ASU Tempe Campus Durham Language and Literature Building Renovation Design Professional RFQ Pre-Submittal Meeting January 16, 2018 What Is the Need? Building Systems are Beyond their Useful Life Tenant Improvements for Current &


  1. ASU Tempe Campus Durham Language and Literature Building Renovation Design Professional RFQ Pre-Submittal Meeting January 16, 2018

  2. What Is the Need? • Building Systems are Beyond their Useful Life • Tenant Improvements for Current & New Users • Improved Entry and Lobby • ADA & Fire/Life Safety Upgrades • Technology/ Data Upgrades • Exterior Upgrades to Compliment Adjacent Buildings

  3. Old Main Alumni Lawn L&L University Club Fulton Building Site Map

  4. Existing Building

  5. Total Building=137,065 GSF South Wing- Floors LL-2 Central Tower- Floors LL-6 6 th Floor North Wing- Floors LL-4 7,717 GSF 2 nd Floor 5 th Floor 27,083 GSF 8,412 GSF 1 st Floor 4 th Floor 27,378 GSF 18,583 GSF 3 rd Floor Lower Level 28,622 GSF 18,580 GSF Overall Building Diagrams

  6. • Floors LL through 6 =137,065 gross square feet (GSF). • 77,041 net square feet (NSF) of usable space: o ~29,500 (NSF) Classroom Space o ~41,500 (NSF) Office o ~4,000 (NSF) Language Laboratory Space. o The remaining ~2,500 (NSF) is distributed amongst ancillary support space such as mechanical and electrical rooms. • The facility has an efficiency of approximately 56%. • The current occupants are primarily the School of International Letters and Cultures (SILC) and University Classrooms. • The Department of English recently vacated ~24,500 (NSF) o Primarily Floors 3, 5 and 6 Current Space Program

  7. Building Infrastructure/Systems Issues:  Abatement (By ASU)  Fire Alarm & Fire Sprinkler  Plumbing  HVAC (Existing Plenum System)  Electrical  Elevators  Security  Information Technology- WiFi & CAT6 Updates  Audio/Visual Technology Existing Infrastructure/ Systems

  8. Interior Improvements:  Common Space/Entry Lobby  Tenant Improvements for Current & New Users  Restrooms  Offices  Classrooms Exterior Improvements:  Exterior Skin  Exterior Doors  Windows  Window Louvers/Shades  Enhanced Connection between Cady Mall & Alumni Lawn Architectural/ Space Issues

  9. Cady Mall Desired Improvements Elevators • Improved Entry • Improved Lobby & Wayfinding Stairs • Connection of Cady Mall to Restrooms Alumni Lawn Alumni Lawn Entry and Lobby

  10. • 47 University Classrooms • Lower Level, 1 st and 2 nd Floors • Disruption to be Phased • Upgrade AV • Upgrade to CAT6 2 nd Floor • Upgrade WiFi • Update Building Systems • Update Classroom Finishes • ADA Compliance 1 st Floor Lower Level Existing Classrooms

  11. Tenant Improvement Expectations: • School of International Letters and Cultures- 26,000 SF • Associated Research & Outreach Centers- 9,000 SF • Existing Classrooms- 30,000 SF • Unassigned Office- 8,000 SF • Mechanical & Support- 5,000 SF Overall Expectations: • Updated Building Systems & Controls • Sustainable Design- LEED Silver • ADA and Fire/Life Safety Compliance • Interior and Exterior Finish Upgrades Renovated Building Expectations

  12. Total Project Budget: $45 million Project Schedule: • Multi-Phase Construction • All Phases Complete by Summer of 2021 Project Budget and Schedule

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.