CT AC PROJE CT UPDAT E SE PT E MBE R 19, 2012 www.por tofmiamitunne l.c om www.por tofmiamitunne l.c om Project Partners Public Sponsors 90% Equity Partner Contractor 10% Equity Partner VMS Operator Federal Support www.por


slide-1
SLIDE 1

www.por tofmiamitunne l.c om

CT AC PROJE CT UPDAT E

www.por tofmiamitunne l.c om SE PT E MBE R 19, 2012

slide-2
SLIDE 2

www.por tofmiamitunne l.c om www.por tofmiamitunne l.c om 90% Equity Partner 10% Equity Partner Contractor VMS Operator Public Sponsors Federal Support

Project Partners

slide-3
SLIDE 3

www.por tofmiamitunne l.c om

Scope of Work

Shifting of EB MacArthur Cswy MacArthur Cswy Bridge Widening Twin tunnels under Government Cut Modification of Dodge Island Roadway System

slide-4
SLIDE 4

www.por tofmiamitunne l.c om

  • Pier construction for

bridge widening

  • Inside widening of

both bridges to create additional capacity for tunnel traffic

  • 18 Piers and 28 beams
  • To date:15 of 19 spans

have been set

MacArthur Causeway Bridge Widening

slide-5
SLIDE 5

www.por tofmiamitunne l.c om

Dodge Island – Roadway Improvements

  • Construction of Eastbound & Westbound Port Blvd.
  • South Cruise Boulevard
  • Internal Roadways
slide-6
SLIDE 6

www.por tofmiamitunne l.c om

TBM in Launching Pit in median of MacArthur Causeway showing conveyor system that carries excavated material running

  • ut of the eastbound tube

and across MacArthur Causeway and dropping into Spoils Management area.

Watson Island – Tunnel Boring Machine (TBM)

slide-7
SLIDE 7

www.por tofmiamitunne l.c om

  • TBM cutter head with

an outside diameter

  • f 42.3 feet (as high

as a 4 story building)

  • 361 foot long trailing

support gear made up of 6 gantries

  • Total length of the

TBM is 428.5 feet long (more than a football field).

Tunnel Boring Machine (TBM)

slide-8
SLIDE 8

www.por tofmiamitunne l.c om

Tunneling Profile Section & Cross Passages

  • Tunnels are approximately 4200 ft. long
  • +40 ft. under the bottom of Government Cut & approximately

120 ft. below the surface at deepest point

  • 5% Grade
  • 5 cross passages
slide-9
SLIDE 9

www.por tofmiamitunne l.c om

Eastbound Tunnel Interior

Boring Started: November 11, 2011 Breakout on Dodge: July 31, 2012 Rings Installed: 745 Rings Length of Bored Tunnel: 4,186 LF

slide-10
SLIDE 10

www.por tofmiamitunne l.c om

  • Original plan was to disassemble

TBM and move it back to Watson Island to be reassembled and begin boring the second tunnel.

  • Design-Build Team modified the
  • riginal concept on Dodge Island

from two portals to a single split

  • portal. They also revised the
  • perations to mine the second

tunnel from Dodge Island to Watson Island by use of a turntable in the receiving pit on Dodge Island.

TBM inside Dodge Island Receiving Pit

slide-11
SLIDE 11

www.por tofmiamitunne l.c om

TBM Turnaround Table

TBM is in the process of being disassembled, turned and reassembled to begin the Westbound Tunnel Mining in October. A Custom Teflon turn table was used to turn the TBM. This method minimizes logistical risks and preserves project schedule.

slide-12
SLIDE 12

www.por tofmiamitunne l.c om

TBM Turnaround - Translation

slide-13
SLIDE 13

www.por tofmiamitunne l.c om

TBM Turnaround - Rotation

slide-14
SLIDE 14

www.por tofmiamitunne l.c om

TBM Turnaround Placement for WB Boring

slide-15
SLIDE 15

www.por tofmiamitunne l.c om

Watson Island Tunnel Portal & Conceptual Interior View of Tunnel

  • Eastbound MacArthur

Causeway view

  • Tunnel Portal Structure

houses the Flood Gates which come down in the event of a storm to prevent flooding of tunnels

  • Aesthetic challenge

was the massive size and boxy shape of the structure

slide-16
SLIDE 16

www.por tofmiamitunne l.c om

July 31, 2012 – Completion of eastbound tunnel Spring 2013 – Completion of westbound tunnel Spring 2014 – Completion of Dodge Island roadway improvements May 15, 2014 – Substantial Completion - Port of Miami Tunnel opens to traffic, O&M Period begins August 13, 2014 – Final Completion As of 9/13/12 - Construction Days to Date: 1065 of 1765 (55 months) = 60.3% of Design-Build

Project Schedule

slide-17
SLIDE 17

www.por tofmiamitunne l.c om