DSU Modifications Gareth McLoughlin 12 November 2014 SONI Grid - - PowerPoint PPT Presentation
DSU Modifications Gareth McLoughlin 12 November 2014 SONI Grid - - PowerPoint PPT Presentation
DSU Modifications Gareth McLoughlin 12 November 2014 SONI Grid Code Review Panel Meeting 5 Modifications 1. Background 2. Frequency Requirements for Generation operated as part of a DSU 3. Application Form Data Requirements 4. Notice Time
5 Modifications
- 1. Background
- 2. Frequency Requirements for Generation
- perated as part of a DSU
- 3. Application Form Data Requirements
- 4. Notice Time
- 5. Signal Requirements
- 6. Performance Monitoring of DSU Dispatch
Instructions
- 7. Next Steps
Background
- 4 week consultation from 10th May to 7th Jun 2013 on
- riginal modifications with respect to DSU requirements.
- Details of the consultation available on SONI website:
– Consultations: http://www.soni.ltd.uk/Operations/GridCodes/documentation/consultations/ – Modifications: http://www.soni.ltd.uk/Operations/GridCodes/documentation/modifications/
- Comments in 2 responses received were addressed and
a Report issued to URegNI on 10th July 2013 seeking approval of changes.
- URegNI have indicated that they will not approve the
- riginal Modification, but will await a Report on the
further changes proposed for DSUs.
Frequency Requirements
- Each Demand Side Unit (or on-site generation operated as a continuous
Synchronous Generating Unit that forms part of a Demand Side Unit) shall, as a minimum, have the following capabilities:
- (h)
maintain Demand Side Unit MW Response at NI System Frequencies in the range 49.5Hz to 52Hz;
- (i)
maintain Demand Side Unit MW Response at NI System Frequencies within the range 48Hz to 49.5Hz for a duration of 1 hour;
- (j)
maintain Demand Side Unit MW Response at NI System Frequencies within the range 47.0Hz to 48Hz for a duration of 5 minutes; and
- (k)
maintain Demand Side Unit MW Response for a rate of change of NI System Frequency up to and including 1.0 Hz per second as measured over a rolling 500 milliseconds period.
- On-site Generation operating in DSU Short-term Synchronous Operating Mode
that forms part of a Demand Side Unit, shall, as a minimum, have the following capabilities:
- (p)
- perate continuously at normal rated output at NI System Frequencies in the
range 49.5Hz to 52Hz;
Frequency Requirements
EirGrid Requirement (Hz) Period Synchronised 49.5 – 50.5 Continuous 47.5 – 52.0 60 Mins 47.0 – 47.5 20 sec Short Term 49.5 – 50.5 Continuous SONI Requirement (Hz) Period Synchronised 49.5 – 52.0 Continuous 48.0 – 49.5 60 Mins 47.0 – 48.0 5 Mins Short Term 49.5 – 52.0 Continuous
Application Form Data Requirements
- Aligning application form data requirements on an
all-island basis, as much as possible.
- EirGrid have included ‘Modes of Operation’ of
Individual Demand Sites at request of ESB. SONI have included a new definition ‘DSU Short-term Synchronous Operating Mode’ in the glossary to provide clarity on the frequency requirements for generators that form part of a DSU.
- TSO-DSO engagement on-going regarding
application process. DSOs have differing views on
- this. TSO relaxed as who provides the information
as long as it is available.
DI Effective Time DI Effective Time
Notice Time
Signal Requirements
- total aggregated Demand Side Unit MW Response from Generation operating
as a continuous Synchronous Generating Unit;
- aggregated Demand Side Unit MW Response from Generation operating as a
continuous Synchronous Generating Unit per Bulk Supply Point;
- total aggregated Demand Side Unit MW Response from avoided Demand
consumption and Generation operating in DSU Short-term Synchronous Operating Mode;
- aggregated Demand Side Unit MW Response from avoided Demand
consumption and Generation operated in DSU Short-term Synchronous Operating Mode per Bulk Supply Point;
- Remaining Demand Side Unit MW Capacity Availability;
Signal Requirements
- Demand Side Unit MW Response from each Individual Demand Site with a
Demand Side Unit MW Capacity of greater than or equal to 5 MW;
- MW Output from Generation Units with a capacity greater than or equal to 5
MW;
- Mvar output from Generation Units with a capacity greater than or equal to 5
MW at Individual Demand Sites with a Maximum Export Capacity specified in the Connection Agreement or DNO Connection Agreement as applicable, as required by the TSO;
- Aggregate MW Output from Generation Units with a combined Capacity of
greater than or equal to 5 MW on an Individual Demand Site, as required by the TSO; and
- Demand Side Unit MW Response from each Individual Demand Site that
comprises the Demand Side Unit, as required by the TSO.
Performance Monitoring of DSU DIs
- Current Method
– DSU predicts D-1 aggregated demand of all Individual Demand Sites that comprise the DSU for each half-hour trading period of the trading day – Must be accurate to within 5% when not dispatched – Used as baseline when dispatched
- New Method
– Baseline calculated based on correlation with historical data – Worked example available on EirGrid Website:
- http://www.eirgrid.com/media/DSU_PM_of_DI_Worked_Example_DRAFT-
Multiple_Sheets_No_Formulas.xlsb
- http://www.eirgrid.com/media/DSU_PM_of_DI_Worked_Example_DRAFT-
Single_Sheet_Formulas.xlsb
Next Steps
- 4 week Consultation on NI Grid Code wording issued on
17th October 2014.
- As previous modifications have not been approved, the
consultation document covered both sets of modifications.
- Any comments that may be received are expected to be
- f a minor nature as working group has addressed most
issues already.
- Report will then be forwarded to URegNI seeking