Cryomodule Installation Kathleen Ratcliffe Outline Scope - - PowerPoint PPT Presentation

cryomodule installation
SMART_READER_LITE
LIVE PREVIEW

Cryomodule Installation Kathleen Ratcliffe Outline Scope - - PowerPoint PPT Presentation

Cryomodule Installation Kathleen Ratcliffe Outline Scope Cryomodule Interconnect Overview Welding Overview HOM Installation Overview Cleanroom Variations 2 CEBAF SRF linacs' Monday 29 February Scope 1.02.02


slide-1
SLIDE 1

Cryomodule Installation

Kathleen Ratcliffe

slide-2
SLIDE 2

Outline

CEBAF SRF linacs' Monday 29 February

  • Scope
  • Cryomodule Interconnect Overview
  • Welding Overview
  • HOM Installation Overview
  • Cleanroom Variations

2

slide-3
SLIDE 3

Scope 1.02.02 – Injector Systems

CEBAF SRF linacs' Monday 29 February

  • Installation of all beamline areas
  • Gun, L0B, HTR, COL0 and DIAG0
  • Laser Installation
  • Installation of gallery racks, plus cables and waveguide to beamline

Slide courtesy of Ginger DeContreras 3

slide-4
SLIDE 4

Scope 1.02.04 Linac Systems

CEBAF SRF linacs' Monday 29 February

  • Linac Systems divided into areas:
  • L1 (two 1.3 GHz cryomodules)
  • HL (two 3.9 GHz cryomodules)
  • BC1/COL1 (collimation and diagnostics)
  • L2 (twelve 1.3 GHz cryomodules)
  • BC2/COL2 (collimation and diagnostics)
  • L3 and Extension (twenty 1.3 GHz cryomodules and connecting

beamline)

  • Installation includes Mechanical, RF and Power Conversion

for all areas.

/HL

REMOVED FROM SCOPE

Slide courtesy of Karen Fant 4

slide-5
SLIDE 5

5

Scope

  • CM will be delivered to SLAC Ready for Installation
  • SLAC is responsible for the following:
  • Design, procure and install CM supports
  • Design and develop interconnect tooling and fixturing
  • Develop interconnect procedures
  • Develop interconnect travelers
  • Incoming acceptance inspection confirms no change or damage during

long transit

  • Checks for vacuum, electrical continuity, alignment and shipping

damage

  • Conflat flange removal and prep for welding
  • Install and Checkout Cryomodules
  • Install HOM
  • All other that is necessary for safe and reliable commissioning.
  • Water, Vacuum, Air, Purge Gas, RF Systems
  • Safety Systems
  • Radiation Shielding, BCS, MPS and PPS.

CEBAF SRF linacs' Monday 29 February

slide-6
SLIDE 6

6

CM Installation/Interconnect Overview

CEBAF SRF linacs' Monday 29 February

  • A bellows interconnect installed between two modules
  • Outer shell of the inter-connect unit can slide over the vacuum vessel to allow

space for welding of six cryogenic pipes in-situ

  • Mechanically decouples adjacent CM’s and allows for thermal contraction or

expansion during thermal cycling

  • 33 interconnects are needed for the 37 CM’s in the LCLS-II configuration
  • (not including feed-cans and end-caps)

Slide courtesy of Yun He (FNAL)

slide-7
SLIDE 7

7

Interconnect Requirements

  • - In-situ Welding & Pressure Piping Code Compliance

CEBAF SRF linacs' Monday 29 February

  • Space for welding is very tight
  • Leak checking
  • Pressure testing (or X-ray inspection) for full penetration welding

Slide courtesy of Yun He (FNAL)

slide-8
SLIDE 8

8

DESY Welding the HGRP

Qualify the weld Tack interconnect pipe in place Checking weld set-up Performing weld-workers on both sides of CM Orbital Track Welder with Custom Head

CEBAF SRF linacs' Monday 29 February

slide-9
SLIDE 9

9

Interconnect Requirements

  • - Particle Free UHV for Beamline

CEBAF SRF linacs' Monday 29 February

  • Beamline vacuum needs to preserve the particle cleanliness of the cavity surfaces
  • When making beamline connections between the modules, similar cleaning and

assembly procedures as those performed for the cavities in the particle free clean rooms will be applied

  • A portable softwall cleanroom (class 10) and strict adherence to the particle free

UHV assembly protocols will be applied

  • Prior to installation in the Linac string, the beamline vacuum of each module will be

under vacuum

Slide courtesy of Yun He (FNAL)

Downstream Gate valve will be closed and Gauge tree will be removed before moving into position

slide-10
SLIDE 10

10

DESY Interconnect Cleanroom

Class 10 Portable Cleanroom HOM Install Fixture

CEBAF SRF linacs' Monday 29 February

Donning CR Apparel Particle Counter

slide-11
SLIDE 11

11

HOM Inside of Portable Cleanroom

CEBAF SRF linacs' Monday 29 February

slide-12
SLIDE 12

12

Preparing HOM for Beamline Installation in Tunnel Portable Cleanroom

CEBAF SRF linacs' Monday 29 February

slide-13
SLIDE 13

13

Fermi Lab Cleanroom

CEBAF SRF linacs' Monday 29 February

Photo courtesy Jerry Leibfritz

slide-14
SLIDE 14

End