DGA Oncors Past, Present, and Future Dustin Best Russell W. Smith Hannah Webb SEPTEMBER 5 - 7, 2018 SEPTEMBER 5 - 7, 2018 Oncor Transformer Fleet Approximate Approximate Number of Number of DGA's Annually (not Transformer


slide-1
SLIDE 1

SEPTEMBER 5 - 7, 2018

DGA – Oncor’s Past, Present, and Future

Dustin Best Russell W. Smith Hannah Webb

slide-2
SLIDE 2

SEPTEMBER 5 - 7, 2018

slide-3
SLIDE 3

SEPTEMBER 5 - 7, 2018

Oncor Transformer Fleet

Transformer Approximate Number of Transformers Approximate Number of DGA's Annually (not including resamples) 3 Phase with LTC 1,232 2,464 3 Phase without LTC 718 718 1 Phase Substations 75 Total 2,025 3,182

slide-4
SLIDE 4

SEPTEMBER 5 - 7, 2018

slide-5
SLIDE 5

SEPTEMBER 5 - 7, 2018

1980’s

  • Early 1980’s

– Time-based maintenance on every LTC yearly and eventually moved to every 3 years.

  • Very Labor Intensive
  • Mid-Late 1980’s

– Dissolved Gas Analysis (DGA) began on main tanks.

  • Focus: Acetylene, Moisture Content, and Total

Combustible Gas

slide-6
SLIDE 6

SEPTEMBER 5 - 7, 2018

slide-7
SLIDE 7

SEPTEMBER 5 - 7, 2018

1990’s

  • Early-Mid 1990’s

– Time-based maintenance on every LTC moved to every 6 years or after 30,000 operations .

  • Unknown condition between the 6 years.
  • Late 1990’s

– Oncor committee formed to focus on the development of analyzing LTC DGAs.

  • Research cause of coking.
slide-8
SLIDE 8

SEPTEMBER 5 - 7, 2018

slide-9
SLIDE 9

SEPTEMBER 5 - 7, 2018

2000’s

  • Early 2000’s

– Committee began experimenting with arcing in oil and reviewing the gas relationships.

slide-10
SLIDE 10

SEPTEMBER 5 - 7, 2018

2000’s

  • Mid 2000’s

– Transition to automated DGA email notifications.

  • Reporting system used algorithms developed by the

committee to determine the condition of the asset.

  • Levels of Concern: caution, warning, wet, etc.
  • Notifications sent to specific lists of personnel.
  • Late 2000’s

– Single and Multi-gas online monitors evaluated for selected autotransformer main tanks.

slide-11
SLIDE 11

SEPTEMBER 5 - 7, 2018

slide-12
SLIDE 12

SEPTEMBER 5 - 7, 2018

2010’s

  • Early 2010’s

– Transition to a centralized asset data base with reporting capabilities.

  • Same algorithms utilized
  • Better organization and tracking
slide-13
SLIDE 13

SEPTEMBER 5 - 7, 2018

slide-14
SLIDE 14

SEPTEMBER 5 - 7, 2018

slide-15
SLIDE 15

SEPTEMBER 5 - 7, 2018

2010’s

  • Mid 2010’s

– Refinement of DGA notification algorithms on both main tanks and LTCs. – Single gas online monitors were specified to come on all new medium power transformers on both main tank and vacuum LTC.

DGA Notification Refinements Refinement Before After Reduced by Moisture tracking 695 154 541 LTC 802 222 580 Total 1497 376 1121

slide-16
SLIDE 16

SEPTEMBER 5 - 7, 2018

2010’s

  • Late 2010’s

– Basic DGA trending dashboard – Notifications setup for online monitors – Further refinement on DGA notifications

  • LTC model specific
slide-17
SLIDE 17

SEPTEMBER 5 - 7, 2018

slide-18
SLIDE 18

SEPTEMBER 5 - 7, 2018

Beyond

  • Advanced DGA Fleet Dashboard

– Arrange assets in order of highest concern

  • Asset Health Score

– Prioritize maintenance and/or proactive replacements based on score

slide-19
SLIDE 19

SEPTEMBER 5 - 7, 2018

Conclusion

Transformers 19 LTCs 36 Saves Based on DGAs (2016 to 2018)