 97.21
50000 100000 150000 200000 250000
Sale ( MUs) Input ( MUs)
20 40 60 80 100 120 140
2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12
% Coll. efficiency % Dist. Loss
Loss Reduction approx.by 50% after company formation i.e.in 7 years
murharikele@gmail.com 14
Year No of Distribution Transformers Installed No of Transformers Failed during year Distribution Transformers failure rate in %
2005-06 226824 36618 16.14% 2006-07 239333 40483 16.91% 2007-08 256793 33375 13.00% 2008-09 271251 38785 14.30% 2009-10 284633 38084 13.38% 2010-11 321351 36495 11.36% 2011-12 358408 33973 9.48% 2012-13 376329 21386 5.68%
50000 100000 150000 200000 250000 300000 350000 400000 0.00% 2.00% 4.00% 6.00% 8.00% 10.00% 12.00% 14.00% 16.00% 18.00% 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13
Distribution T/F failure rate in %
T/F failure rate is reduced by: 66 % As Compared with last year: 45%
murharikele@gmail.com 15
murharikele@gmail.com 16
Aim & Objectives
Plan
Reliable and Quality Power Supply Meet the Load Growth Demand. Reduce Distribution Losses. Reduce DTC Failure Rate
Progress of Activity Scope of work Commissioned
New Substation 613 348 Augmentation of Power Transformer 330 272 Additional Power Transformer 428 349 H.T. Lines (Km) 50323 25344 L.T. Lines (Km) 15657 6395 Distribution Transformer ( *** rated T/F) 68147 46734 HVDS 13256 8365 Pole Mounted Capacitor Banks 2896 1707 Cost of Infra.plan project Rs.9013.96 crs Rs.5184 crs
Results of scheme:
reduced by 2-3 %
increased consumers satisfaction.
improved.
murharikele@gmail.com 17
R-APDRP Part-A Part-B
Object Establishment of baseline data with IT & EA with IT Based Consumer Service centers Loss reduction & Strengthening
324 Crs for 130 towns 1793 Crs for 94 towns Progress L&T, Spanco & Reliance Infra had started work in most of Cities DPR of 35 Towns under sanction for Rs. 2708.09 Crs.
Objectives Scope of Work Wadi electrification Releasing of connections for BPL consumers BPL connections released 10.73 lacks as against 13.44 lacks. It will reduce HT/LT ration resulting in T&D loss. Scheme Cost
BPL Households
13,44,087
HT Line (km) 5,218 LT Line 8,506 New DTCs 9,015 Progress 80 %
murharikele@gmail.com 18
Year Cost of Scheme Feeders Covered Villages benefited Load Management 2010-11 456 Crs 1186 11962 1153 MW 2011-12 473 Crs 768 3520 722 MW
Year Cost of Scheme Feeders Covered Villages benefited Load management 2010-11 895 Crs 1498 6932 1633 MW 2011-12 1958 Crs 1631 8104 1085 MW
sheddable (domestic load) by converting three phase supply into single phase supply.
feeder is carried out by using changeover switch at substation
supplied through normal three phase transformers.
phase supply is available to lighting and fan load and three phase AG load can not be
GFSS:
murharikele@gmail.com 19
Name of the Scheme Cost of Scheme ( In Cr.) Feeders Villages Load Management Expen. ( In Cr.) Scope (Nos) Achieved (Nos) Scope (Nos) Achieved (Nos) Scope (MW) Achieved (MW) Single Phasing-I
235 1186 1186 8085 8085 1153 1153 213
Single Phasing-II
221 768 768 3877 3877 722 722 214
Single Phasing-III
205
1880
Single Phasing Left-out
268
1105
Single Phasing Total 929 1954 1954 15482 14947 1875 1875 729
GFSS-I
895 1498 1498 6932 6932 1905 1905 816
GFSS-II
1006 895 877 7005 6321 1088 874 821
GFSS-III
231
325
GFSS Left-out
721 1008 905 3601 1762 628 216 431 GFSS Total 2853 3401 3280 17919 15340 3621 2995 2236 Grand Total 3782 5355 5234 33401 30287 5496 4870 2965
murharikele@gmail.com 20
murharikele@gmail.com 21
Year of Installation Capacity of Bank in MVAr 2007-08 156.54 2008-09 105.65 2009-10 60.665 2010-11 348.08 2011-12 873.42
200 400 600 800 1000 2007-08 2008-09 2009-10 2010-11 2011-12
Capacity of Bank in MVAr
Power Factor & voltage improvement. Low KVA Loading with less stress on T/F Low current drawn from source with Low Transmission and Distribution loss No undue high temperature and low losses
By directly connecting LT capacitor across motor terminals. By connecting LT switched capacitor bank at DTC on load side (LT LMS) Connecting switched capacitor bank (660kVAR) to HT lines & at Sub Station. Connecting capacitor bank to EHV level at 132kV sub station
murharikele@gmail.com 22
Year No.of Conn. checked No.of theft cases detected No.of FIR lodged Amount recovered in Crs
2005-06 160828 56569 8123 35.19 2006-07 225262 59797 10162 38.77 2007-08 476983 89880 9411 55.41 2008-09 990092 57065 4864 44.48 2009-10 1040041 50698 9681 54.28 2010-11 662375 17268 5058 14.30 2011-12 719888 47633 8611 41.04
Total 4275469 378910 55910 283.47
regions under V&s Dept
squads at divisional level.
level.
are established.
high theft prone area.
reading through MRI
value consumers & action
/outsiders
Clear & loud Message to consumers & Employees: “Theft of energy is Stigma on Society & We are going to eradicate it, by Zero tolerance in Theft. ”
murharikele@gmail.com 23
Damini Squad Started –Jan 2010. Purpose: crosschecking & to have control of meter reading activities of agency. Tenure - 3 months on extendable basis. Only women's consisting one Junior engineer from circle level leading a team of 3-4 ITI holder. Headed by Jr.Engineer.
is given.
inviting all Mahila Bachat .
Security Deposit, clear instructions / directions were issued vide Circular No.103 dtd. 16.11.09.
so the earlier S.D. to be refunded as per rules.
reading including photo metering, punching & bill distribution is about Rs. 5 per bill in Urban areas, & Rs. 7 per bill in Rural areas.
Bachat Gats are as under:- murharikele@gmail.com 24
Year Achievement 2000-01 50,502 2001-02 38,052 2002-03 49,014 2003-04 74,021 2004-05 81,294 2005-06 79,466 2006-07 1,22,566 2007-08 1,18,076 2008-09 1,14,728 2009-10 1,54,415 2010-11 321,299 2011-12 252,784
Target for Ag pump Energisation during 2012-13 is : Zero Pendency of Ag. applications
50000 100000 150000 200000 250000 300000 350000
murharikele@gmail.com 25
murharikele@gmail.com 26
Installation of ATP (Any Time Payment) Machines. E-Tendering system( Materials supply, works) Data centre at BKC Bandra. Energy Accounting System( Feeder wise & DTC wise). HT consumers on AMR meters. HT bill payment through RTGS. Online NSC & consumer Bill payment. Implementation of DMS(Document Management system). We have installed 416998 nos of IR meters and 77999 nos of RF meters in all over Maharashtra. Smart Grid project to reduce outage and increase network flexibility. DMS (Document Management System)
Paperless Office Concept:
Phase-I
Scanning and Online Approval for Internal Office Notes Scanning and sending Outward Documents Reduction in Printing activities
Phase II
Deployment of System across Zones and Circles on Independent servers at Zone / Circle Location Link for DMS Solution :- http://10.0.2.65:8080/dms/jsp/prlogin.jsp
murharikele@gmail.com 27
New Connection Disconnection and Dismantling Meter Data Acquisition System (AMR) Energy Accounting GIS based Consumer Indexing, Asset Mapping GIS Based Network Analysis Consumer Care and Customer Relationship Management Web Self Service Portal & Document Management System MIS - Business Intelligence - Dashboards Integration Middleware for Integrating the existing s/w systems viz. billing system, ERP HRMS, PayRoll, Fix Assets, Materials Management, eTendering etc. Identity Access Management & System Security Enterprise and Network Management System (EMS/NMS)
murharikele@gmail.com 28
Meters installed at Mahabaleshwar, Lonawala, 25,000 meter installed.
Without photo, only with HHU reading can be taken, Installed in Urban area..
Meters Balance Installation No. of Met. Installed
LT 780 4882 DTC 31090 22718 HTC 6113 12256 Feeders 5230 4838 Cross Over 278 267 TOTAL 42711 44961
murharikele@gmail.com 29
PFC has Sanctioned 8 towns amounting to Rs 161.62 Crs for implementation of SCADA.(Malegaon, Nashik, Sangli, Solapur, Kolhapur, Pune, Amravati and Greater Mumbai).
SCADA is being implented in integration with IT system under R-APDRP Part-A.
Implementing Agency of SCADA /DMS : M/s SIEMENS.
Only 5 towns (Amravati , Sangli, solapur , Kolhapur , Malegaon and Greater Mumbai ) sanctioned by PFC on 27.08.2012 for Rs 154.54 Crs
The Balance three towns i.e Pune ,Nashik and Kolhapur are not considered for Sanction as the AT&C Losses are less than 15 % .
These three towns are big towns having the population of more than 4 Lakh and the successful implementation of SCADA in these towns is important .
Data recovery centre (DR) to be supplied under SCADA/DMS system is located at Nagpur common for SCADA/DMS of all 8 towns.
The cost of SCADA Part B for these three towns is Rs 275.48 Crs
murharikele@gmail.com 30
murharikele@gmail.com 31
murharikele@gmail.com 32
Year of RPS %RPS Target % RPO Achieved Total RE in MUs 2005-06 0.00 899 2006-07 3 2.89 2100 2007-08 4 3.55 2658 2008-09 5 4.73 3558 2009-10 6 5.17 3957 2010-11 5.75 5.77 4928 2011-12 6.75 7.14 6779
1 2 3 4 5 6 7 8 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12
%RPS Target % RPO Achi-eved
MERC has allowed to achieve solar RPO with cumulative effect up to 2015-16
1000 2000 3000 4000 5000 6000 7000 8000
RE (MUs)
RE (MUs)
RE Source Installed Capacity Wind 2954.31 MW Co-gen (Bagass) 906 MW Biomass 127 MW Hydro 56 MW Solar 26.5 MW
Total 4069.81 MW
murharikele@gmail.com 33
Year of RPS Cogen., Biomass (MUs) Hydro (MUs) Wind (MUs)
2005-06 54 601 244 2006-07 148 739 1213 2007-08 314 749 1595 2008-09 428 888 2242 2009-10 599 753 2604
2010-11 992 1306 2402 2011-12 1329 1526 3610
500 1000 1500 2000 2500 3000 3500 4000
Cogen., Biomass (MUs) Hydro (MUs) Wind (MUs)
murharikele@gmail.com 34
murharikele@gmail.com 35
Conservation and Safety at schools FOR Public awareness.
Conservation programmes are regularly
Eklahare, Nasik.
information.
programs at schools.
at various locations for providing information.
Conservation and safety through mass media/Newspapers/Advertisements
murharikele@gmail.com 36
All the material procured by H.O.is tested by testing engineers, thereby maintaining the quality of the material All HT consumers are tested annually by testing engineers & cases of under billing, due to failure of equipments(CT/PT, meter), wrong billing due to wrong M.F. etc. are detected. Loss measurement of Distribution Transformers 100% Dist. T/Fs purchased by MSEDCL either through CPA or through various Infra/RGGVY single phasing schemes, are tested by Testing Engineers for No Load & Full load losses, thereby restricting the losses to limits specified by MSEDCL. Measurement of Harmonic Distortion in Consumer’s Installation At the time of annual testing of HT consumers, the testing engineers also measure percentage Harmonic Distortion for voltage & current. Notices are issued to the HT consumers if the THD is beyond permissible limits. The HT consumers are insisted to install harmonic filters in their installations, thereby reducing losses due to harmonics.
