Controls, Safety and Engineering Databases CERN Experimental Areas - - PowerPoint PPT Presentation

controls safety and engineering databases cern
SMART_READER_LITE
LIVE PREVIEW

Controls, Safety and Engineering Databases CERN Experimental Areas - - PowerPoint PPT Presentation

Controls, Safety and Engineering Databases CERN Experimental Areas Access Systems for 2007 and beyond Presented by Rui Nunes TS-CSE-AAS 24 Jan 2007 ATC/ ABOC Days Controls, Safety and Engineering Databases Topics Introduction


slide-1
SLIDE 1

24 Jan 2007 ATC/ ABOC Days

Controls, Safety and Engineering Databases CERN Experimental Areas Access Systems for 2007 and beyond Presented by Rui Nunes TS-CSE-AAS

slide-2
SLIDE 2

24 Jan 2007 ATC/ ABOC Days

Controls, Safety and Engineering Databases Topics

  • Introduction

– Types of Access Systems

  • Problems in 2006

– North area interruption 3/ 11/ 2006

  • Why they will not happen in 2007
  • The new (S)PS Experimental Areas Access

System

– Ongoing project

slide-3
SLIDE 3

24 Jan 2007 ATC/ ABOC Days

Controls, Safety and Engineering Databases Introduction – Projects organisation

  • TS-CSE-AAS

– PS : R. Bonzano, D. Chapuis – SPS : M. Grill, R. Villard, D. Vaxelaire

  • (S)PS Experimental

Areas project

– CO: H. Nissen, F. Havart – Ind. Sup : R. Mermillon

slide-4
SLIDE 4

24 Jan 2007 ATC/ ABOC Days

Controls, Safety and Engineering Databases Types of Access Systems

  • SUSI

– Site entry gates & road barriers, building entrance, etc...

  • ZORA Primary

– Access to areas classified as Primary by RP

  • PS machines, SPS machine
  • Overlap with Experimental Areas in target areas

– (e.g. TCC2, East Hall, ISOLDE, etc...)

  • ZORA Secondary

– Access to areas classified as Secondary by RP

  • Corresponds to mostly Exp Areas (with exception of targets)
  • This presentation is about ZORA Secondary Areas
slide-5
SLIDE 5

24 Jan 2007 ATC/ ABOC Days

Controls, Safety and Engineering Databases Existing systems

  • SPS Zone North
  • PS East Hall
  • PS AD
PPG 21036 PPG 21105 PPG 21161 MSE 2183 TED 2103 TBSE 2106 G81 PPGX 81 G82 H2 H4 H6 H8

BA80 BA81 TCC8 ECN3 EHN1

EHN2

PPG 810 PPG 850 PPG 841 P0 M2 PPG 842 PPG 2225 PPG 3003 PPG 3159 PPG 3239 PPG 4003 PPG 4159 PPG 4223 PPG 5003 PPG 5139 PPG 5183 PPG 5190 PPG 6003 PPG 6149 PPG 6159 PPG 66003 PPG 1003 PPG 1159 PPG 102828 PPG 2003 PPG 2159

BA4

ECX4 ECA5 PPG 012058

ECX4 A. P.

PPG 712 PPG 802.2 PPR 800.2 PPG 800.1 PPG 800.3 PPG 800.4 PPG 800.3

BA80 A. P.

PPG 802.1 PPG 802.1

BA81 A.P.

PPG 851.4 TCC8 A.P.

S P S

PPG 812.1 PPG 851.3 PPG 851.2 ECN3 A.P. PPG 853 PPG 854 PPG 852.3 PPG 852.2 PPG 852.1 PPG 852.7 PPG 852.8 PPG 852.5 PPG 852.9 PPG 300.4 PPE 853 PPE 854 PPG 300.6

BA3 BA1

GPI TI180

BA6

SWC 1,2,3 SUPRA 1,2,3,4 SUPRA VALVES RF 100MHz RF 400MHz MAL 1029 ALIMENTATION 18kV Sextupôles LSDA/B, Sextupôles LSFA/B/C, Octupôles LOD1F. 1 3 3 1 5 TT20 6 2 3 4 PPG 710 PPC 711 MSS 2117 MSS 2204 T2 T4 T6 4 PPGX 82 DP 544 4 3 3 PPG 818.3 2 2 2 2 4 PPG 851.6 PPG 851.7 3 5 PPG 851.1 1 1 PPG 300.3 3 PPG 538 PPG 528 2

BA5

MSE 6183 MSES 6183 TED 6103 MBB 6104 MBS 6600/1 MBBT 6202 MBN 6203 PPG620327 ECX5 NEUTRINO PITS BIW295 A. P. CHICANE PPG 61031 ECA4

BA2

PPG 4183 3 2 1 5 2 2 1 ISOLDE

RING PS

BOOSTER

T T 2

AA RING AA HALL AA TARGET TT6 LPI CTF 3 1 2 LINAC2 LINAC3 LEAR HALL SUD LT.STP E2.STP02 L.STP1/2 STP11/12 E2BHN02 BHZ20 E2STP01 EO.BHN2\3 SW FA BI.STP STP176 BTP.STP BTY.BVT101 BTY.STP103 BTI9015/16 BTI247/S STP9021/22 BTI8025 STP2658/59 CAVITY114MHz CANON.LIL V MDK LASER SHUTTER HTE.BHZ40 FA58STP42 MAIN MAGNET SMI5306 STP8032 MTV2210 MTV5303 E4.MTV12 E1.STP SMH26 VVS01 BOUCHON EAST HALL BHZ01 STP T7 FT62 TDU70 MAGNET AA AC 1 5 TAX 012023/4 PPG701 3 3 1 1 2 PPG702 3 PPG V0 PPG V1 PPG V2 4 4 3 4 1 3 1 1 3 1 1 4

TT 70

PPG TCC6 1 4

TT61 A. P.

PPD 61 PPR 61 MAL 1001 MBIV 1003 BHZ 377 PPG100611 (D225) PPG100638 D227 D323 D322 D303 STP6069 D304 D321 D301 D302 D313 D311 D314 D39 D38 D31 D703 D120 D701 D902 D901 SMH58 SMH57 STP1 STP2 D111 D151 D101 D112 D152 HTE.BHZ30 HTE.STP30 D113 D115 HTE.STP22 HTE.BHZ12 D604 D606 HTP.BHZ10 HTP.STP10 HTP.STP14 HTP.BHZ20 HR.STP64 D605 D601 D611 D602 D109 D102 D105 D403 D402 D21 D401 D130 D122 D121 D22 D221 D220 STP152 SMH16 D133

EHW1

PPC 551 PPG 536 PPG 556 PPG 516 PPC 557 2 PPC 561 PPC 541 2 PPG 566 PPG 526

NORTH EXPERIMENTAL AREA WEST EXPERIMENTAL AREA

MAP OF PS - SPS SAFETY ELEMENTS

GPI TI 120 GPI TI 121 IMAH 1204 IMAV 1203 ITED 1203 GPI TI 122 ITED 1221 IMBT 1220 6 7 ITED 1801 IMBT 1801 ITED 1203 GPI TI181 GPI TI182 IMBT 1821 ITED 1822 MCB 7000 MAL 7003

LEP

TT 10 TT 60 TI 18 TI 12

PPG 1203 PPC 101 PPG 102 BA1 A. P. PPG 118 2 2 PPG 117 PPG 101 PPC 202 PPR 204 PPG 201 PPC 203 PPG 218 BA2 A. P. PPG 219 2 2 PPG 220 PPG 202 4 PPC 302 PPR 304 PPG 302 PPG 301 PPC 303 PPG 324 PPG 325 BA3 A. P. 2 2 LIFT PPC 402 PPG 402 PPG 401 PPC403 PPG 422 PPG 420 BA4 A. P. 2 2 LIFT PPC 502 PPG 502 PPG 501 PPG 508 PPG 509 BA5 A. P. 2 2 PPC 602 PPR 604 PPG 601 PPC 603 PPG 618 PPG 617 PPG 615 BA6 A. P. 2 2 PPG 602 PPC 702 PPRC & PPR 704 PPG 705 PPG 713 PPG 714 BA7 A. P. 2 2 PPG 706 5 PPG 300.2 PPG 300.5 PPG 851.8 PPG 851.5 PPG 300.1 PPG 832 PPG 812.2 PPG 831 PPG 801.2 MBE 2103 Part. MBE 2103 Tot.

ECX5 A. P.

PPG 6223

BA7

PPG 6905 PPG V3 PPG V4 PPG V5 PPG V6 MSI 1183

ST/MC/AC/ec/mappub.dsf

slide-6
SLIDE 6

24 Jan 2007 ATC/ ABOC Days

Controls, Safety and Engineering Databases Problems in 2006

  • One major problem in Zone North

– Friday 3/ 11/ 2006 – Effects

  • not possible to close the zone in COMPASS
  • Solution only found on Monday with intervention of contractor staff

Causes

  • HP machine interfacing the safety hardware and the supervision software

was caught in a infinite loop

  • Procedure includes rebooting the machine but this time no success

– Solution

  • Software intervention necessary to change timeouts to break the loop
  • Intervention was only possible on Monday with contractor staff

– Result

  • No beam for compass over this weekend
  • Minor problems in PS

– AD - 19/ 11 last weekend of beam – HP machine crashed and replaced – East Hall : problems with Access DB due to separation of TN and GPN in CSA

slide-7
SLIDE 7

24 Jan 2007 ATC/ ABOC Days

Controls, Safety and Engineering Databases Actions & Why this will not happen again in 2007

  • Zone North

– Migration of FactoryLink Supervision to Windows

  • Machine that interfaces will be removed
  • Interface with CESAR over a PLC S7 (FESA)
  • PS AD & East Hall

– Complete replacement of the Access Control system during 2007 shutdown – PPE (doors) shall be recuperated dismantled from the SPS Zone West, as will all the locks – The control system shall be completely replaced

slide-8
SLIDE 8

24 Jan 2007 ATC/ ABOC Days

Controls, Safety and Engineering Databases New (S)PS Access System

  • Main features

– NO ACCESS CARD necessary to access zones

  • Option for access card validation to close/ open the zone

– Industrial touch panel interface at acces point – Key distributor for Key Access – Reconfiguration of the chains/ zones via a pin matrix – Supervision possible via TIM

  • Possible to extend to SPS (resources allowing)

– Same philosophy of SPS – Based on reccomendations to UNIFY the peocedures to access in Exp areas

  • Documentation available
  • EDMS URD : 476292, SRD : 478678, ADD : 503535

– presented in PS/ SPS days in January 2006

slide-9
SLIDE 9

24 Jan 2007 ATC/ ABOC Days

Controls, Safety and Engineering Databases

Drawing by R. Nunes & Access team

slide-10
SLIDE 10

24 Jan 2007 ATC/ ABOC Days

Controls, Safety and Engineering Databases (S)PS Experimental Areas Access System

  • Status of Zone
  • Touch Panel with Info
  • SPS-type lock
  • Validate CLOSE/ OPEN
  • RP veto KEY
  • Beam Stopper Command
  • Key distributor
slide-11
SLIDE 11

24 Jan 2007 ATC/ ABOC Days

Controls, Safety and Engineering Databases (S)PS Experimental Areas Access System

  • Status of chain/ zones
  • Manual Vetos

– (or MCR vetos for the PS)

  • Reconfiguration matrixes

– EIS-Access – EIS-Faisceau

slide-12
SLIDE 12

24 Jan 2007 ATC/ ABOC Days

Controls, Safety and Engineering Databases Conclusion

  • Positive 2006 summary

– No major problems despite strain in resources

  • Except one weekend for Zone North
  • Modifications for North Area

– Migration of Supervision system to Windows should solve interface problems

  • New PS Exp Areas System to be implemented in

2007

– SPS upgrade necessary in the near future but subject to financial resource constraints

slide-13
SLIDE 13

24 Jan 2007 ATC/ ABOC Days

Controls, Safety and Engineering Databases Thank you for your attention Questions?

(hopefully answers too… ..)