Construction Arna - Bergen Stian Ekornaas Head of Strategies and - - PowerPoint PPT Presentation

construction arna bergen
SMART_READER_LITE
LIVE PREVIEW

Construction Arna - Bergen Stian Ekornaas Head of Strategies and - - PowerPoint PPT Presentation

Construction Arna - Bergen Stian Ekornaas Head of Strategies and Contracts Railway Tender Conference Oslo, 10 May 2017 Construction Arna - Bergen 2 projects: Arna Flen Bergen Flen Approx. 50 employees in Client


slide-1
SLIDE 1

Construction Arna - Bergen

Stian Ekornaas Head of Strategies and Contracts Railway Tender Conference Oslo, 10 May 2017

slide-2
SLIDE 2

Construction Arna - Bergen

  • 2 projects:

‒ Arna – Fløen ‒ Bergen – Fløen

  • Approx. 50 employees in Client organisation
  • Offices in Arna and the city centre of Bergen

Information is correct as of 10 May 2017, but may be subject to change. 2

slide-3
SLIDE 3

Arna – Fløen – Bergen

3

slide-4
SLIDE 4

Arna - Fløen

  • Production from 2014
  • Completed 2022
  • New parallel tunnel Arna – Fløen (Ulriken tunnel)

‒ TBM ‒ Breakthrough autumn 2017

  • Arna station

‒ Start-up August 2017

  • UUT 31 Railway-technical contract

Information is correct as of 10 May 2017, but may be subject to change. 4

slide-5
SLIDE 5

TBM - New Ulriken tunnel

Information is correct as of 10 May 2017, but may be subject to change. 5

slide-6
SLIDE 6

Arna station 2022

6 Information is correct as of 10 May 2017, but may be subject to change.

slide-7
SLIDE 7

UUT 31 Railway-technical contract - p.1

  • Interdisciplinary railway-technical contract

‒ Track/superstructure ‒ Catenary system ‒ Low-voltage system ‒ High-voltage system ‒ Telecommunications

  • New tunnel (7,8 km)
  • Updating old tunnel
  • Arna station area

Information is correct as of 10 May 2017, but may be subject to change. 7

slide-8
SLIDE 8

Information is correct as of 10 May 2017, but may be subject to change. 8

Railway-technical work at Arna station

slide-9
SLIDE 9

UUT 31 Railway-technical contract - p.2

  • Tendered autumn 2017
  • Contract summer 2018
  • Planned start-up 1. quarter 2019
  • Completion 3. quarter 2022
  • Detailed design delivered by Bane NOR
  • Contractor will be responsible for design of the slab track part of

the tunnel (7 km)

  • Estimated cost MNOK 500

Information is correct as of 10 May 2017, but may be subject to change. 9

slide-10
SLIDE 10

The New Ulriken Tunnel

 Arna Bergen 

10 Information is correct as of 10 May 2017, but may be subject to change.

slide-11
SLIDE 11

Bergen - Fløen

  • Double-tracking Bergen – Fløen (1,3 km)
  • Renewal of existing systems
  • Project underway for several years
  • High complexity due to location (city centre), limited space and
  • ld infrastructure
  • Bane NOR needs to take into consideration several other

projects ‒ Bergen light rail ‒ Freight terminal ‒ Railway projects

  • Bane NOR will review the scope of the project
  • Working on a new project progress plan. This will be settled in

the near future

Information is correct as of 10 May 2017, but may be subject to change. 11

slide-12
SLIDE 12

Fløen

Information is correct as of 10 May 2017, but may be subject to change. 12