Commission Mandatory Hearing SHINE Construction Permit Application - - PowerPoint PPT Presentation

commission mandatory hearing shine construction permit
SMART_READER_LITE
LIVE PREVIEW

Commission Mandatory Hearing SHINE Construction Permit Application - - PowerPoint PPT Presentation

Exhibit SHN-028 Commission Mandatory Hearing SHINE Construction Permit Application S f Safety Panel 2 P l 2 Accident Analysis December 15, 2015 , Accident Initiating Events and Scenarios Bases for identification of accidents:


slide-1
SLIDE 1

Exhibit SHN-028

Commission Mandatory Hearing SHINE Construction Permit Application S f P l 2 Safety – Panel 2 Accident Analysis December 15, 2015 ,

slide-2
SLIDE 2

Accident Initiating Events and Scenarios

  • Bases for identification of accidents:
  • Hazard and Operability Study (HAZOPS)
  • Preliminary Hazard Analysis (PHA)
  • List of events from NUREG-1537 and the Interim Staff Guidance (ISG)

List of events from NUREG 1537 and the Interim Staff Guidance (ISG) augmenting NUREG-1537

  • Experience of the hazards analysis team
  • Current preliminary design information

Current preliminary design information

  • Qualitative evaluations within categories
  • Quantitative evaluations to determine consequences

P t l t d i di ti f ilit (IF) d di i t d ti

  • Postulated an irradiation facility (IF) and radioisotope production

facility (RPF) Maximum Hypothetical Accident (MHA)

  • Establishes an outer limit consequence, bounds other accidents
  • Most limiting MHA was in the RPF (“Facility MHA”)

2

slide-3
SLIDE 3

IF Postulated Maximum Hypothetical Accident

  • Target solution vessel (TSV) and

b iti l bl t subcritical assembly support structure (SASS) integrity lost, target solution spills into irradiation unit (IU) cell

Subcritical Assembly Support Structure (SASS)

  • Maximum inventories assumed

in TSV

  • Pool presence ignored
  • High radiation detected initiates

TSV (Internal to SASS)

High radiation detected, initiates alarms and confinement

  • High efficiency particulate

air (HEPA) filters and charcoal d b dit d adsorbers credited

  • Dose consequences
  • Worker TEDE: 3.1 rem
  • Public (site boundary) TEDE:

TSV Dump Tank

3

Public (site boundary) TEDE: 0.017 rem

slide-4
SLIDE 4

RPF Maximum Hypothetical Accident (Facility MHA) (Facility MHA)

  • The five noble gas

TSV Off Gas

g storage tanks rupture simultaneously

  • With the maximum inventory

NGRS Compressors Purge

y

  • Contents are instantly

released

  • High radiation levels initiate

Al

RAD

Al

RAD

Al

RAD

Al

RAD

Al

RAD

Noble Gas Storage Tanks

g alarm and cell isolation

  • Redundant isolation

dampers close

Al

RAD

dampers close

  • 10% of the activity bypasses

the isolation dampers

  • 10% of the activity leaks

Condensate Knock Out Tank Radioactive Process Vessel Vent System

10% of the activity leaks through penetrations

4

Radioactive Liquid Waste

slide-5
SLIDE 5

RPF Maximum Hypothetical Accident (Facility MHA)

  • Dose consequences

(Facility MHA)

  • Worker TEDE: 3.6 rem
  • Public (site boundary) TEDE: 0.082 rem
  • The MHA consequences are conservative
  • Simultaneous, instantaneous rupture
  • Entirety of noble gas is transferred and released
  • The five tanks are filled to capacity
  • Additional ventilation isolation dampers would

close, but are not credited

  • Actual doses would be lower
  • Radiological consequences to

workers and the public are within the limits of 10 CFR 20.1101, 20.1201, and 20.1301 ,

5