diagnosis and restoration of a distressed dam case study
play

DIAGNOSIS AND RESTORATION OF A DISTRESSED DAM: CASE STUDY OF GUJ - PowerPoint PPT Presentation

DIAGNOSIS AND RESTORATION OF A DISTRESSED DAM: CASE STUDY OF GUJ ARAT, INDIA VIVEK P. KAPADIA GOVERNMENT OF GUJ ARAT INTRODUCTION Sabarkantha district in North Gujarat in India - completed before 10 years - river Meshwo INTRODUCTION GROSS


  1. DIAGNOSIS AND RESTORATION OF A DISTRESSED DAM: CASE STUDY OF GUJ ARAT, INDIA VIVEK P. KAPADIA GOVERNMENT OF GUJ ARAT

  2. INTRODUCTION Sabarkantha district in North Gujarat in India - completed before 10 years - river Meshwo

  3. INTRODUCTION GROSS STORAGE CAPACITY - 146 MILLION CUBIC FEET CATCHMENT AREA IS 371 SQUARE KILOMETERS - DESIGNED FLOOD WITH 1 IN 50 YEAR FREQUENCY IS 3774 CUBIC METER PER SECOND LENGTH OF THE SPILLWAY SECTION IS 101.80 METER - CONCRETE GRAVITY DAM WITH PROVIDED 9 VERTICAL GATES - HYDRAULIC J UMP TYPE STILLING BASIN - UPSTREAM AND DOWNSTREAM KEYS WERE 3.5 METER DEEP

  4. INTRODUCTION SIGNS OF DISTRESS IN ONLY 2 YEARS DOWNSTREAM GLACIS SLOPE 1:3 - TOE GOT DISINTEGRATED AND THE REINFORCEMENTS WERE PULLED OUT DOWNSTREAM APRON GOT DAMAGED BUT NOT IN THE ENTIRE LENGTH OF THE DA ONLY IN THE RIGHT HALF OF THE LENGTH I.E. RIVER’S HALF WIDTH

  5. INTRODUCTION PULLED OUT REINFORCEMENT

  6. INTRODUCTION PULLED OUT REINFORCEMENT AT TOE AND DAMAGED APRON

  7. DIAGNOSTIC ANALYSIS GLACIS WITH 1:3 SLOPE WAS INSUFFICIENT TO AVOID CAVITY FORMATION - THERE SHOULD HAVE BEEN A MUCH FLATTER SLOPE OR AN OGEE SOME RECORD - ORIGINALLY A BASALT MINE AS THE RIVER WAS HAVING GOOD QUALITY BASALT IN ITS BED - FOR PREPARATION OF THE SITE, THE DESIGN INCLUDED LEAN CONCRETE FILLING WITH LARGE COARSE AGGREGATE I.E. PLUM CONCRETE IN THE PIT SOME OTHER RECORDS WITH GEOLOGICAL MAPPING SUGGESTED THAT THE MINE WAS ONLY IN THE RIGHT HALF WIDTH OF THE RIVER AND THE DEPTH WAS ABOUT 9 METER

  8. DIAGNOSTIC ANALYSIS SCHEMATIC CROSS SECTION

  9. DIAGNOSTIC ANALYSIS LARGE COARSE AGGREGATES WERE IN PLACE - CEMENT AND SAND WERE IN LOOSE FORM - WATER BENEATH THE APRON IN THE VOIDS - DAM WAS FULL UP TO CREST LEVEL - IT WAS THE WATER FROM THE RESERVOIR CONDITION WAS EXTREMELY DANGEROUS - SUBSURFACE FLOW COULD RESULT IN TO UNDERMINING THE FOUNDATION AND COLLAPSE OF THE CONCRETE DAM ITSELF. WHEN WATER WAS RELEASED, IMPACT OF THE WATER FALL WAS TAKEN UP BY THE APRON WHICH REQUIRED A SOLID FOUNDATION WHICH ACTUALLY WAS NOT THERE - CONCRETE APRON USED TO SETTLE - SAGGING RESULTING IN TO DAMAGE AT THE BOTTOM AND TOP – BOTTOM DAMAGE WAS NOT VISIBLE BUT THE TOP WAS

  10. RESTORATION PLUM CONCRETE REMOVED UP TO 1.5 METER DEPTH – RICH CEMENT SAND MIX 1:4 WITH POLYMER POURED TO PLUG VOIDS IN PLUM CONCRETE LAYER OF 1.5 METETR THICKNESS OF RICH CONCRETE ADDITIONAL PERIPHERAL KEY OF 5 METER – FOUNDATION OF ABUTMENT STRENGTHENED CASTING OF APRON – REINFORCEMENT MESH AT TOP WELDED WITH TOE REINFORCEMENT – SURFACE HARDENER TO PROVIDE IMPACT RESISTANT SURFACE – FILLET AT TOE DOWNSTREAM RIVER CHANNEL REGRADED

  11. RESTORATION

  12. RESTORATION

  13. CONCLUSION PROBLEMS IN CIVIL ENGINEERING ARE VERY COMPLEX AND UNDERSTANDING THE REAL CAUSE OF THE PROBLEM IS THE MOST IMPORTANT ASPECT A SMALL ASPECT IGNORED AT THE CONSTRUCTION STAGE MAY LEAD TO DIFFICULT PROBLEMS EXPERIENCE AND INSIGHT NEEDED AS MOSTLY THE FINDINGS CAN BE REACHED BY WAY OF USING J UDGMENTAL AND INTUITIVE DECISIONS

  14. CONCLUSION SOMETIME THE DIAGNOSIS IS REQUIRED TO BE DONE STAGE-WISE ALONG WITH STEP BY STEP IMPLEMENTATION OF SOLUTION SEVERAL ACTIVITIES TO BE EXECUTED WITH PROPER SEQUENCE AND PROPER MATERIALS

  15. THANKS

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend