dunmore sand and soil
play

Dunmore Sand and Soil Modif ific ication 2 2 - Stage 5 10 10 - PowerPoint PPT Presentation

Dunmore Sand and Soil Modif ific ication 2 2 - Stage 5 10 10 Apr April il 20 2019 19 Com Communit ity Brie riefin ing Pre Presenta tati tion DSS Mod 2 Briefing - Introduction Agenda Welcome - Paul Jackson (Stakeholder


  1. Dunmore Sand and Soil Modif ific ication 2 2 - Stage 5 10 10 Apr April il 20 2019 19 Com Communit ity Brie riefin ing Pre Presenta tati tion

  2. DSS Mod 2 Briefing - Introduction Agenda ● Welcome - Paul Jackson (Stakeholder Relations Manager) and Matthew Banks (DSS Quarry Manager) ● Overview of MOD 2 - Adnan Voloder (Planning and Development Manager) ● Ecology - Adnan Voloder and Simon Tweed (Niche Consulting) ● Water management - Ben Williams (Dunmore Environmental Co-ordinator) ● Other issues nominated by visitors/questions - Residents ● Conclusion

  3. DSS Mod 2 Briefing - Overview

  4. DSS Mod 2 Briefing - Overview

  5. DSS Mod 2 Briefing - Introduction ● Modification to existing approval to establish additional extraction areas (Stage 5) ● Extraction is proposed in two separate extraction areas, namely Stage 5A and 5B ● Stage 5A (immediately south of Riverside Drive) ● Stage 5B (to the north of ~ 370m Minnamurra River). ● Sand resource to be extracted is estimated at 234,000 t and approximately 1,123,000 t respectively ~ 420m ● Mobile plant and equipment will be operated across both extraction areas. Extraction methods will be identical to those in Stages 2 and 3.

  6. DSS Mod 2 Briefing - Stage 5A ● Stage 5A ● Establishment Process Clearing and grubbing of groundcover vegetation. Topsoil stripped and stockpiled, for later re- use in rehabilitation. Earth mounds will be formed using a dozer to construct the flood protection bunding for the dredge pond. ● Rehabilitation Stage 5A backfilled with VENM, topsoil spread and groundcover vegetation planted to return the land to pasture. ● Indicative timeframes 1-3 years

  7. DSS Mod 2 Briefing - Stage 5B ● Establishment Process Same as 5A ● Rehabilitation Stage 5B will be left as a freshwater pond, inline with existing practices implemented in Stage 2 - includes: ·Appropriate edging being implemented on the lake edge, to provide additional habitat for native fauna; ·Plant species planted along the lakes edges will be selected to maximise the bank stability; ·A fringing wetland community being created along the western and southern boundary, complemented by adjoining tree stands, improving habitat diversity; ·stabilise re-profiled areas as soon as possible, minimise potential erosion and degradation of areas of exposed topsoil. ● Indicative timeframes ~ 4-5 years

  8. DSS Mod 2 Briefing - Stage 5B - Rehabilitation

  9. DSS Mod 2 Briefing - Ecology ● Role of Ecologist ● Initial Engagement ● Survey work completed ● Findings of Surveys completed

  10. DSS Mod 2 Briefing - Ecology ● NSW major projects assessed under BC Act using 3-stage approach of: ○ Avoid ○ Mitigate ○ Offset ● Avoidance measures have focused on avoiding the majority of native vegetation and impacts on adjacent areas mapped as Coastal Wetlands including proximity areas. ● Mitigation measures will primarily involve clearing controls, a rehabilitation plan and protection of adjacent areas. ● Offsetting will be done in accordance with the NSW Biodiversity Assessment Methodology

  11. DSS Mod 2 Briefing - Ecology ● Disturbance footprint is not within the Coastal Wetlands Proximity Area (Buffer Area) and the Coastal Wetland itself. ● Design was specifically done to avoid impacts to coastal wetlands areas

  12. DSS Mod 2 Briefing - Ecology

  13. DSS Mod 2 Briefing - Ecology

  14. DSS Mod 2 Briefing - Ecology

  15. DSS Mod 2 Briefing - Ecology

  16. Current Operations Water Management: Stage 2 ● Stage 2 is the former dredge pond. It is being backfilled for rehabilitation. ● The pond is online to Rocklow Creek. The pond was kept offline until the size of the pond was maximised. ● There is a valved transfer pipe which can turn discharge offsite on/off. ● Water quality is measured monthly and after 20mm of rainfall in 24 hours. Monitoring points are shown in red.

  17. Current Operations - Site Discharge ● The re-aligned channel was designed to keep the Stage 3 dredge pond offline. ● The channel has been designed to allow settling of water in the case of high rainfall. ● Has been designed so it does not inhibit natural flows and to mimic the flow of the former Western Tributary channel. ● The water supply from Stage 2 to this channel is valved so the site can turn discharge on/off.

  18. Current Operations - Site Discharge

  19. Current Operations - Site Discharge

  20. Current Operations - Site Discharge

  21. DSS Mod 2 Briefing - Current Ops Water Management ● The Stage 3 pond is the current operational dredge pond. ● The circuit shown in yellow is kept offline to Rocklow Creek. No water flows from this offline circuit expect in the case of an overflow. ● The fines pond is protected by a 3.7m bund which was designed to protect against a 1 in 100 year rainfall event. ● Dredging and backfilling will cease if there is less than 30cm freeboard within the dredge pond. ● Water Quality is measured monthly. Monitoring points are shown in red.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend