Radsynch 2017 Taiwan, 19 21 April 2017 Shielding design study for - - PowerPoint PPT Presentation
Radsynch 2017 Taiwan, 19 21 April 2017 Shielding design study for - - PowerPoint PPT Presentation
Radsynch 2017 Taiwan, 19 21 April 2017 Shielding design study for the ESRF EBS project Paul Berkvens, Reine Versteegen, Patrick Colomp & Laurent Farvacque SHIELDING DESIGN STUDY FOR THE ESRF EBS PROJECT Contents 1. Short introduction
SHIELDING DESIGN STUDY FOR THE ESRF EBS PROJECT
Page 2 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
Contents
- 1. Short introduction to the EBS project
- 2. Shielding study and radiation protection policy
- 3. Normal beam losses
- 4. Abnormal stored beam losses and injection incidents
- 5. Residual dose rates from activation
- 6. RF ducts
ESRF EBS PROJECT: EXTREMELY BRILLIANT SOURCE
Page 3 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
Parameter Existing Lattice New Lattice Energy, E [GeV] 6.04 6.04 Circumference, C [m] 844 844 RF frequency, fRF [MHz] 352 352 Beam current [mA] 200 200 Horizontal Emittance [pm ·rad]
4000 150
Vertical Emittance [pm ·rad] 4 3 Beta at ID center, βx , βy [m] 37.6 , 3.0 (high β) 0.35 , 3.0 (low β) 3.6 , 3.6 Beam size at ID center, σx , σy [μm] 413 , 3.9 (high β) 50 , 3.9 (low β) 24 , 3.3 Beam div. at ID center, σx’ , σy’ [μrad] 10 , 1.3 (high β) 107, 1.3 (low β) 6.4 , 0.91
ESRF EBS PROJECT: EXTREMELY BRILLIANT SOURCE
Page 4 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
User Service Mode Design and Procurement Production Assembly Dismantling Installation Accelerator commissioning Beamline commissioning Friendly users 2016 2017 2018 2019 2020
now
DECOMMISSIONING OF THE EXISTING STORAGE RING
Page 5 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
q
Decommissioning of the existing storage ring has to be done within the French legal framework: absence of clearance levels. Revised technical study sent to ASN, March 2016
- Proposed criteria for radiological classification of
accelerator components
- Detailed activation calculations of standard cell
- Measurement protocols for different components
- Provisional planning
Meeting with ASN, Paris in the coming weeks Reply from ASN expected mid 2017
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
cable trays, cables, piping (322 d) supports quadrupoles (440 d) sextupoles (280 d) dipoles (64 d) vacuum vessels (140 d) 2019 2020 2021 2022 2023 2024
SHIELDING DESIGN STUDY FOR THE ESRF EBS PROJECT
Page 6 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
Contents
- 1. Short introduction to the EBS project
- 2. Shielding study and radiation protection policy
- 3. Normal beam losses
- 4. Abnormal stored beam losses and injection incidents
- 5. Residual dose rates from activation
- 6. RF ducts
EBS PROJECT: RADIATION PROTECTION FRAMEWORK
Page 7 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
1st discussions with ASN:
- Upgrade should not be considered as new facility but as a modification of an existing facility.
- Authorisation request to be submitted to ASN September 2017
- Radiation exposure should be as low as for present facility
Aim ESRF: - Dose constraint: 1 mSv/y 800 µSv/y (2 µSv/4 h 1.6 µSv/4 h)
- Commissioning period: maintain non-exposure status
- Limit access to experimental hall to staff and long-term contractors
- Guarantee monthly non-exposure limits
Compliance with Council Directive 2013/59/EURATOM
EBS PROJECT: SHIELDING ASSESSMENT
Page 8 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
2013/59/EURATOM : "normal exposure” means exposure expected to occur under the normal operating conditions of a facility or activity (including maintenance, inspection, decommissioning), including minor incidents that can be kept under control, i.e. during normal operation and anticipated operational occurrences. Normal losses
- Verify that effective dose rates are << 0.4 µSv/h (1.6 µSv / 4h)
Minor incidents
- Stored beam losses: estimate probability, assess dose
- Injected beam losses
- Assess integrated dose per 5 nC booster pulse (6 GeV, 5 mA, 1 µs)
- Verify doses are kept under control via interlocked radiation monitors
- Dose / booster pulse < 1.6 µSv
- Validate number / location of interlocked dose monitors
EBS PROJECT: SHIELDING ASSESSMENT
Page 9 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