murharikele@gmail.com 37
Awards Category HR Initiatives
World HRD Congress 2012 Contribution to Training & Development
Paperless Working
World CSR Day Awards 2012 Diversity & Human Resource On Line HRMS Shine HR Leadership 2012 Quality of Work Life On Line Confidential reports Bloomberg TV Awards 2012 Dream Employer (State PSU) Direct Recruitment up to ED Asia Pacific HR Congress 2011 Innovative HR Practices Transfer Policy & Seniority List
Training:
(T&S)
Centres headed by Chief Engineer (T&S)
professional, M.D.P & HR etc.
employees put through training
Crores – PFC, REC, N.D.P.L. & Private Establishment
electricity Distribution oriented training
Safety:
15 Nov to 15 Dec 2011
employees & more than 1,00,000 outsiders were educated on safety
following safety instructions
Motivation:
promotions and postings/transfers
qualifications & good suggestions
& Operators
medical relief etc.
cases
murharikele@gmail.com 38
last 18 months
murharikele@gmail.com 39
24X7 Call Center
covering – 20 Major Cities/ District Head Quarter
Pune by 30th Sep 12
will be added to call centers
Consumer Facilitation Centre (CFC) Concept
CFCs
murharikele@gmail.com 40
Mangalwedha
murharikele@gmail.com 41
In order to accelerate energy efficiency measures in
Project is implemented on Brahmapuri, Nandeshwar,
Total 3530 Pump sets are replaced & free R&M of
BEE appointed MITCON for preparation of DPR & M&V
Project Cost: INR 7.063 Cores Pump sets replacement period: 6 Months Project Period: 5 Years after replacement of all Pump
Scheme period 2010-11, closed in December-2012.
murharikele@gmail.com 42
Old Pumps New Pumps
Feeder Name Sanctio ned Voltage Power Usage Discha rge Total Head Old Pump Efficien cy Voltage Power Usage Dischar ge Total Head New Pump Efficien cy
HP V KW m³ /hr m HP % V KW m³ /hr m HP %
Bhose
4.47 380 5.90 20.51 26.39 4.95
22.51
377 4.42 25.92 28.91 4.49
42.65
Borale
4.02 354 5.63 23.52 22.79 4.64
23.92
352 4.24 29.20 25.83 4.23
45.41
Brham apuri
6.25 384 7.25 22.66 25.13 6.47
20.62
382 5.43 27.06 27.10 5.60
35.49
Nandes hwar
4.87 356 6.79 18.47 38.08 5.66
22.18
349 4.99 23.39 40.61 5.06
42.62
Kharat wadi
4.95 370 6.80 20.82 30.58 5.44
22.24
367 5.08 25.73 32.87 5.06
40.28
Averag e
4.73 365 6.35 21.39 28.33 5.29
22.60
362 4.74 26.56 30.9 4.78
42.14
murharikele@gmail.com 43
5.Pump Selection 4.Field Survey 3.Agreement with Farmers 1.Farmers Awareness Programme 6.Existing Pumpsets Observation & its Replacement 8.Inventory Maintenance
2.Interaction with MSEDCL
7.New Pumpset Installation & its Observation
programme arranged AT BATHAN VILLAGE and
BOSE VILLAGE to use of
four star rated electrical equipments for energy saving.
boards are used for notices of energy efficient motors.
murharikele@gmail.com 44
murharikele@gmail.com 45
Peak Clipping Strategic Conservation Valley Filling Load Building Load Shifting Flexible Load Shape .
murharikele@gmail.com 46
47
MERC order dt. 03.08.2005
Division was considered as a base. Divisions was grouped in 4 groups as per Distribution collection loss 70% weightage was given to LT Loss. 30% weightage was given to LT collection efficiency. Based on the loss levels divisions Urban Rural A 0% to 25% 0% to 28% B >25% to 35% >28% to 38% C >35% to 50% >38% to 53% D >Above 50% >above 53% Group DCL
Group Other /Non AG feeders Mix /Ag. Dominated feeders Distribution Collection Losses (DCL) Load shedding hours Distribution Collection Losses (DCL) Load shedding hours A 0% to 18% 3.15 0% to 21% 11.00 B >18% to 26% 4.00 >21% to 29% 11.30 C >26% to 34% 4.45 >29% to 37% 12.00 D >34% to 42% 5.30 >37% to 45% 12.30 E >42% to 50% 6.15 >45% to 53% 13.00 F >50% to 58% 7.00 >53% to 61% 13.00 G1 >58% to 66% 7.45 >61% to 68% 13.30 G2 >66% to 74% 8.30 >68% to 76% 14.00 G3 Above 74% 9.15 Above 76% 14.00
MERC Order Dtd. 2012 (Feeder Based)
murharikele@gmail.com 47
TOTAL FEEDERS
Sr. No.
Feeders Nos.
1
5917 2 Industrial And Express Feeders 2520 3 Non Ag/ Mixed Feeders 4890 4 Feeders in A,B,C & D Group 3474 5 Feeders in E & F Group 727 6 Feeders in G1G2G3 Group 544 7 Absurd Feeders 145
Total Nos. of Feeder
13327
(A) Feeders Liable for LS 1 A,B,C & D Group 3474 2 E & F Group 727 3 G1G2G3 Group 544 4 Absurd Feeders 145 5 Industrial And Express Feeders 2520
Total 7410
(B) LS Free Feeders
1
A,B,C & D Group 3474
2
Industrial And Express Feeders 2520
Total 5994
% LS Free Feeders (594/7410*100)
80.9 %
96.2% 3.8%
Avg. MSEDCL Catered Mus/day in Dec-12
shedding Mus/day in Dec-12
Mus/day in Dec-12
Mus/day in Dec-12 291.2 11.4
murharikele@gmail.com 48
Parameters Bhiwandi Nagpur Aurangabad Jalgaon
Franchisee Company TPL Spanco GTL CGL Date of Comencement 26.01.2007 01.05.2011 01.05.2011 01.11.2011 Parameters Start Today Start Today Start Today Start Today
141857 266408 389665 430063 224806 238123 120991 123736 Losses in % 42 17 30 29 21 21 28 24
67 96 99 99 99 100 96 89 Input in Mus 2320 3188 1331 1400 1696 1866 728 780 Demand in Crs 661 1570 554 599 764 866 260 367 T/F Failure rate 40 1.9 3.49 3.33 3.29 2.21 5.4 3.2 EHV Capicity 675 1000 335 375 263 281 156 176
46 64 228 228 156 172 94 113
murharikele@gmail.com 49
Period of replacement
No of cons. whose meters replaced Billed MUs (Before MMR) Billed MUs (After MMR) Rise in sale in MUs
2008-09
1173881 724.7 1064.2 339.5 46.84%
2009-10 1214822 898.76 1267.74 368.98
41.05 %
2010-11 1205364 876.23 1122.78 246.55
28.13%
2011-12 1295775 983.43 1324.94 341.51
34.72%
Overall Rise in Sale after MMR=30 to 45%
murharikele@gmail.com 50
initiatives
Accurate Energy accounting
System to record, analyze & report consumption & Cost on regular basis
murharikele@gmail.com 51
EHV System 400/220/ 110/66 kV
MSPGCL Generation Power Purchase (Central) Power Purchase TATA Power Purchase NCE & Other Other States TATA Mula Pravara O&M Zones ( HT + LT) Metered Sale + Unmetered Sale EHV System/
O&M Zones/ Dist (D )Loss
EHV system Loss -- Loss upto 11,22,33 kV bus of EHV sub-station Distribution Loss --Loss beyond 11,22,33 kV bus of EHV sub-station
EA is for identifying high loss area & action plan for reduction of losses Maharashtra is first State which has implemented
FBSM System
murharikele@gmail.com 52
1000 2000 3000 4000 5000 6000 7000
2012-13 2013-14 2014-15 2015-16 AMOUNT(Crs.) 5892.49 6047.63 4061.3 2587
murharikele@gmail.com 53
murharikele@gmail.com 54
MSEDCL
Damini squad
ZLS
Model
GFSS & Single Phasing
Amnesty schemes for Ag,PWW,
Mahavit ran Aplya Dari
Spot Photo Billing
Dist.
