Radsynch 2017 Taiwan, 19 21 April 2017 Shielding design study for - - PowerPoint PPT Presentation

radsynch 2017
SMART_READER_LITE
LIVE PREVIEW

Radsynch 2017 Taiwan, 19 21 April 2017 Shielding design study for - - PowerPoint PPT Presentation

Radsynch 2017 Taiwan, 19 21 April 2017 Shielding design study for the ESRF EBS project Paul Berkvens, Reine Versteegen, Patrick Colomp & Laurent Farvacque SHIELDING DESIGN STUDY FOR THE ESRF EBS PROJECT Contents 1. Short introduction


slide-1
SLIDE 1

Shielding design study for the ESRF EBS project Paul Berkvens, Reine Versteegen, Patrick Colomp & Laurent Farvacque

Radsynch 2017

Taiwan, 19 – 21 April 2017

slide-2
SLIDE 2

SHIELDING DESIGN STUDY FOR THE ESRF EBS PROJECT

Page 2 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

Contents

  • 1. Short introduction to the EBS project
  • 2. Shielding study and radiation protection policy
  • 3. Normal beam losses
  • 4. Abnormal stored beam losses and injection incidents
  • 5. Residual dose rates from activation
  • 6. RF ducts
slide-3
SLIDE 3

ESRF EBS PROJECT: EXTREMELY BRILLIANT SOURCE

Page 3 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

Parameter Existing Lattice New Lattice Energy, E [GeV] 6.04 6.04 Circumference, C [m] 844 844 RF frequency, fRF [MHz] 352 352 Beam current [mA] 200 200 Horizontal Emittance [pm ·rad]

4000 150

Vertical Emittance [pm ·rad] 4 3 Beta at ID center, βx , βy [m] 37.6 , 3.0 (high β) 0.35 , 3.0 (low β) 3.6 , 3.6 Beam size at ID center, σx , σy [μm] 413 , 3.9 (high β) 50 , 3.9 (low β) 24 , 3.3 Beam div. at ID center, σx’ , σy’ [μrad] 10 , 1.3 (high β) 107, 1.3 (low β) 6.4 , 0.91

slide-4
SLIDE 4

ESRF EBS PROJECT: EXTREMELY BRILLIANT SOURCE

Page 4 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

User Service Mode Design and Procurement Production Assembly Dismantling Installation Accelerator commissioning Beamline commissioning Friendly users 2016 2017 2018 2019 2020

now

slide-5
SLIDE 5

DECOMMISSIONING OF THE EXISTING STORAGE RING

Page 5 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

q

Decommissioning of the existing storage ring has to be done within the French legal framework: absence of clearance levels. Revised technical study sent to ASN, March 2016

  • Proposed criteria for radiological classification of

accelerator components

  • Detailed activation calculations of standard cell
  • Measurement protocols for different components
  • Provisional planning

Meeting with ASN, Paris in the coming weeks Reply from ASN expected mid 2017

J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

cable trays, cables, piping (322 d) supports quadrupoles (440 d) sextupoles (280 d) dipoles (64 d) vacuum vessels (140 d) 2019 2020 2021 2022 2023 2024

slide-6
SLIDE 6

SHIELDING DESIGN STUDY FOR THE ESRF EBS PROJECT

Page 6 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

Contents

  • 1. Short introduction to the EBS project
  • 2. Shielding study and radiation protection policy
  • 3. Normal beam losses
  • 4. Abnormal stored beam losses and injection incidents
  • 5. Residual dose rates from activation
  • 6. RF ducts
slide-7
SLIDE 7

EBS PROJECT: RADIATION PROTECTION FRAMEWORK

Page 7 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

1st discussions with ASN:

  • Upgrade should not be considered as new facility but as a modification of an existing facility.
  • Authorisation request to be submitted to ASN September 2017
  • Radiation exposure should be as low as for present facility

 Aim ESRF: - Dose constraint: 1 mSv/y  800 µSv/y (2 µSv/4 h  1.6 µSv/4 h)

  • Commissioning period: maintain non-exposure status
  • Limit access to experimental hall to staff and long-term contractors
  • Guarantee monthly non-exposure limits

Compliance with Council Directive 2013/59/EURATOM

slide-8
SLIDE 8

EBS PROJECT: SHIELDING ASSESSMENT

Page 8 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

2013/59/EURATOM : "normal exposure” means exposure expected to occur under the normal operating conditions of a facility or activity (including maintenance, inspection, decommissioning), including minor incidents that can be kept under control, i.e. during normal operation and anticipated operational occurrences. Normal losses

  • Verify that effective dose rates are << 0.4 µSv/h (1.6 µSv / 4h)

Minor incidents

  • Stored beam losses: estimate probability, assess dose
  • Injected beam losses
  • Assess integrated dose per 5 nC booster pulse (6 GeV, 5 mA, 1 µs)
  • Verify doses are kept under control via interlocked radiation monitors
  • Dose / booster pulse < 1.6 µSv
  • Validate number / location of interlocked dose monitors
slide-9
SLIDE 9

EBS PROJECT: SHIELDING ASSESSMENT

Page 9 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

Purpose: assessment of "normal exposure” and verify compliance with dose constraint. 2013/59/EURATOM : "normal exposure” means exposure expected to occur under the normal

  • perating conditions of a facility or activity (including maintenance, inspection, decommissioning),

including minor incidents that can be kept under control, i.e. during normal operation and anticipated operational occurrences. Major challenge:

  • maximum beam losses × 10 use existing bulk shielding

 install (2) beam loss collimators + local shielding Lifetime (h) Beam losses (e/s) Beam mode Stored current (mA) Present lattice EBS lattice Present lattice EBS lattice Multi-bunch 200 45 19.3 2.2 107 5.1 107 16 bunch 92 16 1.8 2.8 107 2.5 108 4 bunch 40 9 1.2 2.2 107 1.6 108

slide-10
SLIDE 10

EBS PROJECT: SHIELDING ASSESSMENT

Page 10 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

FLUKA model of EBS storage ring

FLUKA model of optics hutch

Shielding study: need for

  • 1. realistic geometry
  • 2. realistic beam losses
slide-11
SLIDE 11

ELECTRON BEAM LOSS DISTRIBUTION

Page 11 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

0.01 0.1 1 10 100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32

beam loss distribution along storage ring

beam loss per unit cell (% of total losses)

unit cell number

collimator location: between QF4E and SD1E

Matlab Accelerator Toolbox  Module developed for Touschek losses: 6 dimensional phase space distribution of lost electrons

slide-12
SLIDE 12

ELECTRON BEAM LOSS DISTRIBUTION: EXAMPLE UNIT CELL NUMBER 10

Page 12 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

  • 0.05

0.05

  • 0.03

0.03

  • 0.01

0.01

  • 0.015

0.015

y (m) y' (rad) x (m) x' (rad)

0.2 0.4 0.6 0.8 1

beam loss distribution within unit cell

cumulative beam losses within unit cell

for each unit cell: 6 dimensional phase space distribution of lost electrons

slide-13
SLIDE 13

SHIELDING DESIGN STUDY FOR THE ESRF EBS PROJECT

Page 13 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

Contents

  • 1. Short introduction to the EBS project
  • 2. Shielding study and radiation protection policy
  • 3. Normal beam losses
  • 4. Abnormal stored beam losses and injection incidents
  • 5. Residual dose rates from activation
  • 6. RF ducts
slide-14
SLIDE 14

NORMAL BEAM LOSSES: 92 mA, 1.8 H LIFETIME – EX: CELLS 19, 20 AND 21

Page 14 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

µSv/h 0.4 µSv/h

beam height above roof

cm 1.E-05 1.E-04 1.E-03 1.E-02 1.E-01

  • 2000
  • 1000

1000 2000 3000 4000 500

total effective dose rate (µSv/h) inner wall

  • uter wall

roof

slide-15
SLIDE 15

BEAM LOSS COLLIMATORS

Page 15 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

0.01 0.1 1 10 100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32

beam loss distribution along storage ring

beam loss per unit cell (% of total losses)

unit cell number

slide-16
SLIDE 16

5 4 3 2 1

  • 3000
  • 2000
  • 1000

1000 2000 3000 4000 5000

  • 3000
  • 2000
  • 1000

1000 2000 3000 4000 5000

COLLIMATOR: 92 mA, 1.8 H LIFETIME DECAY – 40 % LOCAL LOSS NO LOCAL SHIELDING

Page 16

µSv/h 0.1 µSv/h

total dose total effective dose rate (µSv/h)

cm

neutron

0.1

Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

1 0.1 0.01 0.001 1×10-4 1×10-5

inner wall total inner wall neutrons

  • uter wall total
  • uter wall neutrons

1 0.1 0.01 0.001 1×10-4 1×10-5

slide-17
SLIDE 17
  • 3000
  • 2000
  • 1000

1000 2000 3000 4000 5000 3000

  • 2000
  • 1000

1000 2000 3000 4000 5000

COLLIMATOR: 92 mA, 1.8 H LIFETIME DECAY – 40 % LOCAL LOSS LOCAL HEAVY CONCRETE SHIELDING

Page 17

µSv/h

total dose total effective dose rate (µSv/h)

cm

neutron

0.1

Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

1 0.1 0.01 0.001 1×10-4 1×10-5

inner wall total inner wall neutrons

  • uter wall total
  • uter wall neutrons

1 0.1 0.01 0.001 1×10-4 1×10-5

0.1 µSv/h

slide-18
SLIDE 18

COLLIMATOR: 92 mA, 1.8 H LIFETIME DECAY – 40 % LOCAL LOSS NO LOCAL SHIELDING VS. LOCAL HEAVY CONCRETE SHIELDING µSv/h 0.1

No shielding Local heavy concrete shielding

Page 18 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

slide-19
SLIDE 19

3000

  • 2000
  • 1000

1000 2000 3000 4000 5000 3000

  • 2000
  • 1000

1000 2000 3000 4000 5000

COLLIMATOR: 200 mA BEAM DUMP (RF TRIP) – 100 % LOCAL LOSS LOCAL HEAVY CONCRETE SHIELDING

Page 19

µSv

total dose total effective dose (µSv)

cm

neutron

Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

1 0.1 0.01 0.001 1×10-4 1×10-5

inner wall total inner wall neutrons

  • uter wall total
  • uter wall neutrons

1 0.1 0.01 0.001 1×10-4 1×10-5

slide-20
SLIDE 20

SHIELDING DESIGN STUDY FOR THE ESRF EBS PROJECT

Page 20 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

Contents

  • 1. Short introduction to the EBS project
  • 2. Shielding study and radiation protection policy
  • 3. Normal beam losses
  • 4. Abnormal stored beam losses and injection incidents
  • 5. Residual dose rates from activation
  • 6. RF ducts
slide-21
SLIDE 21

1.E-07 1.E-06 1.E-05 1.E-04 1.E-03 1.E-02 1.E-01 1.E+00

  • 3000
  • 2000
  • 1000

1000 2000 3000 4000 5000

INJECTED BEAM INCIDENTS: 5 nC INJECTED WITH DQ1B MAGNET OFF

Page 21 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

µSv

beam height above roof

Roof Inner wall Outer wall cm

total effective dose (µSv)

slide-22
SLIDE 22

1.E-06 1.E-05 1.E-04 1.E-03 1.E-02 1.E-01

  • 3000
  • 2000
  • 1000

1000 2000 3000 4000 5000

INJECTED BEAM INCIDENTS: 5 nC INJECTED ON CLOSED GATE VALVE

Page 22 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

µSv

beam height above roof

Roof Inner wall Outer wall cm

total effective dose (µSv)

slide-23
SLIDE 23

1.E-04 1.E-03 1.E-02 1.E-01 1.E+00 1.E+01 1.E+02

  • 3000
  • 2000
  • 1000

1000 2000 3000 4000 5000

STORED BEAM INCIDENT: 200 mA LOST ON CLOSING GATE VALVE

Page 23 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

µSv

total dose neutrons

Inner wall total Inner wall neutrons Outer wall total Inner wall neutrons

1.6 µSv

cm

total effective dose (µSv)

beam

slide-24
SLIDE 24

SHIELDING DESIGN STUDY FOR THE ESRF EBS PROJECT

Page 24 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

Contents

  • 1. Short introduction to the EBS project
  • 2. Shielding study and radiation protection policy
  • 3. Normal beam losses
  • 4. Abnormal stored beam losses and injection incidents
  • 5. Residual dose rates from activation
  • 6. RF ducts
slide-25
SLIDE 25

1.E-05 1.E-04 1.E-03 1.E-02

  • 2000
  • 1000

1000 2000 3000 4000 5000

STANDARD CELL ACTIVATION EQUILIBRIUM RESIDUAL DOSE RATES AFTER 20 y

Page 25

µSv/h

1 day decay time

Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

Residual effective dose rate at 1 m from beam axis (µSv/h)

cm

slide-26
SLIDE 26

1.E-06 1.E-05 1.E-04 1.E-03 1.E-02 1.E-01 1.E+00

  • 2000
  • 1000

1000 2000 3000 4000

COLLIMATOR ACTIVATION EQUILIBRIUM RESIDUAL DOSE RATES (20 y) – 40 % LOCAL LOSS

Page 26

µSv/h

5 minutes decay time

Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

Residual effective dose rate at 1 m from beam axis (µSv/h)

slide-27
SLIDE 27

COLLIMATOR ACTIVATION EQUILIBRIUM RESIDUAL DOSE RATES (20 y) – 40 % LOCAL LOSS

Page 27

µSv/h

1 day decay time

Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

slide-28
SLIDE 28

COLLIMATOR ACTIVATION EQUILIBRIUM RESIDUAL DOSE RATES (20 y) – 40 % LOCAL LOSS

Page 28

µSv/h

Local shielding: 5 mm Pb under roof beams

Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

slide-29
SLIDE 29

COLLIMATOR ACTIVATION RESIDUAL DOSE RATES FOLLOWING 200 mA BEAM DUMP – 100 % LOCAL LOSS

Page 29

µSv/h

1 minute decay time

0.1

Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

1.E-06 1.E-05 1.E-04 1.E-03 1.E-02 1.E-01 1.E+00 1.E+01

  • 2000
  • 1000

1000 2000 3000 4000

Residual effective dose rate at 1 m from beam axis (µSv/h)

slide-30
SLIDE 30

ACTIVATION: RESIDUAL DOSE RATES FOLLOWING 200 mA BEAM DUMP (100 % LOCAL LOSSES)

Page 30

µSv/h

1 day decay time

0.1

Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

Interlock areas around collimators No access before ~1 hour after beam dump  Requires major modification of PSS

slide-31
SLIDE 31

SHIELDING DESIGN STUDY FOR THE ESRF EBS PROJECT

Page 31 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

Contents

  • 1. Short introduction to the EBS project
  • 2. Shielding study and radiation protection policy
  • 3. Normal beam losses
  • 4. Abnormal stored beam and injection incidents
  • 5. Residual dose rates from activation
  • 6. RF ducts
slide-32
SLIDE 32

RF DUCTS

Page 32 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

25 cm × 25 cm square hole 119 cm Cells 5, 7 and 25 Single-cells HOM cavities

slide-33
SLIDE 33

1.E-04 1.E-03 1.E-02 1.E-01

  • 400
  • 200

200 400

RF DUCTS: 92 mA, 1.8 H LIFETIME DECAY

Page 33 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

total dose neutrons µSv/h

distance from beam axis (cm) effective dose rate (µSv/h) total dose neutron dose

slide-34
SLIDE 34

1.E-02 1.E-01 1.E+00 1.E+01 1.E+02 1.E+03

  • 200
  • 150
  • 100
  • 50

RF DUCTS: SYNCHROTRON RADIATION 200 mA STORED BEAM

Page 34 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens

µSv/h

distance from beam axis (cm) effective dose rate (µSv/h)

5 mm Pb

total dose neutron dose

no shielding 5 mm Pb

slide-35
SLIDE 35

MANY THANKS FOR YOUR ATTENTION

Page 35 Radsynch17, Taiwan 19 - 21 April 2017 - EBS project ESRF - Paul Berkvens