DE BEERS GAHCHO KU SUMMARY OF AMENDMENT APPLICATION Tree of Peace, - - PowerPoint PPT Presentation
DE BEERS GAHCHO KU SUMMARY OF AMENDMENT APPLICATION Tree of Peace, - - PowerPoint PPT Presentation
DE BEERS GAHCHO KU SUMMARY OF AMENDMENT APPLICATION Tree of Peace, Yellowknife 8:30-4:30 May 30-31, 2018 GAHCHO KU MINE Gahcho Kue is owned by a Joint Venture Partnership - De Beers (51%) - Mountain Province Diamonds (49%) Located
1 The De Beers Group of Companies
- Gahcho Kue is owned by a Joint Venture Partnership
- De Beers (51%)
- Mountain Province Diamonds (49%)
- Located 280 km northeast of Yellowknife, 140 km from
Lutsel K’e
- Open Pit Mine
- 5034 Pit
- Hearne Pit
- Tuzo Pit
- 2 Years of Construction
- 11.6 Years of Operation
- 2 Years of Active Closure
- 19 years of re-filling Kennady Lake
GAHCHO KUÉ MINE
2 The De Beers Group of Companies
2005 Application for a Type A Land Use Permit and Water Licence 2006 Environmental Assessment and Environmental Impact Review 2010 Environmental Impact Statement submitted 2012 EIS Supplement 2013 Responsible Ministers approved the Project 2013 Updated Project Description 2013 Early Earthworks Land Use Permit 2014 Type A Land Use Permit and Water Licence 2017 Land Use Permit Amendment #1 for Jet Fuel 2017 Land Use Permit Amendment #2 for Fine PK Facility 2018 Water Licence Amendment #1 & Land Use Permit Amendment #3 for Mine Rock 2018 Water Licence Amendment #2 for water use (Bridging amendment)
REGULATORY HISTORY
3 The De Beers Group of Companies
PROJECT OJECT DESCRIPTION DESCRIPTION Gahc hcho ho Kué Mi Mine ne
4 The De Beers Group of Companies
- A jo
join int is a break (fracture) of natural origin in the continuity of the rock
- A jo
join int set set is a family of parallel, evenly spaced joints
- When jo
join int sets ets are blasted, the blast pattern is affected
- Rock is not only breaking along vertical blast lines, but
also along the joint sets
- Result is a reduction of the catch benches – leading to a
safety issue for our workers below
- 5034 Pit has joint sets on the eastern wall
- Issue extends to Tuzo and Hearne
- Necessary to re-design the slope walls to accommodate
the additional break-back
A NEW CHALLENGE – JOINT SETS IN ALL THREE PITS
BFA 85°
90°
BFA 70°
2m 6m 24m
Planned break-back Actual break-back
5 The De Beers Group of Companies
BENCH WIDTHS MUST BE PRESERVED FOR SAFETY
6 The De Beers Group of Companies
HOW WILL THE PITS CHANGE AS A RESULT?
Pit (Worst Case) 2013 3 UPD (ha) a) 2018 8 UPD (ha) a) 5034 41 50 Tuzo 43 50 Hearne 24 32 Total 108 132 Difference 24
- Pit wall slopes will decrease
- Planned case: 41-50°
- Worst case: 41°east wall slopes
7 The De Beers Group of Companies
WHERE TO PUT THE EXTRA ROCK?
- Planned case = 65 Mt
- Worst case = 100 Mt
- Alternatives Analysis conducted to
examine each potential option
- Parameters considered:
- Feedback received from Aboriginal
Parties and during previous reviews
- Containment within Controlled Area
- Minimize footprint on land
- Minimize footprint in water
- Close to pits
- Minimize height increase
- Technical feasibility
8 The De Beers Group of Companies
WEST MINE ROCK PILE – OPTION A
Op Option A Capacity 130 Mt Height Increase 35 m Total Height 135 m Proximity to pits Close Land increase 7.8 ha Water increase 54.9 ha Key Features:
- Footprint remains within
Controlled Boundary
- Drainage watercourse
required at closure
9 The De Beers Group of Companies
- Sufficient space for
130 Mt
- More impact on land
- Close to pits
- Less underwater
storage of PAG
- Requires 1 drainage
watercourse to be constructed at closure
- Close to Controlled Area
Boundary
- Odd configuration
difficult for large trucks
- Pile up to 35m higher
WEST MINE ROCK PILE – OPTION B
Op Option B Capacity 130 Mt Height increase 35 m Total height 155 m Proximity to pits Close Land increase 23.5 ha Water increase 40.4 ha Key Features:
- Footprint within Controlled
Area Boundary
- Drainage watercourse
required at closure
- Odd configuration makes it
difficult for large trucks
10 The De Beers Group of Companies
MINE ROCK COVERED COARSE PK PILE – OPTION C
Option
- n C
Capacity 35 Mt Height Increase 70 m Total Height 100 m Proximity to pits Far Land Footprint 32.4 ha Water Footprint 14.3 ha Key Features:
- Insufficient space for
material
11 The De Beers Group of Companies
NEW MINE ROCK PILE IN AREA 6 – OPTION D
Option
- n D
Capacity 95 Mt Height Increase 95 m Total Height 95 m Proximity to pits Close to Hearne Land Footprint 60 ha Water Footprint 24 ha Key Features:
- New mine rock pile
- Insufficient space for
material
- Permanent removal of Area 6
- Would require long drainage
connection from E Lakes
12 The De Beers Group of Companies
OTHER OPTIONS CONSIDERED – AREA 7
Are rea 7 Op Opti tion 1 South of Area 7 m mostly on l land nd Key Features
- Limited height due to
airstrip flight obstacle limitation Area 7 Op Option 2 South of Area 7 c covering g both land and water Key Features
- Permanent alteration of
Area 7
- Limit Kennady Lake
reconnection at closure
13 The De Beers Group of Companies
WEST MINE ROCK PILE – FINAL SELECTED AND REFINED OPTION
Selecte ted and Refined ed Op Option Capacity 130 Mt Height increase 35 m Total height 135 m Proximity to pits Close Land increase 7.1 ha Water increase 55.4 ha Key Features
- Footprint within
Controlled Boundary
- Drainage watercourse
required at closure
14 The De Beers Group of Companies
HOW DOES THIS AFFECT OTHER ASPECTS OF MINE DEVELOPMENT?
15 The De Beers Group of Companies
Ope peration ional al
- Larger west mine rock pile
- Increased footprint
- Adjustments to planned discharge
- Discharge from Water Management Pond to N11 for 1 additional year
- Discharge from Area 7 to Area 8 periodically throughout Operations
- Additional camp occupancy
- Increased annual camp water intake
- Additional mining equipment and operating hours
- 7 months longer life of mine
Closure re
- Longer to refill Kennady Lake
- Watercourse required for closure to reconnect Watershed D to Kennady Lake
UPDATED PROJECT DESCRIPTION
16 The De Beers Group of Companies
LARGER WEST MINE ROCK PILE DESIGN
Design gn Land d (ha) Water (ha) Total (ha) Height t (m) PAG <420.7 masl masl (Mt) t) 2013 41.7 39.6 81.3 100 3.4 2018 48.8 95.0 143.8 135 10.8 Difference 7.1 55.4 62.5 35 7.4
2013 2018
- Close to the pits
- Uses existing disturbance
- Most footprint in WMP
- Requires drainage channel
at closure
- Two ramps incorporated
into design for wildlife access/egress
Drai rainag age e cha hannel el
17 The De Beers Group of Companies
2013 UPDATED PROJECT DESCRIPTION FOOTPRINT
Year Purpose Area (ha) 2014 2014 UPD 2013 1172
18 The De Beers Group of Companies
2017 APPROVED FOOTPRINT
Year Purpose Area (ha) 2014 2014 UPD 2013 1172 2015 2015 Dyke L haul road 5 2015 2015 Road to temporary laydown 1 2015 2015 Temporary laydowns 19.25 2014 2014 Airstrip re-alignment 17.5 2017 2017 ROM pad area 12 2017 2017 East pad extension 9 2017 2017 Jet fuel 0.25 2017 2017 FPKC expansion and AN building 30 Total 1266
19 The De Beers Group of Companies
2018 UPDATED PROJECT DESCRIPTION FOOTPRINT
Year Purpose Area (ha) 2014 2014 UPD 2013 1172 2015 2015 Dyke L haul road 5 2015 2015 Road to temporary laydown 1 2015 2015 Temporary laydowns 19.25 2014 2014 Airstrip re-alignment 17.5 2017 2017 ROM pad area 12 2017 2017 East pad extension 9 2017 2017 Jet fuel 0.25 2017 2017 FPKC expansion and AN building 30 2018 2018 Mine Rock Amendment 26 Total 1292
20 The De Beers Group of Companies
Dyke e G Dyke e H
WATER MANAGEMENT – OPERATIONS
- Discharge water from WMP to Lake N11
- Current W.L. = Annually for 3 years
- Amendment = Annually for 4 years
- Pump water from A1 to A8
- Current W.L. = Annually
- Pump water from Lake N11 to A8
- Current W.L. = 3 out of 4 years
- Pump Water from A7 to A8
- Amendment = Periodically
21 The De Beers Group of Companies
- 1 Additional Year of Discharge to Lake N11 (Year 4)
- Same annual allotment = 3.45 Mm3/ year
- Option in water license (Part G, item 34)
- EQC evaluation report submitted
- Request annual discharge to carry over anniversary date
- Discharge planned for Sept.1 to Nov.1
ADDITIONAL YEAR OF DISCHARGE TO LAKE N11 (YEAR4) Lake N11 Diffuser
Pipe Availability
Available Not Available
Water Quality
Adequate Not Adequate
M M A June A J O S N J F D
Available Discharge Period Sept.24
22 The De Beers Group of Companies
- Discharge from A7 to A8
- Secondary source of downstream flow water
- ~1.55 Mm3 as available during Life of Mine (~4 years)
- To reduce volume of water reporting to WMP
- EQC evaluation report submitted
- Existing W.L. permits 1 year of discharge from WMP to A8
- No discharge from WMP to A8 occurred to date
- No discharge from WMP to A8 is planned
- A7 as contingency storage area
- WMP water may be temporarily stored in A7
- WMP water would either be pumped back to the WMP or to a pit
- If discharge to A8 is required, an EQC evaluation report to be
submitted
DISCHARGE FROM AREA 7 TO AREA 8 (PERIODICALLY)
A8
23 The De Beers Group of Companies
Characteris risti tic 2013 (Upd pdate ted d Project t Descriptio iption) 2018 2018 (Mine Plan Upd pdate) e) Project ct Schedule ule
- Construction: 2 years
- Operations: 11 years
- Closure (interim): 2 years
- Closure: 12 to 23+ years
- Construction: 2 years
- Operations: 11.6 years
- Closure (interim): 2 years
- Closure: 19 + years
Mine sequence Hearne, 5034, and Tuzo 5034, Hearne, and Tuzo Produ duction tion rate 3 Mt of ore per year 3.15 Mt of ore per year Surface ce Disturb rbance e (mine footprin print) t) • Total = 1,172 ha
- Total = 1,292 ha
Pit depth ths
- Hearne Pit = 252 m
- 5034 Pit = 310 m
- Tuzo Pit = 360 m
- Hearne Pit = 216 m (up to 252m)
- 5034 Pit = 286 m (up to 310m)
- Tuzo Pit = 373 m (up to 373)
Total Amount of Mine Rock Rock
- 300 Mt
- 400 Mt
Placement t of Mine Rock Rock
- West Rock Pile = ~100 Mt
- South Rock Pile = ~100 Mt
- Mined-out 5034 Pit = ~85 Mt
- Mined-out Hearne pit = ~15 Mt
- West Rock Pile = ~228 Mt
- South Rock Pile = ~100 Mt
- Mined-out 5034 Pit = ~72 Mt
- Mined-out Hearne pit as contingency storage area
Height t of Mine Rock Pile les
- West Mine Rock Pile = ~100 m
- South Mine Rock Pile = ~120 m
- West Mine Rock Pile = ~135 m
- South Mine Rock Pile = ~120 m
Categories ries of Processed sed Kimberlite berlite (PK)
- coarse PK (including grits) = 0.25 to 6 mm
- fine < 0.25 mm
- No change
Total Amount of PK
- coarse (plus grits) = 23.4 Mt
- fine = 10.0 Mt
- coarse (plus grits) = 23.7 Mt
- fine = 12.7 Mt
24 The De Beers Group of Companies
Characteris risti tic 2013 (Upd pdate ted d Project t Descriptio iption) 2018 2018 (Mine Plan Upd pdate) e) Pl Placem emen ent t of Fine e PK PK
- Fine PKC Facility Area 2
- Mined-out Hearne Pit
- No change
Placement of Coarse PK
- Coarse PK Pile
- Dyke construction and reclamation
- Mine Rock Piles
- Mined-out 5034 and Hearne Pits
- No Change
Dewatering ering of Kennady dy Lake
- Water discharge to N11
- Contingency for winter pumping
- Dewatering of Kennady Lake completed in 2016
- Winter discharge conducted
Water Diversio ions
- De Beers has committed to look for opportunities to
restore Area 7 earlier in the mine plan
- No Change
Water Management
- Diversion of water from Lake N11 or other sources
(e.g., WMP, if quality is adequate) to augment Area 8 flow (i.e., downstream flow mitigation
- Diversion of water from Lake N11 or other sources
(e.g. Area 7 if quality is adequate) to augment Area 8 flow (i.e., downstream flow mitigation) Infra rastr tructur ture
- Variation in airstrip alignment
- Designated waste management area
- Slight variation in fuel storage area
- Slight variation in the location and alignment of the
AN storage and emulsion plants
- AN Building
- Gymnasium
- Dust extraction facilities
- Tire shop and cold storage
- Additional accommodation
- Jet Fuel storage
Closure
- De Beers has committed to look for opportunities to
restore Area 7 earlier in the mine plan
- Refilling of Kennady Lake extended to approximately
12 years
- No Change
- Refilling of Kennady Lake extended to approximately
19+ years by using natural runoff and supplemental flows from Lake N11
25 The De Beers Group of Companies
SUMMARY OF LUP AMENDMENT CHANGES
Topic LUP P Sectio ion LUP P 2005C0032 2014 2014 LUP P 2005C0032 2018 2018 Reference to UPD 2018 Part B Definitions Reference to UPD 2013 Reference to UPD 2018 Fuel storage inspections Part C Item 58 a Examine fuel storage tanks once per day Examine fuel storage tanks once per week month
26 The De Beers Group of Companies
SUMMARY OF W.L. AMENDMENT CHANGES
W.L.
- L. Reference
ce W.L.
- L. 2005L2-0015
0015 2014 2014 W.L.
- L. 2005L2-0015
0015 2018 2018 Scope and Definitions Part A, Scope and Definitions 1 a) Reference to UPD 2013 Reference to UPD 2018 Definition of Modification Part A, Scope and 2. Definitions Definition excludes ‘expansion’ Definition to not specifically exclude ‘expansion’ SNP Stations to be considered prior to discharge from WMP to Lake N11 Part G: EQC – Lake N11 Item 29 SNP 02 to Inspector prior to discharge SNP 02 to Inspector prior to
- discharge. Allowance for
consideration of other SNP stations. Carry-over of discharge volume Schedule 3 Part D: Water Use Item 2b Annual discharge volume is 3.45Mm3 Annual discharge volume remains 3.45Mm3 but if it is not completed, it can carry over to the subsequent anniversary year
- r alternatively water discharge
volumes could be measured on a calendar year
27 The De Beers Group of Companies
SUMMARY OF W.L. AMENDMENT CHANGES
W.L.
