Community Liaison Committee Meeting #26 Sept 11, 2018 Agenda 1. - - PowerPoint PPT Presentation

community liaison committee meeting 26
SMART_READER_LITE
LIVE PREVIEW

Community Liaison Committee Meeting #26 Sept 11, 2018 Agenda 1. - - PowerPoint PPT Presentation

Community Liaison Committee Meeting #26 Sept 11, 2018 Agenda 1. Review of June 5, 2018 meeting notes 2. Membership items 3. Site Specific Standards for Particulate, BaP, Benzene 4. Algoma Boat Slip and Port 5. MacLeod Mine WTP update


slide-1
SLIDE 1

Community Liaison Committee Meeting #26

Sept 11, 2018

slide-2
SLIDE 2

June 5, 2018

1. Review of June 5, 2018 meeting notes 2. Membership items 3. Site Specific Standards for Particulate, BaP, Benzene 4. Algoma Boat Slip and Port 5. MacLeod Mine WTP update 6. Road Paving / Dust mitigation 7. Noise Abatement 8. Environmental Compliance Approval updates 9. Greenhouse gases

  • 10. Public Open House
  • 11. Next Meetings

Agenda

slide-3
SLIDE 3

3

Membership Items

Current Members and Alternates Representation Primary Member Alternate Algoma Fred Post Chris Galizia Algoma Chris Galizia Fred Post Ministry of Environment, Conservation & Parks Lori Greco Ron Dorscht Public David Trowbridge Ildiko Horvath Public Patt Marquis SSM Tribe of Chippewa Indians Kathie Brosemer Algoma Public Health Kara Flannigan Jonathon Bouma Chippewa County Health Dept. Trevor Quinlan Suzanne Lieurance Batchewana First Nations Dan Sayers Jr. City of Sault Ste. Marie Catherine Taddo Maggie McAuley United Steel Workers Local 2251 Reginald Dunn

  • St. Mary’s River RAP Coordinator

Lisa Derickx

slide-4
SLIDE 4

4

Site Specific Standard for Particulate and BaP

  • On March 27th, 2015 Algoma received a Site Specific Standard for Particulate

accompanied by a Directors Order which sets specific emission limits in cokemaking: – Certified observers (per EPA Method 9 and Method 303) – 5 days per week, 10 Saturdays and 10 Sundays each year – Must observe daily per battery: 4 pushes, 5 charges, all lids, all doors, and all standpipes – Must make operational adjustments if over the daily limits and notify MECP

slide-5
SLIDE 5

5

Site Specific Air Quality Standard for Particulate & B(a)P

Identifies Key Performance Indicators related to Cokemaking Emissions:

  • average intensity of pushing emissions
  • average duration of charging emissions
  • % lid leaks
  • % off-takes leaks
  • % door leaks

Implementation Date 30 day rolling average % Charging Emission Pushing Opacity (%) Doors Lids Off-takes July 2, 2015 38 0.8 25 12 sec 50 Jan 1, 2016 22.5 0.8 15 12 sec 50 Jan 1, 2017 7 0.8 4.2 12 sec 50 Jan 1, 2019 7 0.8 4.2 12 sec 40 Jan 1, 2020 4 0.4 2.5 12 sec 30

Conformance calculated daily for each battery

New limits set July 2015. Progressive, annual reduction.

slide-6
SLIDE 6

6

Continued Success through Operating Adjustments

To date all corrective actions have been successful at reducing

  • pacity below the limit.

Corrective actions include:

  • Taking cross-wall temperature readings to identify problem flues
  • Cleaning the flues, pins, orifices, risers, flex hoses, venturies and bus flues
  • Increasing oven temperature
  • Repairing adjacent ovens and ensure proper heating of the shared walls
  • Adjusting fuel or air to improve combustion
  • Extending coking time
slide-7
SLIDE 7

7

Charging Emissions Below Limit

Preventative Measures include: Adjusting carbon scraper bar Decarbonizing standpipes, goosenecks and charge holes Cleaning goosenecks, sleeves to the collector main, and steam jets Replacing drop sleeve donuts, bellow bags, and carbon seals Adjusting coal feed systems to

  • ptimize coal charging volume

Leveling charge hole bases to ensure proper elevation and tight seal

slide-8
SLIDE 8

8

Lid Emissions Below Limit

Preventative Measures include: Applying lid sealant immediately after charging an oven and whenever emissions are

  • bserved

Replacing damaged or cracked lids Repairing, leveling and grouting charge hole bases to ensure proper seal

slide-9
SLIDE 9

9

Off-take Emissions Below Limit

Preventative measures include: Replacing the soft seal and adjusting the cap Cleaning the gooseneck, sleeve to collector main, and steam jet Re-packing collar or base of the pipe with refractory Applying masonry seal to small cracks until welding can be completed Replacing the standpipe at the end

  • f its lifecycle
slide-10
SLIDE 10

10

Door Emissions Below Limit

Adjusting door bolts, frame clips and hour glass clips Cleaning doors, door jambs, sill plates and spotting targets Replacing door cleaner bushes and jamb cleaner blades on frequent schedule Replacing damaged doors and frames. Applying silicate to seal leaks Preventative measures include:

slide-11
SLIDE 11

11

Stack Opacity

Continuous corrective actions on all batteries

  • Part of the investment plan to achieve compliance with SSS limits also focuses on reducing

stack emissions from cokemaking

  • Focus is on reducing intensity of stack emissions
slide-12
SLIDE 12

12

Public Complaints

There were no public complaints received since the last CLC meeting that related to a matter addressed in the SSS Order. The following public complaints were received by the company:

  • June 6 – Odour and particulate – temperature inversion observed (haze)
  • July 20 – Road dust at Conmee Avenue facility– water truck dispatched
  • August 25 – Odour – nothing abnormal identified
slide-13
SLIDE 13

13

MECP Comments

slide-14
SLIDE 14

14

Site Specific Standards

The Benzene SSS approval requires continued addition to Benzene Emission Control (BEC) systems and on site monitoring to identify missing sources

  • North Raw Liquor Tank – removed from service in late spring
  • Planning has started to install remaining controls by 2020 year end
  • A benzene air monitoring program underway in the by-products area to identify

benzene emission sources not currently controlled A metals air monitoring program has commenced along Algoma’s property boundaries (Iron, Chromium VI, Manganese and Nickel)

slide-15
SLIDE 15

15

Industry / Technical Standard

Regulatory Instrument to replace existing SSS’s

  • The MECP commenced discussions with sector on new Industry / Technical / Site Specific Standards for

multiple air contaminants

  • Contaminants could include: Particulate, B(a)P, Benzene, SO2, Stack Opacity, Metals (x4)
  • Process expected to take 3-4 years to develop
  • Site visit (May 8) and acceptance of monitoring programs
  • Benzene air monitoring program commenced in July
  • Metals air monitoring program commenced in August
slide-16
SLIDE 16

16

Boat Slip Sediment

Dredging occurred in summer 2017 The objective was to remove legacy contaminated sediment A post-dredge sediment sampling was completed in May 2018. Analysis and interpretation of results are pending from consultant.

slide-17
SLIDE 17

17

Port of Algoma

  • As a result of the mediation between the relevant stakeholders to negotiate port

arrangements for a reorganized Algoma following its emergence from the CCAA Proceedings, the Buyers and Port of Algoma stakeholders have reached an agreement in principle and are working toward inking the agreement.

slide-18
SLIDE 18

18

MacLeod Mine Water Treatment

  • WTP commissioned in June 2018 and is performing exceptionally well
slide-19
SLIDE 19

19

Road Paving / Particulate Control

Continued efforts to reduce particulate include paving:

  • Trans East Yard 43,054 ft2
  • North Coke Making Road

29,430 ft2

  • #1 Gate In Road at Praxair

61,440 ft2

  • #4 Gate North Bridge Apps

6,300 ft2

  • #7 Blast Furnace Track Crossing 8,000 ft2
  • Cost ~ $1.25 Million
  • Significantly reducing track-out and subsequent

sweeping requirements

slide-20
SLIDE 20

20

Noise Abatement

  • Three ventilated, acoustically

controlled cooling tower fan motor enclosures were installed in July

  • Reduced noise levels from 85 dBA to

73 dBA at source

  • Cost $120,000
slide-21
SLIDE 21

21

Noise Abatement

  • Engineering complete for 2

gas cleaning plant fan motor enclosures

  • Fabrication underway
  • Installation anticipated in

November

  • Cost ~$1,076,000
slide-22
SLIDE 22

22

Noise Abatement

  • Re-design and final engineering complete for new BOSP muffler
  • Installation anticipated in December maintenance shutdown – aligned with crane availability
  • Cost $635,000
slide-23
SLIDE 23

23

New Environmental Compliance Approval Applications

  • Algoma submitted an administrative ECA amendment application for noise

requesting a six year extension on the remaining five noise sources

  • Basis of request:
  • 6 control measures installed in past 6 years at cost of $2.86 million
  • Progressive reduction in public noise complaints
  • Constraints related to CCAA
  • Focus on toxics related to Site Specific Standards
  • Remaining controls estimated at $2.4 million over 5 years
slide-24
SLIDE 24

24

New Environmental Compliance Approval Applications

  • Algoma submitted an ECA application for a surface and groundwater treatment

facility at base line ditch as per previous communications

slide-25
SLIDE 25

25

Greenhouse Gas Regulations

Ontario Cap and Trade regulation revoked

  • Allowances to be retired for compliance purposes
  • No reimbursements for purchased allowances
  • GreenOn program closed - funding eliminated - Project Peregrine postponed
  • Ontario to fight federal backstop regulations
  • Ontario indicated they will create a new carbon reduction program but no details provided

Federal Low Carbon Economy Fund

  • Proceeding with application for $2.8M for light oil project – Deadline Sept 28

Federal Backstop

  • Benchmarks currently set at 80% coverage – Energy Intensive Trade Exposed (EITE) sectors including steel raised

to 90%

  • Algoma conducting company specific EITE evaluation to demonstrate severity of exposure to US market/tariffs

Future Outlook

  • Continue consultation with federal government to develop Output Based Pricing System for integrated steelmaking
  • Monitor and participate in provincial developments
  • Continue planning for future projects (i.e. bio-mass substitution in coal and CO2 capture with BOF slag)
slide-26
SLIDE 26

26

Public Open Houses

  • Last open house held on December 5, 2017 at the Polish Canadian Hall located

at 232 Goulais Avenue.

  • Next open house will be scheduled in fall, 2018 – preferably after exit from CCAA
slide-27
SLIDE 27

27

Next Meeting

  • Proposed 2018 Schedule:
  • September 11th, 2018 (today)
  • December 4th, 2018
  • March 5th, 2019
  • June 4th, 2019