Construction Progress Woodson YMCA | March 6, 2019 D E S I G N - - PowerPoint PPT Presentation

construction progress
SMART_READER_LITE
LIVE PREVIEW

Construction Progress Woodson YMCA | March 6, 2019 D E S I G N - - PowerPoint PPT Presentation

Construction Progress Woodson YMCA | March 6, 2019 D E S I G N | B U I L D | D E V E L O P Sitework and Foundations Demolition of existing entry and preparations for new foundations begins Excavation and pouring of concrete


slide-1
SLIDE 1

D E S I G N | B U I L D | D E V E L O P

Woodson YMCA | March 6, 2019

Construction Progress

slide-2
SLIDE 2

D E S I G N | B U I L D | D E V E L O P

Sitework and Foundations

Demolition of existing entry and preparations for new foundations begins Existing entry prior to start of construction Excavation and pouring of concrete foundations for west side of senior center along existing north pool wall Removal of canopy over existing entry and site preparations for senior center foundations Removal of existing entry walls Masonry forms for structural piers along existing north pool Masonry reinforcement for foundations of senior center conservatory and stair tower Excavation of foundations under new reception for mechanical access below north pool

Woodson YMCA | October 2018

slide-3
SLIDE 3

D E S I G N | B U I L D | D E V E L O P

Cranes and lifts erecting steel columns and girders Installation of structural steel framework that supports structure of new gymnasium Arrival of 110’ long structural steel roof joists down 3rd St. Manoeuvring roof joists into construction site Lifting roof joists into position Lowering roof girder system into place Connecting joists to support structure

Woodson YMCA | November 2018

Steel Framing

Arrival of structural steel framework and initial phases of installation

slide-4
SLIDE 4

D E S I G N | B U I L D | D E V E L O P

Assembling masonry foundation forms and steel reinforcement along 4th St. Curing of masonry foundations for new gymnasium and parking structure Installation of roof system over existing north pool Steel reinforcement of masonry foundations Structural support foundation for new gymnasium

Woodson YMCA | December 2018

Removal of masonry forms and site grading Pouring of concrete along south wall of senior center

Steel Framing and Foundations

Installation of new pool roof system and foundations for new gymnasium

slide-5
SLIDE 5

D E S I G N | B U I L D | D E V E L O P

Interior framing and pre-cast planks being lifted into position Masonry wall along south end of covered parking area takes shape Crane lifting the pre-cast floor system for the new activity gym Installation of activity gym roof system Framed structure of activity gym above new senior center

Woodson YMCA | January 2019

Roof structure over new reception area and floor

  • f gym lobby

Work begins on structure of south stair tower

Steel Framing and Pre-Cast

Steel framing of activity gym and senior center and installation of flooring and roof systems

slide-6
SLIDE 6

D E S I G N | B U I L D | D E V E L O P

Excavation of new whirlpool area Concrete forms and insulation for new whirlpool Removal of walls for new whirlpool space adjacent to north pool deck Select demolition of north locker room areas Removal of flooring and lockers in updated north womens locker room

Woodson YMCA | January 2019

Floor excavation and framing of new north universal locker room walls Concrete removal of north locker room floors for new plumbing

North Locker Rooms and Whirlpool

Demolition and excavation of lower level north universal locker room, womens locker room and whirlpool

slide-7
SLIDE 7

D E S I G N | B U I L D | D E V E L O P

New senior center looking south Installation of new gymnasium floor Construction of elevator shaft between new gymnasium and activity gymnasium New entry vestibule and canopy

Woodson YMCA | February 2019

Looking south at new entry canopy and two story reception

New Gymnasium

Placement of new gymnasium pre-cast plank flooring and framing of new entry

slide-8
SLIDE 8

D E S I G N | B U I L D | D E V E L O P

Plumbing installed for new universal shower rooms New whirlpool walls and water-line tile installed Concrete poured to form north womens locker room floor and new locker bases Trench drains installed in new north universal locker rooms

Woodson YMCA | February 2019

Walls, openings and door frames of new universal locker room

North Locker Rooms and Whirlpool

Continued work on new whirlpool foundation and mechanicals; New north locker room floors and walls take shape Trench drains installed in updated north womens locker room

slide-9
SLIDE 9

D E S I G N | B U I L D | D E V E L O P

Removal of existing walls and updated mechanical systems Existing space on January 15 New entry area New exterior doors added to all childcare rooms

Woodson YMCA | February 2019

New Infant Room

Temporary Childcare Facility

Remodel work for the temporary childcare facility on 3rd St.; Work completed by March 1 for the temporary childcare center opening March 4 Updated flooring, new walls and storage areas New Toddler rooms with direct exterior exit and updated casework

slide-10
SLIDE 10

D E S I G N | B U I L D | D E V E L O P

Woodson YMCA | February 2019

Join the conversation

Follow us @GhidorziCompanies on Facebook to see how we are keeping the community engaged and excited.