October 3, 201 9 1 Project Team ADOT Northcentral District - - PowerPoint PPT Presentation

october 3 201 9
SMART_READER_LITE
LIVE PREVIEW

October 3, 201 9 1 Project Team ADOT Northcentral District - - PowerPoint PPT Presentation

October 3, 201 9 1 Project Team ADOT Northcentral District Engineer Audra Merrick ADOT Project Manager Rashidul Haque City of Flagstaff Project Manager J eremy DeGeyter ADOT Northcentral District Brenden Foley Design


slide-1
SLIDE 1

October 3, 201 9

1

slide-2
SLIDE 2

Project Team

— ADOT Northcentral District Engineer

— Audra Merrick

— ADOT Project Manager

— Rashidul Haque

— City of Flagstaff Project Manager

— J

eremy DeGeyter

— ADOT Northcentral District

— Brenden Foley

— Design Manager (AECOM)

— Robert Ringwald

2

slide-3
SLIDE 3

N

Project Overview

3

slide-4
SLIDE 4

Project Purpose

— Rehabilitate the Butler Avenue bridges — Replace the Fourth Street bridges over I-40

— Provide additional capacity for vehicles, bicycles, and

pedestrians on Fourth Street

4

slide-5
SLIDE 5

Butler Avenue Bridge Funding

— I-40 Butler Avenue Bridges – Bridge Retrofit

— 1

00% ADOT and FHWA Funding: $900,000

5

slide-6
SLIDE 6

Butler Avenue Bridges

— Improvements to bridges:

— Patch and epoxy overlay the bridge decks — Repair the slope pavement — Bridge deck joint replacement — Concrete barrier repair

6

slide-7
SLIDE 7

Traffic Control Goals

— Two lanes of traffic on I-40 in each direction

throughout the majority of construction

— Limited night and weekend restrictions of one

lane on I-40 (eastbound or westbound)

7

slide-8
SLIDE 8

Fourth Street Bridge Replacements Funding

— I-40 Fourth Street Underpasses –

Bridge Replacements

— Base Project: $1

2,300,000

— 50% ADOT and FHWA funding — 50% City of Flagstaff funding

— City Requested Project Enhancements: $360,000

— 1

00% City of Flagstaff funding

8

slide-9
SLIDE 9

Project Background

— ADOT planned a rehabilitation project for the

existing Fourth Street bridges over I-40

— An Intergovernmental Agreement (IGA) was

signed in 201 7 to conduct a project assessment addendum

— Additional IGAs were signed between ADOT and

the City of Flagstaff to design and construct/replacements of the existing bridges and to share costs between two agencies

9

slide-10
SLIDE 10

City-funded Project Enhancements

— Two-tube railing creates protected bicycle lane — Retaining wall supports the FUTStrail — Additional aesthetics

1

slide-11
SLIDE 11

Fourth Street Bridge

— Project Improvements:

— Widen bridges and approach roadways

— Additional multi-use FUTS trail — Additional vehicle lane in each direction — Additional bicycle lane in southbound direction — Additional multi-use (bicycle and pedestrian) path in

northbound direction — Enhanced bridge aesthetics

1 1

slide-12
SLIDE 12

Fourth Street Bridge Replacements

— Existing Bridge Section — New Bridge Section

1 2

slide-13
SLIDE 13

Traffic Control Goals

— Two lanes of traffic on I-40 in each direction

throughout the majority of construction

— Limited night and weekend restrictions of one lane on

I-40 (eastbound or westbound)

— Maintain one lane of traffic in each direction

throughout the majority of construction

— Close Fourth Street to vehicle access for two weeks

plus weekend for bridge slide and approach construction (emergency, pedestrian and bicycle traffic maintained)

1 3

slide-14
SLIDE 14

M aintenance of Traffic on I-40

1 4

— During limited night and weekend restrictions

slide-15
SLIDE 15

WB Typical Section

(Looking East)

M aintenance of Traffic on I-40

— Two lanes in each direction through the entire

duration of bridge replacement.

— (One lane in one direction during night or weekend closures.)

1 5

slide-16
SLIDE 16

Sequence of Construction, Fourth Street Bridge

1 6

slide-17
SLIDE 17

Sequence of Construction, Fourth Street Bridge

1 7

slide-18
SLIDE 18

Final Bridge Section

1 8

slide-19
SLIDE 19

— Innovative Bridge Slide Construction

— Maintains pedestrian, bicycle, and emergency access on

Fourth Street (no vehicular access)

— Short-duration closure (two weeks + weekend closure) — A detour is required — Pedestrian and emergency access will be maintained during

closure

M aintenance of Fourth Street Traffic During Bridge Removal and Slide

slide-20
SLIDE 20

Bridge Slide

— Part of FHWA Every Day Counts (EDC) — Accelerated Bridge Construction — Additional Federal Funding through the FHWA

Technology and Innovation Deployment Program (TIDP)

20

slide-21
SLIDE 21

Benefits of the Slide M ethod of Construction

— Reduces overall construction duration on I-40 by an estimated 65 calendar days — Reduces vehicular closure of Fourth Street (total traffic volume of 25,420 vpd)

by an estimated 1 00 calendar days

— Reduces contractor risk of completion of construction in single season — The total user delay savings to the public is estimated to be $6,81

5,1 57, compared to other alternatives, and has the lowest estimated combined total construction and user cost

— Reduces duration of construction management — The site conditions with shallow bed rock make the location conducive to slide

construction

— Reduces limited emergency access through the construction zone — Slide can be timed to avoid impacted traffic during the first week of school and

  • ther events

21

slide-22
SLIDE 22

Project Schedule

Milestones Dates

Design March 201 9 to October 201 9 Project Advertisement, Bid, and Selection

  • f Contractor

Fall 201 9 to early 2020* Closure of Fourth Street for demolition of existing bridges and slide of new bridges (approximately two weeks + weekend) Late Summer 2020* Construction Spring to Fall 2020*

* Anticipated

22

slide-23
SLIDE 23

Slide Construction Video

23

slide-24
SLIDE 24

Questions can be answered one-on-one by staff at the exhibits

24

slide-25
SLIDE 25

Project Contacts

— ADOT Community Relations Project Manager

— Mackenzie Kirby, mkirby@

azdot.gov

— City of Flagstaff Communications Manager

— J

essica Drum, jdrum@ flagstaffaz.gov

— Designer Community Relations

— Kristin Darr, kristin@

centralcreativeaz.com

25

slide-26
SLIDE 26

26