SLIDE 1
Contaminated Land and Hazardous Substances Masterton Gasworks - - PowerPoint PPT Presentation
Contaminated Land and Hazardous Substances Masterton Gasworks - - PowerPoint PPT Presentation
Contaminated Land and Hazardous Substances Masterton Gasworks Given controlled activity consent under Discharges to Land Plan in 2014 for 25 years Continues to leach arsenic, cyanide and PAHs beyond boundary of the site both in
SLIDE 2
SLIDE 3
Masterton Gasworks
- Given controlled activity consent under
Discharges to Land Plan in 2014 for 25 years
- Continues to leach arsenic, cyanide
and PAHs beyond boundary of the site both in groundwater and surface water and movement of silt within stream bed progressing downstream.
SLIDE 4
- Assessment under pNRP- as the
ground and surface water at or beyond the boundary of the site can not meet the standards set in the permitted activity criteria in R55, they would be required to gain a discretionary resource consent under R56
- Assessing the site under the requested
amendments, the rules will be easier to understand and interpret, activity would still require discretionary consent under R56
SLIDE 5
Gun Club – new activity
- Wairarapa Gun Club
SLIDE 6
- Non notified consent issued November
2016 for discharge of steel shot and clay targets to land – 10 years
- Non notified consent issued July 2017
for discharge of lead shot and clay targets to land – 15 years
- Main contaminants of concern lead
and antimony (heavy metals that contaminate soil and water) and PAH’s from clay targets.
SLIDE 7
- Consent granted as the ‘effects’ were
determined to be localised until they reached certain contaminant levels and the landowner had signed off as an affected party, therefore effects on the landowner could not be considered.
- Would recommended changes to
policies and rules have made any difference to the assessment of activity against objectives/policies?
SLIDE 8
- Policy 89 strengthened by saying shall
be avoided instead of managed
- Policy 95 may be less permissive as it
will refer to RMA definition of contaminated land rather than having to wait for contamination to become so bad that it then falls into Category III definition
- R57 – discharge of hazardous
substances – non complying activity has been extended to cover land i.e. soil
SLIDE 9
- Non complying activity status requires
an ‘or’ test, either adverse effects will be minor OR activity will not be contrary to objectives and policies of relevant plan and proposed plan.
- If the adverse effects on the land are
more than minor, the s104D
- bjective/policy test applies. The
recommended changes would give clearer direction that the objective of the Plan is to avoid creating contaminated land
SLIDE 10
- pNRP does not require a landowner to
undertake contaminated land
- investigations. NES-CS (implemented
by TAs) applies only when land use changing to a more sensitive use or subdivision.
SLIDE 11
- Recommended changes to R42 –