- L. Reference
ce W.L.
- L. 2005L2-0015
0015 2014 2014 W.L.
- L. 2005L2-0015
0015 2018 2018 Water Use for camp Schedule 3 Part D, Item 1. b 27,000 m3 45,000 m3 Source of downstream flow mitigation Scope i.v.) operational discharge of effluent from the Water Management Pond to Lake N11 and Area 8 of Kennady Lake xxii) operational discharge of water from Area 7 to Area 8 EQC for A7 Part G, Item 31 Specific to discharge from WMP to A8 Allowance for discharge from A7 to A8 EQC for Lake N11 Part G, Item 30, 34 Table of values Table of updated values incorporating extended discharge
THANK-YOU
29 The De Beers Group of Companies
TOPIC 1 – CAMP WATER USE
30 The De Beers Group of Companies
CAMP OCCUPANCY HAS INCREASED
Total by Labour Source 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 De Beers Canada Employees 417 482 484 484 484 484 481 438 417 377 314 220 Long Term Contractors 145 143 143 143 143 143 143 139 126 122 112 76 Temporary Contractors 48 38 38 38 38 38 38 38 38 38 38 38 Total 609 663 665 665 665 665 662 615 581 537 464 334 Camp Occupancy 312 338 339 339 339 339 337 315 299 278 240 177
2013 Updated Project Description anticipated 170 people at site during Operations (372 FTE) 2017 Operations currently requires 334 people at site (due to ongoing construction projects) 2019 Peak Operations planning for 339 people at site (665 FTE) + periodic increases Total Capacity = 430 rooms
31 The De Beers Group of Companies
INCREASED CAMP WATER INTAKE FROM AREA 8
- Higher camp occupancy
results in higher water use
- Construction = 60,000m3/y
- Operations = 27,000m3/y
- Anticipate exceeding limit in
August 2018
- Bridging amendment =
35,000m3/y
- Permanent amendment =
45,000m3/y
- Water use is for camp only
GNWT ENR36, 37
32 The De Beers Group of Companies
TOPIC 2 – SNP CHANGES
33 The De Beers Group of Companies
- Water licence requires provision of sample results from SNP-
02 to Inspector prior to discharge
- SNP-02 is an in-line station that cannot be activated without
pumping
- Pre-discharge samples are taken from the intake location at
Area 3 (SNP 20)
- Mixing, particularly in the winter, is somewhat less at the
intake location - it’s a little bay
- De Beers requested that additional samples from active SNP
stations within the WMP (e.g. SNP 06, SNP 05) are also permissible to provide to Inspector prior to discharge to inform his decision
- Request is most relevant for winter discharge
GNWT- 2, 3, 4,5, MVLWB-7,-13
SNP STATIONS TO BE CONSIDERED PRIOR TO DISCHARGE TO LAKE N11
01 01 20 01 02 06 05 SNP Stations
34 The De Beers Group of Companies
- SNP-04 is an in-line monitoring station
- SNP-03 is 3 stations located at edge of the mixing zone
- SNP-03 was located at end of discharge pipe from A7 to A8
during de-watering
- The operational diffuser will be used for discharge from A7
to A8, necessitating a re-location of SNP-03
- SNP-04 location would move to in-line in new pipe
- SNP-03 location would move to end of diffuser, again as 3
stations around the mixing zone GNWT- 2, 3, 4,5, MVLWB-7,-13
SNP STATION LOCATION ADJUSTMENT IN AREA 8
03 04 03 04