|
COMMERCIAL
Confinement and Shielding: Intrabay Doors, Floor Valves and - - PowerPoint PPT Presentation
Confinement and Shielding: Intrabay Doors, Floor Valves and Component Transfer Hatch Pit Lids Penetration Plugs Fire Suppression system COMMERCIAL | Critical Success Factors Affordable Economical design Value for money by delivering
COMMERCIAL
COMMERCIAL
COMMERCIAL
COMMERCIAL
COMMERCIAL
– Keep-in and Keep-out zone define the boundaries of the design – Embedment's are pre-cast to support equipment Sized based on concept
– Mounting of radiological sensors and setting to work Sensors etc are free issued – Requirements are not prescriptive. Open to discuss other ways to address the needs – As built survey to be provided during contract
– No requirement for: Radiological safety system is out of scope Limited to mounting of sensors etc. free issued to the contractor SIL Thermal assessment
COMMERCIAL
– Protection of Workers outside ActCell in the High BAy – Enable docking of Cask & transfer of components into ActCell
– Shielding Door with portal frame shielding
– Recovery system – Confinement
COMMERCIAL
Protection of Workers in the Maintenance Cell Enable crane movements & waste package transfer
Pivot “flap” mechanism (upper door rotated 90º) Sliding door mechanism Locking pin for Upper Door
Recovery Confinement
COMMERCIAL
Purpose
Protection of Workers in outside the ActC CTH performs nuclear safety function Enable transfer of small items into Cell
Major Items
Glovebox
Bagging system Transfer system Tray from cold to hot Shield doors (~4T) Hot & Cold side doors Interlocked
Considerations
Interlocking Hot and cold doors Confinement recovery
COMMERCIAL
PQQ Published
Key Dates PQQ: Q2 2018 Contract Award: Q1 2019 Site Access: Q2/Q3 2021 Completion: Q3/Q4 2021
COMMERCIAL
COMMERCIAL
COMMERCIAL
– Protection of Workers in
– 10 off Pit Lids ( 26 sub- sections) – Concrete filled Pit Lids – Steel Pit Lids
– Pit Cell Location features – O-ring Sealing face on external Pit Lids (WTH & PIE Cell). – Manufacturing tolerance
Concrete Filled Steel construction
COMMERCIAL
COMMERCIAL
– ~42 off SS core (OD
~250mm)
– SS Cap – O-ring Sealing face
COMMERCIAL
Protection of Workers in outside the ActC
1 off Plug
Installed in the Penetration Room (outside of the active cell) Equivalent to 1.3m HDC To fill aperture Removable from cold side
COMMERCIAL
Pit Lid Market Enquiry Published Plugs currently work in progress
Key Dates PQQ: Q3/Q4 2018 Contract Award: Q1/Q2 2019 Site Access: Jan 2020 Completion: Feb 2020
COMMERCIAL
COMMERCIAL
COMMERCIAL
ActC Asset Protection
Major Items Piping and water mist system
Conventional piping water mist system to extinguish a fire
Fire Detection in-cell
VESDA system draws air from cells to detect smoke Rate-of-heat rise sensor detects heat rise within the cell
Pump Skid
Located outside of the Active Cell, in the surrounding technical galleries. Includes, bunded skid consisting of pumps, a water tank and leak detectors
Fire Control Panel
Integrate with ESS fire safety system and utilise the infrastructure supplied by UKAEA to distribute power and signalling
COMMERCIAL
Market Enquiry Published
Key Dates Q2/Q3 2019 Contract Award: Q4 2019 Site Access: Q2/Q3 2021 Completion: Q3/Q4 2021
COMMERCIAL
90º Pan range Tilt range 90º
The active cells facility is a windowless hot cell operated from the remote control room. The operator views of the equipment and components in the cells are only through the Viewing System cameras. Hence the viewing system must be highly reliable and provide a combination of wide area views (safety) and operational views (inspection, process monitoring, etc.)
Camera Pan & Tilt Units
Robotic Handling system
the cells or on moveable stands
Widely varying specs based on type of view and position:
tolerant cameras, B&W and Colour
from 10kGy to 1MGy TID(*) (110 Gy/hr)
(*) Total Integration Dose over ESS lifecycle
COMMERCIAL
RACE-ESS-TEM-0038
COMMERCIAL
RACE
Procurement will consist of 3 main parts:
The exact nature of the procurement has not been finalised, however at present it is expected that the scope will be for the design and manufacture of all the items based on provided requirements specification. A Negotiated procedure is expected, that will allow for the scope and risk profile of the procurement to be
COMMERCIAL
RACE
Boxes (WSBs) to be manufacture by ESS as they are needed. The boxes will be placed within an existing shielded container approximately 3mx2mx1m and will allow for:
when full.
accessories.
COMMERCIAL
RACE
When Target Station components are introduced into the cell, a set of support structures are required to fix their location and provide stability. These include:
are lowered into the cell.
components whilst they are waiting to be processed. General Requirements:
rules).
height from the floor
COMMERCIAL
RACE
A lifting adaptor to allow the lifting of a >8000kg section of target station component using the in cell Grapple.
COMMERCIAL
27
The Electrical Power and Signalling system is responsible for providing electrical services into the Active Cells from supplier control cubicles to supplier equipment. The Active Cells are a radiological area that will require a degree of radiation tolerance within the designed electrical
Process Cell Maintenance Cell
COMMERCIAL
28
Free Issue Components for Manufacture
Purchasing Value Band
Purchasing Key Dates Contract Award: Q4 2018/Q1 2019 Completion: Q3/Q4 2019 <£100K >£100K to <£500K Purchasing Value Band
COMMERCIAL
29
Manufacture, Assembly and Delivery of the following:
Purchasing Value Band
<£100K >£100K to <£500K Purchasing Value Band
Manufacturing Key Dates Contract Award: Q1/Q2/Q3 - 2019 Completion: Q2 - 2020
COMMERCIAL
30
>£100K to <£500K Purchasing Value Band
Manufacturing Key Dates Contract Award: Q4 - 2019 Completion: Q3/Q4 2020 4 – 5 month Installation Scope à Band B
Install the following:
Install and commissioning the following:
COMMERCIAL
3 1 R A C E
Transfer Trolley
SWL = 100t Confinement Shroud to control particulate spread (Not shown) Rails and Mounting Hardware Electrical and Control Systems
Scope Provisional Timescales
Tender start = Q1 2019 Contract Award = Q3 2019 Site Access = Q3/Q4 2021 Completion = Q3/Q4 2021