PUBLIC
The (Continuing) Evolution of the ERCOT System
Dan Woodfin
- Sr. Director, System Operations, ERCOT
The (Continuing) Evolution of the ERCOT System Dan Woodfin Sr. - - PowerPoint PPT Presentation
The (Continuing) Evolution of the ERCOT System Dan Woodfin Sr. Director, System Operations, ERCOT PUBLIC The ERCOT Region The interconnected electrical system serving 90% of Texas load, with limited external connections 73,308 MW
PUBLIC
PUBLIC
The interconnected electrical system serving 90% of Texas load, with limited external connections
(July 19, 2018)
(75,000 km) of transmission lines
ERCOT connections to other grids are limited to ~1250 MW of direct current (DC) ties, which allow control over flow of electricity
600 MW with SPP 30 MW with Mexico at Eagle Pass 100 MW with Mexico at Laredo 300 MW with Mexico at McAllen
2
220 MW with SPP
TSDOS 9/6/18
PUBLIC
assigned four primary responsibilities by the Texas Legislature:
3
ERCOT is not a market participant and does not own generation or transmission/distribution wires.
TSDOS 9/6/18
PUBLIC
4
Peak Demand Record: 73,308 megawatts (MW)
Weekend Peak Demand Record: 71,445 MW
Winter Peak Demand Record: 65,915 MW
Recent Monthly Peak Demand Records 2018
2017
*New records are preliminary, subject to change in final settlement
TSDOS 9/6/18
PUBLIC
PUBLIC
6
and other factors affect construction decisions and schedules.
Future outcomes uncertain
Wind Generation Records (instantaneous)
‒
‒
‒ Total Load = 28,416 MW
TSDOS 9/6/18
PUBLIC
20,000 40,000 60,000 80,000 100,000 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Nuclear Coal Other Gas CC Gas Steam Gas CT/IC Wind Solar
7
capacity (not adjusted for peak capacity contribution)
4.8% 51.6% 0.3% 28.6% 8.4% 5.3% 1.0% 5.3% 16.9% 35.9% 12.4% 6.6% 21.0% 1.1% 0.8%
TSDOS 9/6/18
PUBLIC
Nuclear 5% Coal 17% Gas CC 36% Gas Steam 12% Gas CT/IC 7% Wind 21% Solar 1% Other 1% Nuclear 8% Coal 29% Gas CC 5% Gas Steam 52% Gas CT/IC 5% Wind 0% Solar 0% Other 1%
1999 2018
TSDOS 9/6/18 8
PUBLIC
generation needed to maintain reliability.
minutes, using the generation with the lowest bids to serve the load, subject to transmission constraints.
signal whether more or less
in that area at that time.
process is the lowest cost way that doesn’t overload the transmission system to meet the system load for each five minute interval.
9
$2.54 $86.4 6
Prices
TSDOS 9/6/18
PUBLIC
10
TSDOS 9/6/18
PUBLIC
11 TSDOS 9/6/18
PUBLIC
PUBLIC
TSDOS 9/6/18 13
PUBLIC
14
Panhandle Projects
growing wind resources and weak grid conditions
Index Transmission Improvement 1 Alibates Synchronous Condenser 2 Tule Canyon Synchronous Condenser 3 Alibates-AJ Swope-Windmill Ogalalla- Tule Canyon 345 kV Circuit Addition
TSDOS 9/6/18
PUBLIC
15
Lubbock Integration
Light load switching into ERCOT
summer peak load
connected by multiple 345-kV lines
needed; will also provide new export capacity from Panhandle
TSDOS 9/6/18
PUBLIC
16 Transmission Improvement Project ERCOT Endorsement Anticipated Service Dates
Line 69H Rebuild and 138-kV Conversion Project October 2016 June 2018 Permian Basin-Solstice 138-kV line rebuild October 2016 February 2019 Riverton-Sand Lake 138-kV line (new) November 2016 May 2019 Far West Texas Project 1.0 (New Odessa-Riverton and Bakersfield-Solstice 345-kV lines) June 2017 May 2020 / April 2021 Far West Dynamic Reactive Devices June 2018 May/ December 2019 Far West Texas Project 2.0 (New Riverton-Sand Lake-Solstice 345-kV line and Kyle Ranch-Riverton and Horseshoe Spring- Riverton 138-kV lines) June 2018 December 2020
TSDOS 9/6/18
PUBLIC
PUBLIC
18 Future outcomes uncertain TSDOS 9/6/18
PUBLIC
19
Fuel Type Screening Study (MW) FIS Pending or Completed (MW) IA Executed, FIS Pending
(MW) Total (MW) Gas- All Other 779 1,972 2,751 Gas- Combined Cycle 3,292 2,046 3,165 8,503 Gas- Compressed Air 324 324 Total Gas 3,292 2,825 5,461 11,578 Nuclear Coal Wind 7,624 18,046 12,027 37,697 Battery 322 200 522 Solar 8,186 19,318 2,551 30,055
TSDOS 9/6/18
PUBLIC
Geographic Spread of Solar Interconnection Studies
20 TSDOS 9/6/18
PUBLIC
TSDOS 9/6/18 21
Load Higher than Forecasted Load Lower than Forecasted Wind Higher than Forecasted Wind Lower than Forecasted
3HR Ahead Forecast Errors - 2017
PUBLIC
TSDOS 9/6/18 22
address variability that cannot be covered by the five-minute energy market.
– Instantaneous Load Variation – Changes in variable generation output – Generators tripping offline – Forecast errors
designs and quantities continue to evolve to meet changing system needs and resource capabilities
PUBLIC
TSDOS 9/6/18 23
PUBLIC
PUBLIC
ERCOT
– If it injects to the grid; and – Is not registered with PUC as Self- Generation
– Annual DER interconnection reports to PUC – Regular updates to ERCOT Profile Codes
– Aggregated data on units >50 kW that inject energy to the grid – Some anecdotal summaries to City Councils, etc.
25
Based on this info, we estimate:
– About 30,000 units (mainly rooftop solar) – About 250 MW
– 140 units (~90% diesel
– More than 850 MW
TSDOS 9/6/18
PUBLIC
26
Modeled Equipment
CB-2 CB-1 Line-2 Line-1
Load-1 Load-2
Mapped Information DG-1
transmission grid
– Requires cooperation among TSPs, DSPs and the ISO – Underway now
– Local price signals would enhance reliability and would align DER behavior with overall market design
– e.g. forecasting, powerflow studies, dynamic analyses, A/S requirements, etc.
TSDOS 9/6/18
PUBLIC
27
500 1000 1500 2000 2500 3000 2018 2019 2020 2021 2022 Operational Signed IA FIS Requested Initial Request
within other GINRs
uncertainty and other factors affect construction decisions and schedules TSDOS 9/6/18
PUBLIC
TSDOS 9/6/18 28
PUBLIC
29 TSDOS 9/6/18
PUBLIC
30
ERCOT website – www.ercot.com
Social media – join us!
ERCOT mobile app
TSDOS 9/6/18