east rockaway community meeting
play

East Rockaway Community Meeting Bay Park Sewage Treatment Plant - PowerPoint PPT Presentation

East Rockaway Community Meeting Bay Park Sewage Treatment Plant September 17, 2014 Meeting Agenda Review of Last Meeting Milestones and Timeline Active construction projects Schedule Plant treatment performance Questions 2


  1. East Rockaway Community Meeting Bay Park Sewage Treatment Plant September 17, 2014

  2. Meeting Agenda • Review of Last Meeting • Milestones and Timeline • Active construction projects • Schedule • Plant treatment performance • Questions 2 7 October 2014

  3. Review of Last Meeting • Community Concerns: • Temporary engine generator noise • Soil quality • Construction-related dust • Additional lighting in Park • Maintaining trees and berm in the Park 3 7 October 2014

  4. Milestones and Timeline 4 7 October 2014

  5. Schedule Update – Capital Projects Construction Existing Capital Projects Construction Start Complete Odor Control at Bay Park & Cedar Creek 28-Oct-13 12-Oct-15 Influent Screening Facility Improvements 27-May-14 24-Nov-16 Grit Removal Facility Improvements 30-Sept-14 23-Aug-16 Sludge Thickening Facility Improvements 28-Oct-13 27-Oct-15 Cleaning & Repair of Digesters & Storage Tanks 20-May-13 28-May-15 Generator Controls 15-Nov-13 20-Apr-15 Construction Hurricane Sandy Pump Stations Projects Construction Start Complete Dock Place & Southland Drive 28-Oct-13 19-Sept-14 Cedar, Roosevelt, Whitewood, Biltmore & Alhambra 04-May-15 03-Nov-16 Wantagh, Newbridge, Merrick & Ray 20-Apr-15 20-Oct-16 Millar, Mott, Long Beach, Royal & Lido 04-May-15 03-Nov-16 Ocean, Mill, Woodmere, Longagree & Doxey 04-May-15 03-Nov-16 East, Inwood, Doughty & Bayview 4-May-15 3-Nov-16 Roslyn Road 4-May-15 3-Nov-16 Barnes Ave SSO & Hempstead Flow Diverson 11-May-15 10-Nov-16 5 7 October 2014

  6. Schedule Update – Capital Projects Construction Construction Hurricane Sandy Projects Start Complete Final Settling Tank Rehabilitation 28-Oct-13 27-Oct-15 Phase E1 Electrical Distribution System Improvements 27-May-14 26-Mar-16 Phase E2 Substation No.2 & Electrical Distribution 29-Dec-14 28-Oct-16 Phase E3 Main Substation & Electrical Distribution 18-May-15 28-Dec-17 Perimeter Flood Protection 27-May-14 4-Jun-16 Flood Protection Phase 1 Stormwater Pumping Stations 24-Aug-15 06-Sept-17 Flood Protection Phase 2 Stormwater Green Infrastructure 4-Jul-17 3-Jul-18 Sludge Dewatering 22-Jun-15 21-Jun-18 Sludge Dewatering Demolition 11-Sept-14 09-Mar-15 Vehicle Fueling & Tanks Reconstruction 30-Sept-14 26-June-15 Effluent Tide Pumping Building 07-Sept-15 14-Nov-17 Effluent Screening & Disinfection 04-Jan-16 17-Jan-18 Digesters 26-Mar-16 04-Apr-18 Secondary Treatment 21-Mar-16 04-Apr-18 Influent Screens & RSPs 4-Jan-16 17-Jan-18 Grit Removal & Primary Settling 21-Mar-16 04-Apr-18 Central & Distributed HVAC 26-Mar-16 06-Oct-17 Odor Control Systems 21-Mar-16 06-Oct-17 General Plant Site Facilities 21-Mar-16 04-Apr-18 Sludge Thickening 24-Mar-16 12-Apr-17 Lawrence STP & Sage Lake PS 19-Oct-15 20-Apr-17 6 7 October 2014

  7. Plant Treatment Performance 7 7 October 2014

  8. Plant Treatment Performance 8 7 October 2014

  9. Active Construction Projects - East Park 9 7 October 2014

  10. Active Construction Projects - East Park 10 7 October 2014

  11. Active Construction Projects - Perimeter Flood Protection 11 7 October 2014

  12. Active Construction Projects - Perimeter Flood Protection 12 7 October 2014

  13. Active Construction Projects - Perimeter Berm 13 7 October 2014

  14. Active Construction Projects - Perimeter Berm 14 7 October 2014

  15. Active Construction Projects - West Berm 15 7 October 2014

  16. Active Construction Projects - West Berm 16 7 October 2014

  17. Active Construction Projects - Plant-wide Odor Control Upgrades 17 7 October 2014

  18. Active Construction Projects - Plant-wide Odor Control Upgrades 18 7 October 2014

  19. Active Construction Projects - Plant-wide Odor Control Upgrades 19 7 October 2014

  20. Active Construction Projects - Primary Source Power Generation Controls Rehabilitation 20 7 October 2014

  21. Active Construction Projects - Primary Source Power Generation Controls Rehabilitation 21 7 October 2014

  22. Active Construction Projects - Digesters Repair & Cleaning 22 7 October 2014

  23. Active Construction Projects - Sludge Thickening Improvements 23 7 October 2014

  24. Active Construction Projects - Final Settling Tank Rehabilitation 24 7 October 2014

  25. Active Construction Projects - Phase E1 Electrical Distribution System 25 7 October 2014

  26. Active Construction Projects - Phase E1 Electrical Distribution System 26 7 October 2014

  27. Active Construction Projects - Phase E1 Relocation of Site Utilities 27 7 October 2014

  28. Your Questions

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend