CT AC PROJE CT UPDAT E SE PT E MBE R 19, 2012 www.por tofmiamitunne l.c om www.por tofmiamitunne l.c om Project Partners Public Sponsors 90% Equity Partner Contractor 10% Equity Partner VMS Operator Federal Support www.por


  1. CT AC PROJE CT UPDAT E SE PT E MBE R 19, 2012 www.por tofmiamitunne l.c om www.por tofmiamitunne l.c om

  2. Project Partners Public Sponsors 90% Equity Partner Contractor 10% Equity Partner VMS Operator Federal Support www.por www.por tofmiamitunne l.c om tofmiamitunne l.c om

  3. Scope of Work Shifting of EB MacArthur Cswy MacArthur Cswy Bridge Widening Twin tunnels under Government Cut Modification of Dodge Island Roadway System www.por tofmiamitunne l.c om

  4. MacArthur Causeway Bridge Widening • Pier construction for bridge widening • Inside widening of both bridges to create additional capacity for tunnel traffic • 18 Piers and 28 beams • To date:15 of 19 spans have been set www.por tofmiamitunne l.c om

  5. Dodge Island – Roadway Improvements • Construction of Eastbound & Westbound Port Blvd. • South Cruise Boulevard • Internal Roadways www.por tofmiamitunne l.c om

  6. Watson Island – Tunnel Boring Machine (TBM) TBM in Launching Pit in median of MacArthur Causeway showing conveyor system that carries excavated material running out of the eastbound tube and across MacArthur Causeway and dropping into Spoils Management area. www.por tofmiamitunne l.c om

  7. Tunnel Boring Machine (TBM) • TBM cutter head with an outside diameter of 42.3 feet (as high as a 4 story building) • 361 foot long trailing support gear made up of 6 gantries • Total length of the TBM is 428.5 feet long (more than a football field). www.por tofmiamitunne l.c om

  8. Tunneling Profile Section & Cross Passages Tunnels are approximately 4200 ft. long • +40 ft. under the bottom of Government Cut & approximately • 120 ft. below the surface at deepest point 5% Grade • 5 cross passages • www.por tofmiamitunne l.c om

  9. Eastbound Tunnel Interior Boring Started: November 11, 2011 Breakout on Dodge: July 31, 2012 Rings Installed: 745 Rings Length of Bored Tunnel: 4,186 LF www.por tofmiamitunne l.c om

  10. TBM inside Dodge Island Receiving Pit Original plan was to disassemble • TBM and move it back to Watson Island to be reassembled and begin boring the second tunnel. Design-Build Team modified the • original concept on Dodge Island from two portals to a single split portal. They also revised the operations to mine the second tunnel from Dodge Island to Watson Island by use of a turntable in the receiving pit on Dodge Island. www.por tofmiamitunne l.c om

  11. TBM Turnaround Table A Custom Teflon turn table was used to turn the TBM. This method minimizes logistical risks and preserves project schedule. TBM is in the process of being disassembled, turned and reassembled to begin the Westbound Tunnel Mining in October. www.por tofmiamitunne l.c om

  12. TBM Turnaround - Translation www.por tofmiamitunne l.c om

  13. TBM Turnaround - Rotation www.por tofmiamitunne l.c om

  14. TBM Turnaround Placement for WB Boring www.por tofmiamitunne l.c om

  15. Watson Island Tunnel Portal & Conceptual Interior View of Tunnel • Eastbound MacArthur Causeway view • Tunnel Portal Structure houses the Flood Gates which come down in the event of a storm to prevent flooding of tunnels • Aesthetic challenge was the massive size and boxy shape of the structure www.por tofmiamitunne l.c om

  16. Project Schedule July 31, 2012 – Completion of eastbound tunnel Spring 2013 – Completion of westbound tunnel Spring 2014 – Completion of Dodge Island roadway improvements May 15, 2014 – Substantial Completion - Port of Miami Tunnel opens to traffic, O&M Period begins August 13, 2014 – Final Completion As of 9/13/12 - Construction Days to Date: 1065 of 1765 (55 months) = 60.3% of Design-Build www.por tofmiamitunne l.c om

  17. Questions? For additional project information, please visit our website at: www.portofmiamitunnel.com Project Videos & Gallery www.por tofmiamitunne l.c om

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.