East Rockaway Community Meeting Bay Park Sewage Treatment Plant September 17, 2014 Meeting Agenda Review of Last Meeting Milestones and Timeline Active construction projects Schedule Plant treatment performance Questions 2


slide-1
SLIDE 1

East Rockaway Community Meeting

Bay Park Sewage Treatment Plant September 17, 2014

slide-2
SLIDE 2

7 October 2014 2

Meeting Agenda

  • Review of Last Meeting
  • Milestones and Timeline
  • Active construction projects
  • Schedule
  • Plant treatment performance
  • Questions
slide-3
SLIDE 3

7 October 2014 3

Review of Last Meeting

  • Community Concerns:
  • Temporary engine generator noise
  • Soil quality
  • Construction-related dust
  • Additional lighting in Park
  • Maintaining trees and berm in the Park
slide-4
SLIDE 4

7 October 2014 4

Milestones and Timeline

slide-5
SLIDE 5

7 October 2014 5

Schedule Update – Capital Projects

Existing Capital Projects Construction Start Construction Complete Odor Control at Bay Park & Cedar Creek 28-Oct-13 12-Oct-15 Influent Screening Facility Improvements 27-May-14 24-Nov-16 Grit Removal Facility Improvements 30-Sept-14 23-Aug-16 Sludge Thickening Facility Improvements 28-Oct-13 27-Oct-15 Cleaning & Repair of Digesters & Storage Tanks 20-May-13 28-May-15 Generator Controls 15-Nov-13 20-Apr-15 Hurricane Sandy Pump Stations Projects Construction Start Construction Complete Dock Place & Southland Drive 28-Oct-13 19-Sept-14 Cedar, Roosevelt, Whitewood, Biltmore & Alhambra 04-May-15 03-Nov-16 Wantagh, Newbridge, Merrick & Ray 20-Apr-15 20-Oct-16 Millar, Mott, Long Beach, Royal & Lido 04-May-15 03-Nov-16 Ocean, Mill, Woodmere, Longagree & Doxey 04-May-15 03-Nov-16 East, Inwood, Doughty & Bayview 4-May-15 3-Nov-16 Roslyn Road 4-May-15 3-Nov-16 Barnes Ave SSO & Hempstead Flow Diverson 11-May-15 10-Nov-16

slide-6
SLIDE 6

7 October 2014 6

Schedule Update – Capital Projects

Hurricane Sandy Projects Construction Start Construction Complete Final Settling Tank Rehabilitation 28-Oct-13 27-Oct-15 Phase E1 Electrical Distribution System Improvements 27-May-14 26-Mar-16 Phase E2 Substation No.2 & Electrical Distribution 29-Dec-14 28-Oct-16 Phase E3 Main Substation & Electrical Distribution 18-May-15 28-Dec-17 Perimeter Flood Protection 27-May-14 4-Jun-16 Flood Protection Phase 1 Stormwater Pumping Stations 24-Aug-15 06-Sept-17 Flood Protection Phase 2 Stormwater Green Infrastructure 4-Jul-17 3-Jul-18 Sludge Dewatering 22-Jun-15 21-Jun-18 Sludge Dewatering Demolition 11-Sept-14 09-Mar-15 Vehicle Fueling & Tanks Reconstruction 30-Sept-14 26-June-15 Effluent Tide Pumping Building 07-Sept-15 14-Nov-17 Effluent Screening & Disinfection 04-Jan-16 17-Jan-18 Digesters 26-Mar-16 04-Apr-18 Secondary Treatment 21-Mar-16 04-Apr-18 Influent Screens & RSPs 4-Jan-16 17-Jan-18 Grit Removal & Primary Settling 21-Mar-16 04-Apr-18 Central & Distributed HVAC 26-Mar-16 06-Oct-17 Odor Control Systems 21-Mar-16 06-Oct-17 General Plant Site Facilities 21-Mar-16 04-Apr-18 Sludge Thickening 24-Mar-16 12-Apr-17 Lawrence STP & Sage Lake PS 19-Oct-15 20-Apr-17

slide-7
SLIDE 7

7 October 2014 7

Plant Treatment Performance

slide-8
SLIDE 8

7 October 2014 8

Plant Treatment Performance

slide-9
SLIDE 9

7 October 2014 9

Active Construction Projects - East Park

slide-10
SLIDE 10

7 October 2014 10

Active Construction Projects - East Park

slide-11
SLIDE 11

7 October 2014 11

Active Construction Projects - Perimeter Flood Protection

slide-12
SLIDE 12

7 October 2014 12

Active Construction Projects - Perimeter Flood Protection

slide-13
SLIDE 13

7 October 2014 13

Active Construction Projects - Perimeter Berm

slide-14
SLIDE 14

7 October 2014 14

Active Construction Projects - Perimeter Berm

slide-15
SLIDE 15

7 October 2014 15

Active Construction Projects - West Berm

slide-16
SLIDE 16

7 October 2014 16

Active Construction Projects - West Berm

slide-17
SLIDE 17

7 October 2014 17

Active Construction Projects - Plant-wide Odor Control Upgrades

slide-18
SLIDE 18

7 October 2014 18

Active Construction Projects - Plant-wide Odor Control Upgrades

slide-19
SLIDE 19

7 October 2014 19

Active Construction Projects - Plant-wide Odor Control Upgrades

slide-20
SLIDE 20

7 October 2014 20

Active Construction Projects -

Primary Source Power Generation Controls Rehabilitation

slide-21
SLIDE 21

7 October 2014 21

Active Construction Projects -

Primary Source Power Generation Controls Rehabilitation

slide-22
SLIDE 22

7 October 2014 22

Active Construction Projects - Digesters Repair & Cleaning

slide-23
SLIDE 23

7 October 2014 23

Active Construction Projects - Sludge Thickening Improvements

slide-24
SLIDE 24

7 October 2014 24

Active Construction Projects - Final Settling Tank Rehabilitation

slide-25
SLIDE 25

7 October 2014 25

Active Construction Projects - Phase E1 Electrical Distribution System

slide-26
SLIDE 26

7 October 2014 26

Active Construction Projects - Phase E1 Electrical Distribution System

slide-27
SLIDE 27

7 October 2014 27

Active Construction Projects - Phase E1 Relocation of Site Utilities

slide-28
SLIDE 28

Your Questions