Early Engagement Jeremy Dunster Manager Technical Services APPEA - - PowerPoint PPT Presentation

early engagement
SMART_READER_LITE
LIVE PREVIEW

Early Engagement Jeremy Dunster Manager Technical Services APPEA - - PowerPoint PPT Presentation

Early Engagement Jeremy Dunster Manager Technical Services APPEA Conference Adelaide, 14 May 2012 The Objective Facilities that are safe and without risk to the health of any person at or near them. 14 May 2012 A207354 2 The


slide-1
SLIDE 1

Early Engagement

Jeremy Dunster – Manager Technical Services

APPEA Conference Adelaide, 14 May 2012

slide-2
SLIDE 2

The Objective

Facilities that are safe and without risk to the health of any person at or near them.

14 May 2012 A207354 2

slide-3
SLIDE 3

The Operator’s General Duty

The operator of a facility must take all reasonably practicable steps to ensure

14 May 2012 A207354 3

that the facility is safe and without risk to the health of any person at or near the facility*

* Subclause 9(1)(a) of Schedule 3 to the Offshore Petroleum and Greenhouse Gas Storage Act 2006

slide-4
SLIDE 4

Where we are now

slide-5
SLIDE 5

Stages in the life of a facility

Context: Legislative framework (Safety)

14 May 2012 A207354 5

Exploration & Appraisal Concept Evaluation Conceptual Design FEED Detailed Design Overseas Construction Field Construct & Install Operate (Production) Modify

Decommission

P(SL)A Schedule P(SL)A MoSoF Regulations OPS Regulations OPGGS(S) Regulations

slide-6
SLIDE 6

Context: The Rise of Gas

14 May 2012 A207354 6

slide-7
SLIDE 7

Early Engagement Today: Provisions

14 May 2012 A207354 7

Exploration & Appraisal Concept Evaluation Conceptual Design FEED Detailed Design Overseas Construction Field Construct & Install Production Modify

Decommission

SoV Flexibility Fee for assessment of a safety case for a proposed Facility Submission for Assessment, Scope, Feedback

SC

slide-8
SLIDE 8

14 May 2012 A207354 8

Safety Management System Description Formal Safety Assessment Description Monitor, Audit and Review Facility Description

Description of Technical Controls including:

Emergencies Activities and O perating Parameters G eneral Description

(the layout of the facility)

Machinery and Equipment Safety Measures HAZID Risk Assessment Emergencies (EERA, FERA) Performance Standards

Description of Procedural Controls including:

Identification of Control Measures Implementation and Improvement of the SMS Scope (Activities) O HS Risk Management Maintenance Communication Emergencies Safety Measures

C

  • rrective &

Preventative action Implemented & F unctional? Implemented & F unctional?

Comprehensive and Integrated

Monitor, Audit and Review

slide-9
SLIDE 9

SC SC FID Concept Selected

Early Engagement Safety Case Assessments to-date

Early Engagement Today: Participants

14 May 2012 A207354 9

Concept Evaluation Conceptual Design FEED Detailed Design Overseas Construction Field Construct & Install Production

slide-10
SLIDE 10

Early Engagement Today: Experiences

  • Positive feedback regarding process
  • Useful introduction for new operators
  • A limited opportunity to question:

– Safety & design philosophies – Concept selection – Design choices – ALARP demonstration

14 May 2012 A207354 10

slide-11
SLIDE 11

Early Engagement Today: Challenges

  • No provisions for Concept selection & Design
  • Dialog constraints (requests for further information)
  • Decision making focus of the regulations
  • Optional process, no submission trigger

= Sub-optimal arrangements with limited potential to improve safety outcomes.

14 May 2012 A207354 11

slide-12
SLIDE 12

Drivers for change

slide-13
SLIDE 13

Reasonable Practicability

14 May 2012 A207354 13

Cost to avert Risk

slide-14
SLIDE 14

Bounded Practicability: The Risk Playing Field(s)

14 May 2012 A207354 14

High Risk Low Risk Concept Design Construct, Install, Operate, Modify, Decommission

slide-15
SLIDE 15

Reasonable Practicability: Passage of time

14 May 2012 A207354 15

Concept Evaluation Conceptual Design FEED Detailed Design Overseas Construction Field Construct & Install Production Starts

Concept Selected FID SC SC

Time

Cost to change Reasonable

  • pportunity to

challenge

slide-16
SLIDE 16

Where we are headed

slide-17
SLIDE 17

Future Directions: work in progress

  • Research & evaluation of options
  • Design notification:

– Focus on concept selection & design – Required for production facilities – Submitted no later than a Field Development Plan – Basis for ongoing dialog transitioning into submission of a safety case

14 May 2012 A207354 17

slide-18
SLIDE 18

Conclusion

14 May 2012 A207354 18

Effective provisions for early engagement: increasing the likelihood that future production facilities are safer and with lower risk to the health of any person at or near them.

slide-19
SLIDE 19

Our Vision

A safe and environmentally responsible Australian offshore petroleum industry.

Our Mission

To independently and professionally regulate offshore safety, integrity and environmental management.