copper river delta bridge 339 pp g
play

Copper River Delta Bridge #339 pp g Russell Johnson, P.E. El Elmer - PowerPoint PPT Presentation

Copper River Delta Bridge #339 pp g Russell Johnson, P.E. El Elmer E. Marx, P.E. E M PE State of Alaska DOT&PF Bridge Section Bridge Background Originally built around 1977 Originally built around 1977 Five spans of 80 ft each ~


  1. Copper River Delta Bridge #339 pp g Russell Johnson, P.E. El Elmer E. Marx, P.E. E M PE State of Alaska DOT&PF Bridge Section

  2. Bridge Background • Originally built around 1977 Originally built around 1977 • Five spans of 80 ‐ ft each ~ 401 ‐ ft total length

  3. Bridge Background • Two piles per pier = “non ‐ redundant” Two piles per pier = non redundant • Precast concrete girders spans

  4. Recent Hydraulic Events • Natural realignment of the Copper River Natural realignment of the Copper River • Water flow considerations: Design value = 21,300 cfs 2011 measured 2011 measured = 89 000 cfs = 89,000 cfs Predicted future = 119,000 to 235,000 cfs • Flow under the Million Dollar Bridge is about 205 600 f 205,600 cfs

  5. Recent Hydraulic Events #339

  6. Recent Hydraulic Events #339

  7. Recent Hydraulic Events #339

  8. Recent Hydraulic Events #339

  9. Recent Hydraulic Events #342

  10. Recent Hydraulic Events • Channel soundings 1998 to 2006 Channel soundings 1998 to 2006

  11. Recent Hydraulic Events • Channel soundings summer 2011 Channel soundings summer 2011

  12. Ice Concerns • Bridge failure due to ice loads is not unexpected Bridge failure due to ice loads is not unexpected

  13. Proposed Bridge • Increase spans to 140 ‐ ft each • Approximately 840 ‐ ft long or more • Deep single drilled shaft foundations ($) • Deep, single drilled shaft foundations ($) … • … Or multiple 4 ‐ ft diameter pipe piles at piers 75 ft

  14. Proposed Bridge

  15. Other hurdles • Access to proposed piers Access to proposed piers • Channel migration (see bridge #342)

  16. Anticipated Schedule • Spring / Summer 2012 – gather engineering field data Spring / Summer 2012 gather engineering field data • Summer / Fall 2012 – develop hydraulic river model • Fall / Winter 2012 – Develop preliminary bridge design • Winter / Spring 2013 – Final environmental document / l l d • Summer 2013 – Final design g • Fall 2013 to Winter 2014 – Permitting & possible ROW • Spring 2015 ‐ Construction

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend