East Rockaway Community Meeting
Bay Park Sewage Treatment Plant September 17, 2014
East Rockaway Community Meeting Bay Park Sewage Treatment Plant - - PowerPoint PPT Presentation
East Rockaway Community Meeting Bay Park Sewage Treatment Plant September 17, 2014 Meeting Agenda Review of Last Meeting Milestones and Timeline Active construction projects Schedule Plant treatment performance Questions 2
Bay Park Sewage Treatment Plant September 17, 2014
7 October 2014 2
7 October 2014 3
7 October 2014 4
7 October 2014 5
Existing Capital Projects Construction Start Construction Complete Odor Control at Bay Park & Cedar Creek 28-Oct-13 12-Oct-15 Influent Screening Facility Improvements 27-May-14 24-Nov-16 Grit Removal Facility Improvements 30-Sept-14 23-Aug-16 Sludge Thickening Facility Improvements 28-Oct-13 27-Oct-15 Cleaning & Repair of Digesters & Storage Tanks 20-May-13 28-May-15 Generator Controls 15-Nov-13 20-Apr-15 Hurricane Sandy Pump Stations Projects Construction Start Construction Complete Dock Place & Southland Drive 28-Oct-13 19-Sept-14 Cedar, Roosevelt, Whitewood, Biltmore & Alhambra 04-May-15 03-Nov-16 Wantagh, Newbridge, Merrick & Ray 20-Apr-15 20-Oct-16 Millar, Mott, Long Beach, Royal & Lido 04-May-15 03-Nov-16 Ocean, Mill, Woodmere, Longagree & Doxey 04-May-15 03-Nov-16 East, Inwood, Doughty & Bayview 4-May-15 3-Nov-16 Roslyn Road 4-May-15 3-Nov-16 Barnes Ave SSO & Hempstead Flow Diverson 11-May-15 10-Nov-16
7 October 2014 6
Hurricane Sandy Projects Construction Start Construction Complete Final Settling Tank Rehabilitation 28-Oct-13 27-Oct-15 Phase E1 Electrical Distribution System Improvements 27-May-14 26-Mar-16 Phase E2 Substation No.2 & Electrical Distribution 29-Dec-14 28-Oct-16 Phase E3 Main Substation & Electrical Distribution 18-May-15 28-Dec-17 Perimeter Flood Protection 27-May-14 4-Jun-16 Flood Protection Phase 1 Stormwater Pumping Stations 24-Aug-15 06-Sept-17 Flood Protection Phase 2 Stormwater Green Infrastructure 4-Jul-17 3-Jul-18 Sludge Dewatering 22-Jun-15 21-Jun-18 Sludge Dewatering Demolition 11-Sept-14 09-Mar-15 Vehicle Fueling & Tanks Reconstruction 30-Sept-14 26-June-15 Effluent Tide Pumping Building 07-Sept-15 14-Nov-17 Effluent Screening & Disinfection 04-Jan-16 17-Jan-18 Digesters 26-Mar-16 04-Apr-18 Secondary Treatment 21-Mar-16 04-Apr-18 Influent Screens & RSPs 4-Jan-16 17-Jan-18 Grit Removal & Primary Settling 21-Mar-16 04-Apr-18 Central & Distributed HVAC 26-Mar-16 06-Oct-17 Odor Control Systems 21-Mar-16 06-Oct-17 General Plant Site Facilities 21-Mar-16 04-Apr-18 Sludge Thickening 24-Mar-16 12-Apr-17 Lawrence STP & Sage Lake PS 19-Oct-15 20-Apr-17
7 October 2014 7
7 October 2014 8
7 October 2014 9
7 October 2014 10
7 October 2014 11
7 October 2014 12
7 October 2014 13
7 October 2014 14
7 October 2014 15
7 October 2014 16
7 October 2014 17
7 October 2014 18
7 October 2014 19
7 October 2014 20
7 October 2014 21
7 October 2014 22
7 October 2014 23
7 October 2014 24
7 October 2014 25
7 October 2014 26
7 October 2014 27