Franchise e Direct recruitm ent for all posts
Mahavitaran Apulia Dari to release Ag connections MMRS- Approx. 2 lack meters/month 100 percent Metering and billing to Ag pumps on non separated/mixed feeder. Connected Load of all AG pumps to be checked Reactive Power management by Repairing of capacitors bank & by additional Station & line capacitors. Temporary withdrawal of employees where manhandling, mass agitation against recovery,etc Massive Theft detection & disconnection drive
murharikele@gmail.com 55
Loss reduc tion CPP
Open Access
Threat
loosing market High power purchas e cost
Consu mer Satisfac tion
Parallel license
Deemed license
Exempt ion of license
Loss Reduction: 1% Loss= 200-250 Crs High Power Purchase Cost: Rs.3.84 & Av.cost to serve consumer is 5.56/- Private Generators: CPP/IPP & Co-generators are having their own use/ sale to third party through Open access provisions. License: Exemption/Parallel/Deemed license provision will loose consumer base of utilities. REC Policy: Distribution business by SHGs, local panchayat,, Co-op.societies. Customer satisfaction: By improving services / by rationalized tariff.
murharikele@gmail.com 56
Distribution loss to be brought down to 14% Collection efficiency to be improved to 100% All old meters beyond 10 years in service to be replaced. Upgrade Infrastructure to meet challenge of 25000 MW. AMR for 20000 revenue intensive consumers & 10240 HV FDR to be introduced. Paperless working through DMS system. Centralized MIS system to be in place for better information flow Smart Metering: IR,RF & prepaid meters & AMR for HT Consumers. Advanced technology: Smart Grid, AMR, SCADA etc. Ring Main in Urban. Consumer Satisfaction: 24x7 Call center, Consumer facility centers. Help Desk: For LT Consumers. Online Service Connection & On Line billing & payment facility.
murharikele@gmail.com 57
murharikele@gmail.com 58
– Infrastructure plan – RGGVY – APDRP & R-APDRP
– Single phasing – Gaothan feeder Separation
– Installation of Energy efficient Motors at -Mangalwedha – Installation of Energy Efficient fans at Substations. – Installation of Star rated Distribution Transformer.
murharikele@gmail.com 59
Case 1 Stage 1 (2300 MW)
Sr No. Developer Location of plant Capacity Offered In MW Levelized Tariff Rs./ kwh SCoD 1 JSW Energy Ltd Ratnagiri Jaigad, Dist:-Ratnagiri 300 MW 2.71 Oct 2010 2 Adani Power Maharashtra Limited Tiroda Dist: Gondia 1320 MW 2.642 Aug 2012 3 Lanco Vidarbha Thermal Power Ltd Mandava Dist:- Wardha 680 MW 2.70 Sept 2012
Case 1 Stage 2 (2600 MW)
Sr No. Developer Location of Plant Capacity Offered Levelized Tariff Rs./kwh SCoD
1 Emco Energy Limited Warora, District Chandrapur 200 MW 2.879 17.03.2014 2 India bulls Power Limited, Amravati Nandgaonpeth , Amravati 450 MW 750 MW 3.26 3.26 22.03. 2014 05.06.2014 3 Adani Power Maharashtra Limited Tiroda, Dist: - Gondia 1200 MW 3.28 31.03.2014
murharikele@gmail.com 60
Access to meet emergency power shortfall. Access to sell excess power due to sudden decrease in demand. Availability of variable demand and quantum according to season. Easy online bidding procedure as per variable bidding rates. Timely availability of various reports from exchange. Competitive rates. Introduction of 15 minutes Block in bidding in IEX. enables better load management and disposal of surplus (w.e.f.
01.04.2012)
In order to meet demand supply gap, MSEDCL procures power on long term, medium term and short term
required to meet any emergent need, and the same is procured from power exchange. Towards this, MSEDCL has taken membership with the Indian Energy Exchange (IEX) and Power Exchange India Ltd.(PXIL). Similarly these exchanges can also be used to dispose(Sell) off excess power, if any.
murharikele@gmail.com 61
Year of RPS Cogen., Biomass (MUs) Hydro (MUs) Wind (MUs) Total RE (MUs) %RPS Target Gross
MUs % RPO Achi- eved 2005-06 54.016 601.01 243.641 898.667
148 739 1213 2100 3 72752.19 2.89 2007-08 314.469 748.69 1595.369 2658.527 4 74873.269 3.55 2008-09 427.838 887.737 2242.129 3557.704 5 75287.074 4.73 2009-10 598.963 753.19 2604.43 3956.583 6 76529.692 5.17 2010-11 991.523 1306.193 2401.796 4928.06 5.75 85357.35 5.77 2011-12 1328.99 1526.29 3610.22 6779.084 6.75 94967.357 7.14
from FY 2010-11.
There is steep rise in the Gross Energy Consumption since FY 2010-11 due to efforts for reduction in load shedding, providing standby demand etc.
murharikele@gmail.com 62
Year of RPS Cogen., Biomass (MUs) Hydro (MUs) Wind (MUs) Total RE (MUs) %RP S Targe t Gross
MUs % RPO Achi- eved 2005-06 54 601 244 899
148 739 1213 2100 3 72752 2.89 2007-08 314 749 1595 2658 4 74873 3.55 2008-09 428 888 2242 3558 5 75287 4.73 2009-10 599 753 2604 3957 6 76529 5.17 2010-11 992 1306 2402 4928 5.75 85357 5.77 2011-12 1329 1526 3610 6779 6.75 94967 7.14
from FY 2010-11.
murharikele@gmail.com 63
Year of RPS Installe d capacity MW Cogen., Biomass (MUs) Installe d capacit y MW Hydro (MUs) Installe d capacity MW Wind (MUs ) Total RE (MUs) %RP S Targe t Gross Cons. In MUs % RPO Achi- eved 2005-06 107 54 18 601 1026 244 899
54 148 34 739 422 1213 2100 3 72752 2.89 2007-08 82 314 749 154 1595 2658 4 74873 3.55 2008-09 61 428 888 179 2242 3558 5 75287 4.73 2009-10 120 599 753 40 2604 3957 6 76529 5.17 2010-11 247 992 1306 45 2402 4928 5.75 85357 5.77 2011-12 283 1329 15.40 1526 264 3610 6779 6.75 94967 7.14 2012-13 (As on Nov- 12) 12 474 6 837 230 3683 4543 7.75 64087 7.09 2012-13 (Project ed) 1 400 1600 80 4500 7500 7.75 97087 7.73
murharikele@gmail.com 64
Sr. No NCE Source (Non Solar) Capacit y in MW as
31.03.12 Actual Units procured (Mus) in FY 11-12 Capacit y in MW as
30.11.12 Expected Mus in a FY (as per CUF/ PLF) Actual Units Procured in MUs as
November 2012. Expected Mus as per trend 1 Co- Gen. 828 1396 827 3696 518 1400 2 Biomas s 127 249 127 890 160 250 3 Hydro 56 144 56 146 111 150 4 Wind 2131 2625 2344 4722 2850 3600 Total 3141 4414 3354 10463 3640 5400
murharikele@gmail.com 65