SLIDE 1
Electrical setup at 19 Chancellors Mains connected with additional - - PowerPoint PPT Presentation
Electrical setup at 19 Chancellors Mains connected with additional - - PowerPoint PPT Presentation
Electrical setup at 19 Chancellors Mains connected with additional 4kW of PV generation and 4.8kWh of battery storage with automatic failover to battery supply in the event of a power cut. Inverter and batteries are housed in garage. There are
SLIDE 2
SLIDE 3
Main fuse board
6 circuits have been moved
- ver to battery-
backed fuse board.
SLIDE 4
Battery-backed fuse box
...with duct around external cable entry. New POD cables to use existing duct please if coming into main fuse board.
SLIDE 5
Battery-backed fuse box
SLIDE 6
Meter cabinet
One possible location for POD POINT charger is on this external wall to right of meter cabinet in which case connection will be to main fuse board in downstairs cloakroom following existing cable pathway.
SLIDE 7
Cables under gravel
Solar AC cables (and any new ones going to main fuse box inside) go under gravel trap at front
- f house.
SLIDE 8
Right hand door frame
External cable entry comes up inside right hand door frame column. New cabling to use same route please.
SLIDE 9
Inside electricity meter cabinet
Contains:
- Meter
- Failover circuitry
- Hot water clamp circuit
for excess generation
SLIDE 10
Garage fuse board
Currently no spare fuse locations. If we chose to locate POD charger off garage board then might need to be upgraded. But a connection to this board would be a much simpler physical process.
SLIDE 11
Inside garage fuse board
SLIDE 12
PV Inverter
Inverter with DC and AC isolators. Also located in the garage. Battery supply connected via red/black cables (bottom right).
SLIDE 13
SLIDE 14