decision on the iso 2016 2017 transmission plan
play

Decision on the ISO 2016-2017 Transmission Plan Neil Millar - PowerPoint PPT Presentation

Decision on the ISO 2016-2017 Transmission Plan Neil Millar Executive Director, Infrastructure Development Board of Governors Meeting General Session March 15-16, 2017 ISO Confidential Approving the plan means approving determinations and


  1. Decision on the ISO 2016-2017 Transmission Plan Neil Millar Executive Director, Infrastructure Development Board of Governors Meeting General Session March 15-16, 2017 ISO Confidential

  2. Approving the plan means approving determinations and recommendations contained in the plan. • Two transmission projects: – Both are new reliability projects each of which is less than $50 million – no policy driven projects – no economically driven projects • Canceling 13 - primarily local – previously approved projects in PG&E’s service area • Identifying 16 transmission projects requiring further evaluation in the 2017-2018 planning cycle No regional transmission solutions found to be needed are eligible for competitive solicitation Page 2 ISO Confidential

  3. The 2016-2017 Transmission Planning Process Four Consultation Windows April 2016 March 2017 October 2017 ISO Board Approval of Transmission Plan Coordination of Conceptual Statewide Plan Phase 3 • Request for bids, receive Phase 1 proposals, evaluate, and award to successful Development of ISO unified applicant to build identified planning assumptions and Phase 2 reliability, policy and study plan Technical Studies and Board Approval economic transmission projects. • State and Federal policy • Reliability analysis requirements and directives • Renewable delivery (policy) analysis • Demand forecasts, energy • Economic analysis efficiency, demand response • Consider Transmission Alternatives, e.g. preferred resources and energy storage. • Renewable and conventional generation • Publish comprehensive transmission plan additions and retirements • Input from stakeholders Continued regional and sub-regional coordination Slide 3 ISO Confidential

  4. Transmission approvals over the last 6 years – over 30 projects a year until 2014-2015: $2,500 Delaney-Colorado River and Harry Allen-Eldorado $2,000 Capital Cost in $ millions $1,500 Economic $1,000 Policy Reliability $500 $0 Transmission Plan Page 4 ISO Confidential

  5. The ISO’s reliability analysis led to the following: • Two reliability projects are recommended in SCE’s service territory: – Lugo-Victorville 500 kV Upgrade - coordinated with LADWP ($18 million – SCE portion) – Big Creek Rating Increase Project ($6 million) • In the PG&E service territory: – 13 previously approved projects are recommended to be cancelled – 15 have been identified as needing further review and scoping - 5 will proceed with concluding siting activities • One project in the SDG&E area needs further review Page 5 ISO Confidential

  6. 13 projects are no longer required based on reliability and local capacity requirements and deliverability assessments: • Pease-Marysville #2 60 kV Line • Almaden 60 kV Shunt Capacitor • Monta Vista – Los Gatos – Evergreen 60 kV Project • Lockheed No. 1 115 kV Tap Reconductor • Mountain View/Whisman-Monta Vista 115 kV Reconductoring • Stone 115 kV Back-tie Reconductor • Kearney - Kerman 70 kV Line Reconductor • Cressey - North Merced 115 kV Line Addition • Taft-Maricopa 70 kV Line Reconductor • Natividad Substation Interconnection • Soledad 115/60 kV Transformer Capacity • Tesla-Newark 230 kV Path Upgrade • Vaca Dixon-Lakeville 230 kV Reconductoring Slide 6 ISO Confidential

  7. Projects on hold and completing engineering activities • Management has identified that further review of the need and scope for the following PG&E-area projects is required in the 2017-2018 planning cycle. – Midway-Andrew 230 kV Project – Spring Substation – Wheeler Ridge Junction Substation – Lockeford-Lodi Area 230 kV Development – Vaca-Davis Voltage Conversion Project – • Management is recommending that the project sponsors do not proceed with filings for permitting and certificates of public convenience and necessity until the ISO completes the reviews. • Completing the design and siting permitting activities (but not filing for permits) will assist in the reviews. Slide 7 ISO Confidential

  8. Projects on hold with all development suspended • For the following PG&E area projects, all development activities are recommended to be put on hold until a review is complete. – Gates-Gregg 230 kV Line – Watsonville Voltage Conversion – Atlantic-Placer 115 kV Line – Northern Fresno 115 kV Area Reinforcement – South of San Mateo Capacity Increase – Evergreen-Mabury Conversion to 115 kV – New Bridgeville Garberville No. 2 115 kV Line – Cottonwood-Red Bluff No. 2 60 kV Line Project and Red Bluff Area 230 kV Substation Project – Kern PP 115 kV Area Reinforcement – Wheeler Ridge-Weedpatch 70 kV Line Reconductor • In the SDG&E area, the Mission-Penasquitos project requires further review. Slide 8 ISO Confidential

  9. Oakland Area – reviewing potential alternatives for existing fossil-fueled Oakland Power Plant • The ISO is working with Dynegy to assess the expected life of the plant, to aid in developing alternatives to address the reliability needs currently met by the plant. • • The alternatives that the ISO considered in the 2015-2016 transmission planning process remain valid to address the reliability needs. • The leading alternative at this time is a combination of transmission upgrades and preferred resources - a portfolio of demand response, energy efficiency, distributed generation and storage. • • The ISO will continue to work with the Dynegy and PG&E and reassess the situation in the 2017-2018 transmission planning process. Slide 9 ISO Confidential

  10. The ISO’s policy-driven analysis focused on the 33% Renewables Portfolio Standard:  For assessing policy-driven transmission, the CPUC and CEC provided direction on June 13, 2016 to re-use the same 33% RPS portfolios as in 2015-2016 cycle and avoid triggering new transmission for a 50% RPS at this time.  For the policy driven analysis with 33% RPS portfolios, the ISO studied only on the Imperial, Baja and Arizona areas due to changes in transmission plans in the Imperial Irrigation District from the 2015-2016 Transmission Plan. No policy- driven requirements were identified.  Note that the portfolios used in the ISO’s informational 50% RPS special studies were provided by CPUC staff through a collaborative effort, but not as the basis for policy-driven transmission Page 10 ISO Confidential

  11. Regional high voltage transmission access charge projection trended from January 1, 2017 values: $16 $15 $14.11 $14 $13.91 $13 Regional $12 High Voltage TAC $11 2017 Projection with $/MWh recommended approvals $10 January 1 2017 HV TAC very close to January 1 2016 level $9 due to significantly larger 2016 Projection with negative TRBAA and other recommended $8 revenue requirement approvals offsetting adjustments. $7 $6 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 * Existing returns are maintained for existing PTO rate base, and 11% return on equity is assumed for new transmission capital. Slide 11 ISO Confidential

  12. Incremental impact of post-2016 capital expenditures related to all ISO-approved transmission projects $4.50 $4.00 $3.50 $3.00 Shift primarily due to increased forecast cost $2.50 of previously approved Incremental projects and, to a lesser Regional $2.00 degree, new capital High Voltage projects and other corrections $1.50 TAC $/MWh $1.00 Shift due to deferral of previously approved projects $0.50 $0.00 -$0.50 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2015-16 Plan - relative to 2016 2016-17 Plan - ISO Approved Expenditures * Existing returns are maintained for existing PTO rate base, and 11% return on equity is assumed for new transmission capital. Slide 12 ISO Confidential

  13. Six special studies on emerging issues were undertaken in this cycle:  Continuation of frequency response efforts through improved generator modeling  Risks of early economic retirement of gas fleet  50% renewable generation (in-state analysis, out of state analysis and Interregional Transmission Project evaluation)  Large scale storage benefits  Gas/electric reliability coordination  Slow response resources in local capacity areas Page 13 ISO Confidential

  14. Stakeholder feedback provided a wide range of views: • Concerns about specific projects, and the ISO’s basis for moving forward – Projects driven by high voltage concerns – Previously approved projects – Projects not recommended for approval • Deliverability of CPUC-provided 33% renewable generation portfolios for policy-driven transmission • Support for continuation of special studies Page 14 ISO Confidential

  15. Management recommends the Board approve the 2016-2017 ISO Transmission Plan. • Continues to pursue low emissions strategies in addressing reliability needs of the ISO controlled grid • Enables the state’s 33% RPS goals and sets a foundation for higher renewable energy goals • Provides for prudent and economic development of the transmission system Slide 15 ISO Confidential

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.