Purpose: assessment of "normal exposure” and verify compliance with dose constraint. 2013/59/EURATOM : "normal exposure” means exposure expected to occur under the normal
- perating conditions of a facility or activity (including maintenance, inspection, decommissioning),
including minor incidents that can be kept under control, i.e. during normal operation and anticipated operational occurrences. Major challenge:
- maximum beam losses × 10 use existing bulk shielding
install (2) beam loss collimators + local shielding Lifetime (h) Beam losses (e/s) Beam mode Stored current (mA) Present lattice EBS lattice Present lattice EBS lattice Multi-bunch 200 45 19.3 2.2 107 5.1 107 16 bunch 92 16 1.8 2.8 107 2.5 108 4 bunch 40 9 1.2 2.2 107 1.6 108
EBS PROJECT: SHIELDING ASSESSMENT
Page 10 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
FLUKA model of EBS storage ring
FLUKA model of optics hutch
Shielding study: need for
- 1. realistic geometry
- 2. realistic beam losses
ELECTRON BEAM LOSS DISTRIBUTION
Page 11 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
0.01 0.1 1 10 100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
beam loss distribution along storage ring
beam loss per unit cell (% of total losses)
unit cell number
collimator location: between QF4E and SD1E
Matlab Accelerator Toolbox Module developed for Touschek losses: 6 dimensional phase space distribution of lost electrons
ELECTRON BEAM LOSS DISTRIBUTION: EXAMPLE UNIT CELL NUMBER 10
Page 12 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
- 0.05
0.05
- 0.03
0.03
- 0.01
0.01
- 0.015
0.015
y (m) y' (rad) x (m) x' (rad)
0.2 0.4 0.6 0.8 1
beam loss distribution within unit cell
cumulative beam losses within unit cell
for each unit cell: 6 dimensional phase space distribution of lost electrons
SHIELDING DESIGN STUDY FOR THE ESRF EBS PROJECT
Page 13 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
Contents
- 1. Short introduction to the EBS project
- 2. Shielding study and radiation protection policy
- 3. Normal beam losses
- 4. Abnormal stored beam losses and injection incidents
- 5. Residual dose rates from activation
- 6. RF ducts
NORMAL BEAM LOSSES: 92 mA, 1.8 H LIFETIME – EX: CELLS 19, 20 AND 21
Page 14 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
µSv/h 0.4 µSv/h
beam height above roof
cm 1.E-05 1.E-04 1.E-03 1.E-02 1.E-01
- 2000
- 1000
1000 2000 3000 4000 500
total effective dose rate (µSv/h) inner wall
- uter wall
roof
BEAM LOSS COLLIMATORS
Page 15 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
0.01 0.1 1 10 100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
beam loss distribution along storage ring
beam loss per unit cell (% of total losses)
unit cell number
5 4 3 2 1
- 3000
- 2000
- 1000
1000 2000 3000 4000 5000
- 3000
- 2000
- 1000
1000 2000 3000 4000 5000
COLLIMATOR: 92 mA, 1.8 H LIFETIME DECAY – 40 % LOCAL LOSS NO LOCAL SHIELDING
Page 16
µSv/h 0.1 µSv/h
total dose total effective dose rate (µSv/h)
cm
neutron
0.1
Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
1 0.1 0.01 0.001 1×10-4 1×10-5
inner wall total inner wall neutrons
- uter wall total
- uter wall neutrons
1 0.1 0.01 0.001 1×10-4 1×10-5
- 3000
- 2000
- 1000
1000 2000 3000 4000 5000 3000
- 2000
- 1000
1000 2000 3000 4000 5000
COLLIMATOR: 92 mA, 1.8 H LIFETIME DECAY – 40 % LOCAL LOSS LOCAL HEAVY CONCRETE SHIELDING
Page 17
µSv/h
total dose total effective dose rate (µSv/h)
cm
neutron
0.1
Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
1 0.1 0.01 0.001 1×10-4 1×10-5
inner wall total inner wall neutrons
- uter wall total
- uter wall neutrons
1 0.1 0.01 0.001 1×10-4 1×10-5
0.1 µSv/h
COLLIMATOR: 92 mA, 1.8 H LIFETIME DECAY – 40 % LOCAL LOSS NO LOCAL SHIELDING VS. LOCAL HEAVY CONCRETE SHIELDING µSv/h 0.1
No shielding Local heavy concrete shielding
Page 18 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
3000
- 2000
- 1000
1000 2000 3000 4000 5000 3000
- 2000
- 1000
1000 2000 3000 4000 5000
COLLIMATOR: 200 mA BEAM DUMP (RF TRIP) – 100 % LOCAL LOSS LOCAL HEAVY CONCRETE SHIELDING
Page 19
µSv
total dose total effective dose (µSv)
cm
neutron
Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
1 0.1 0.01 0.001 1×10-4 1×10-5
inner wall total inner wall neutrons
- uter wall total
- uter wall neutrons
1 0.1 0.01 0.001 1×10-4 1×10-5
SHIELDING DESIGN STUDY FOR THE ESRF EBS PROJECT
Page 20 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
Contents
- 1. Short introduction to the EBS project
- 2. Shielding study and radiation protection policy
- 3. Normal beam losses
- 4. Abnormal stored beam losses and injection incidents
- 5. Residual dose rates from activation
- 6. RF ducts
1.E-07 1.E-06 1.E-05 1.E-04 1.E-03 1.E-02 1.E-01 1.E+00
- 3000
- 2000
- 1000
1000 2000 3000 4000 5000
INJECTED BEAM INCIDENTS: 5 nC INJECTED WITH DQ1B MAGNET OFF
Page 21 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
µSv
beam height above roof
Roof Inner wall Outer wall cm
total effective dose (µSv)
1.E-06 1.E-05 1.E-04 1.E-03 1.E-02 1.E-01
- 3000
- 2000
- 1000
1000 2000 3000 4000 5000
INJECTED BEAM INCIDENTS: 5 nC INJECTED ON CLOSED GATE VALVE
Page 22 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
µSv
beam height above roof
Roof Inner wall Outer wall cm
total effective dose (µSv)
1.E-04 1.E-03 1.E-02 1.E-01 1.E+00 1.E+01 1.E+02
- 3000
- 2000
- 1000
1000 2000 3000 4000 5000
STORED BEAM INCIDENT: 200 mA LOST ON CLOSING GATE VALVE
Page 23 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
µSv
total dose neutrons
Inner wall total Inner wall neutrons Outer wall total Inner wall neutrons
1.6 µSv
cm
total effective dose (µSv)
beam
SHIELDING DESIGN STUDY FOR THE ESRF EBS PROJECT
Page 24 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
Contents
- 1. Short introduction to the EBS project
- 2. Shielding study and radiation protection policy
- 3. Normal beam losses
- 4. Abnormal stored beam losses and injection incidents
- 5. Residual dose rates from activation
- 6. RF ducts
1.E-05 1.E-04 1.E-03 1.E-02
- 2000
- 1000
1000 2000 3000 4000 5000
STANDARD CELL ACTIVATION EQUILIBRIUM RESIDUAL DOSE RATES AFTER 20 y
Page 25
µSv/h
1 day decay time
Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
Residual effective dose rate at 1 m from beam axis (µSv/h)
cm
1.E-06 1.E-05 1.E-04 1.E-03 1.E-02 1.E-01 1.E+00
- 2000
- 1000
1000 2000 3000 4000
COLLIMATOR ACTIVATION EQUILIBRIUM RESIDUAL DOSE RATES (20 y) – 40 % LOCAL LOSS
Page 26
µSv/h
5 minutes decay time
Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
Residual effective dose rate at 1 m from beam axis (µSv/h)
COLLIMATOR ACTIVATION EQUILIBRIUM RESIDUAL DOSE RATES (20 y) – 40 % LOCAL LOSS
Page 27
µSv/h
1 day decay time
Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
COLLIMATOR ACTIVATION EQUILIBRIUM RESIDUAL DOSE RATES (20 y) – 40 % LOCAL LOSS
Page 28
µSv/h
Local shielding: 5 mm Pb under roof beams
Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
COLLIMATOR ACTIVATION RESIDUAL DOSE RATES FOLLOWING 200 mA BEAM DUMP – 100 % LOCAL LOSS
Page 29
µSv/h
1 minute decay time
0.1
Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
1.E-06 1.E-05 1.E-04 1.E-03 1.E-02 1.E-01 1.E+00 1.E+01
- 2000
- 1000
1000 2000 3000 4000
Residual effective dose rate at 1 m from beam axis (µSv/h)
ACTIVATION: RESIDUAL DOSE RATES FOLLOWING 200 mA BEAM DUMP (100 % LOCAL LOSSES)
Page 30
µSv/h
1 day decay time
0.1
Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
Interlock areas around collimators No access before ~1 hour after beam dump Requires major modification of PSS
SHIELDING DESIGN STUDY FOR THE ESRF EBS PROJECT
Page 31 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
Contents
- 1. Short introduction to the EBS project
- 2. Shielding study and radiation protection policy
- 3. Normal beam losses
- 4. Abnormal stored beam and injection incidents
- 5. Residual dose rates from activation
- 6. RF ducts
RF DUCTS
Page 32 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
25 cm × 25 cm square hole 119 cm Cells 5, 7 and 25 Single-cells HOM cavities
1.E-04 1.E-03 1.E-02 1.E-01
- 400
- 200
200 400
RF DUCTS: 92 mA, 1.8 H LIFETIME DECAY
Page 33 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
total dose neutrons µSv/h
distance from beam axis (cm) effective dose rate (µSv/h) total dose neutron dose
1.E-02 1.E-01 1.E+00 1.E+01 1.E+02 1.E+03
- 200
- 150
- 100
- 50
RF DUCTS: SYNCHROTRON RADIATION 200 mA STORED BEAM
Page 34 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens
µSv/h
distance from beam axis (cm) effective dose rate (µSv/h)
5 mm Pb
total dose neutron dose
no shielding 5 mm Pb
MANY THANKS FOR YOUR ATTENTION
Page 35 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens