cryomodule installation
play

Cryomodule Installation Kathleen Ratcliffe Outline Scope - PowerPoint PPT Presentation

Cryomodule Installation Kathleen Ratcliffe Outline Scope Cryomodule Interconnect Overview Welding Overview HOM Installation Overview Cleanroom Variations 2 CEBAF SRF linacs' Monday 29 February Scope 1.02.02


  1. Cryomodule Installation Kathleen Ratcliffe

  2. Outline • Scope • Cryomodule Interconnect Overview • Welding Overview • HOM Installation Overview • Cleanroom Variations 2 CEBAF SRF linacs' Monday 29 February

  3. Scope 1.02.02 – Injector Systems • Installation of all beamline areas - Gun, L0B, HTR, COL0 and DIAG0 • Laser Installation • Installation of gallery racks, plus cables and waveguide to beamline Slide courtesy of Ginger DeContreras CEBAF SRF linacs' Monday 29 February 3

  4. Scope 1.02.04 Linac Systems • Linac Systems divided into areas: • L1 (two 1.3 GHz cryomodules) • HL (two 3.9 GHz cryomodules) • BC1/COL1 (collimation and diagnostics) • L2 (twelve 1.3 GHz cryomodules) • BC2/COL2 (collimation and diagnostics) • L3 and Extension (twenty 1.3 GHz cryomodules and connecting beamline) - Installation includes Mechanical, RF and Power Conversion for all areas. /HL REMOVED FROM SCOPE Slide courtesy of Karen Fant CEBAF SRF linacs' Monday 29 February 4

  5. Scope • CM will be delivered to SLAC Ready for Installation • SLAC is responsible for the following: - Design, procure and install CM supports - Design and develop interconnect tooling and fixturing - Develop interconnect procedures - Develop interconnect travelers - Incoming acceptance inspection confirms no change or damage during long transit • Checks for vacuum, electrical continuity, alignment and shipping damage - Conflat flange removal and prep for welding - Install and Checkout Cryomodules - Install HOM - All other that is necessary for safe and reliable commissioning. • Water, Vacuum, Air, Purge Gas, RF Systems - Safety Systems • Radiation Shielding, BCS, MPS and PPS. 5 CEBAF SRF linacs' Monday 29 February

  6. CM Installation/Interconnect Overview • A bellows interconnect installed between two modules • Outer shell of the inter-connect unit can slide over the vacuum vessel to allow space for welding of six cryogenic pipes in-situ • Mechanically decouples adjacent CM’s and allows for thermal contraction or expansion during thermal cycling • 33 interconnects are needed for the 37 CM’s in the LCLS-II configuration • (not including feed-cans and end-caps) 6 Slide courtesy of Yun He (FNAL) CEBAF SRF linacs' Monday 29 February

  7. Interconnect Requirements -- In-situ Welding & Pressure Piping Code Compliance • Space for welding is very tight • Leak checking • Pressure testing (or X-ray inspection) for full penetration welding Slide courtesy of Yun He (FNAL) CEBAF SRF linacs' Monday 29 February 7

  8. DESY Welding the HGRP Qualify the weld Tack interconnect pipe in place Orbital Track Welder with Custom Head Performing weld-workers on both sides of CM Checking weld set-up 8 CEBAF SRF linacs' Monday 29 February

  9. Interconnect Requirements -- Particle Free UHV for Beamline • Beamline vacuum needs to preserve the particle cleanliness of the cavity surfaces • When making beamline connections between the modules, similar cleaning and assembly procedures as those performed for the cavities in the particle free clean rooms will be applied • A portable softwall cleanroom (class 10) and strict adherence to the particle free UHV assembly protocols will be applied • Prior to installation in the Linac string, the beamline vacuum of each module will be under vacuum Downstream Gate valve will be closed and Gauge tree will be removed before moving into position Slide courtesy of Yun He (FNAL) 9 CEBAF SRF linacs' Monday 29 February

  10. DESY Interconnect Cleanroom Class 10 Portable Cleanroom HOM Install Fixture Donning CR Apparel Particle Counter CEBAF SRF linacs' Monday 29 February 10

  11. HOM Inside of Portable Cleanroom CEBAF SRF linacs' Monday 29 February 11

  12. Preparing HOM for Beamline Installation in Tunnel Portable Cleanroom CEBAF SRF linacs' Monday 29 February 12

  13. Fermi Lab Cleanroom Photo courtesy Jerry Leibfritz CEBAF SRF linacs' Monday 29 February 13

  14. End

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend