Dynamic Mapping of ERCOT Interconnection Process Gavin Dillingham, - - PowerPoint PPT Presentation

dynamic mapping of ercot interconnection process
SMART_READER_LITE
LIVE PREVIEW

Dynamic Mapping of ERCOT Interconnection Process Gavin Dillingham, - - PowerPoint PPT Presentation

Dynamic Mapping of ERCOT Interconnection Process Gavin Dillingham, PhD Satish Ravindran P.E, CEM, LEED Green Assoc. HARC Agenda Interconnecting in Texas Greater than 10 MW Process Requirements Introduce Interconnection Dynamic


slide-1
SLIDE 1

Dynamic Mapping of ERCOT Interconnection Process

Gavin Dillingham, PhD Satish Ravindran P.E, CEM, LEED Green Assoc. HARC

slide-2
SLIDE 2

Agenda

  • Interconnecting in Texas – Greater than 10 MW
  • Process Requirements
  • Introduce Interconnection Dynamic Mapping Tool
slide-3
SLIDE 3

SECO DOE Project

  • Regulatory and Policy Barriers to CHP

– Department of Energy and State Energy Conservation Office – SEP

  • Air Permitting
  • Stand-by Rates
  • Power Export
  • Interconnection
slide-4
SLIDE 4

Interconnection > 10MW – Stakeholder interviews

  • Interconnection process > 10 MW is

DEMANDING

  • Two thirds of projects in state > 10MW
  • Process times average 270 days to 1020 days
  • Process times average 270 days to 1020 days
  • ERCOT transmission infrastructure is strained-

requires expensive upgrades

  • Unclear understanding of modeling

requirements

slide-5
SLIDE 5

Interconnection > 10MW – What we heard from ERCOT

  • Developers may use incorrect equipment – does

not match with study

  • Uncertainty of modeling data required by

developers developers

  • Incorrect understanding of process and documents
  • Timelines are not followed
  • Upgrades to infrastructure takes a long time
  • Telemetry not set up properly
slide-6
SLIDE 6

Interconnection > 10 MW

  • Affects Project Design and

Economics

  • Developers need deeper

understanding of the technical requirements of process requirements of process

  • Solid understanding of market

protocols and operating guides

  • Closer communication

between TSP, ERCOT and developers

slide-7
SLIDE 7

Process Requirements

  • Stringent ERCOT Compliance Review
  • Increasing Technical Data Requirements
  • Complex Facility studies
  • Complex Facility studies
  • Generator Modeling requirements differ for

each project

  • Testing and Telemetry requirements
slide-8
SLIDE 8

Process Flow Map

slide-9
SLIDE 9

Online Interconnection Wizard

  • An interactive / simplified Users Guide
  • Avoid paperwork delays and incorrect

submissions

  • A system to notify approaching deadlines
  • Avoid communication delays
  • Breaks complicated steps into simplified single

task sub-steps

slide-10
SLIDE 10

Online Interconnection Wizard

  • Keep track of timelines
  • Tips and Tricks based of feedbacks from other

stakeholders –common pitfalls, incorrect information etc. information etc.

  • One place to manage multiple projects
slide-11
SLIDE 11

Online Interconnection Wizard

slide-12
SLIDE 12

Online Interconnection Wizard

slide-13
SLIDE 13

Online Interconnection Wizard

slide-14
SLIDE 14

Online Interconnection Wizard

slide-15
SLIDE 15

Online Interconnection Wizard

slide-16
SLIDE 16

Online Interconnection Wizard

slide-17
SLIDE 17

Online Interconnection Wizard

slide-18
SLIDE 18

Online Interconnection Wizard

slide-19
SLIDE 19

Online Interconnection Wizard

slide-20
SLIDE 20

Online Interconnection Wizard

slide-21
SLIDE 21

Online Interconnection Wizard

slide-22
SLIDE 22

Online Interconnection Wizard