Colintraive and Rhubodach Slipways Reconstruction The Project We - - PowerPoint PPT Presentation

colintraive and rhubodach slipways reconstruction the
SMART_READER_LITE
LIVE PREVIEW

Colintraive and Rhubodach Slipways Reconstruction The Project We - - PowerPoint PPT Presentation

Caledonian Maritime Assets Limited Colintraive and Rhubodach Slipways Reconstruction The Project We are replacing the slipway s at Colintraive and Rhubodach The project will deliver new double width and longer slipway s


slide-1
SLIDE 1

Caledonian Maritime Assets Limited

Colintraive and Rhubodach Slipways Reconstruction

slide-2
SLIDE 2

Colintraive and Rhubodach Slipway Rebuild 2

The Project

  • We are replacing the slipway’s at Colintraive and Rhubodach
  • The project will deliver new double width and longer slipway’s

– Access at all states of tide – Future maintenance will be carried out during the day

  • The project will also provide a new vehicle queuing area

– Capacity provided for 2 boat loads of cars and HGV’s

  • The ferry service will continue to operate throughout this project
slide-3
SLIDE 3

Colintraive and Rhubodach Slipway Rebuild 3

Colintraive and Rhubodach Slipways Reconstruction

  • Slipways at end of Serviceable Life:
  • Settled significantly
  • Surfacing is continually breaking up
  • Reconstruct slipways to safeguard ferry

service

  • A number of restrictions will be placed on

the contractor including:

  • Construction sequence
  • Working hours
  • Traffic management
slide-4
SLIDE 4

Colintraive and Rhubodach Slipway Rebuild 4

New Slipway – Phase 2 New Slipway – Phase 3

Rhubodach Slipway

Existing Slipway Contractor’s Compound New Infill / Paved Areas Excavation Separation Structure – Phase 1

slide-5
SLIDE 5

Colintraive and Rhubodach Slipway Rebuild 5

Colintraive – Slipway Area

Excavation New Infill Area / Wall Removed New Slipway – Phase 2 New Slipway – Phase 3 Existing Slipway Site Traffic Entrance (Lane 3) Clear space (Old lanes 1 and 2) Cathodic Protection System to Steel Piles Separation Structure – Phase 1 Contractor’s Compound

slide-6
SLIDE 6

Colintraive and Rhubodach Slipway Rebuild 6

Colintraive Ferry Traffic Queuing

slide-7
SLIDE 7

Colintraive and Rhubodach Slipway Rebuild 7

Colintraive – Previous design Marshalling Area

Existing Access Track and Storage Area (Contractor’s Working Area) CalMac Parking Area CalMac Storage Area General Parking Area Car Marshalling Lane 2 Car Marshalling Lane 1 HGV / Bus Marshalling Area Access Ramp to Shore

slide-8
SLIDE 8

Colintraive and Rhubodach Slipway Rebuild 8

Colintraive – New design Marshalling Area

CalMac Parking Area CalMac Storage Area General Parking Area Car Marshalling Lane 2 Car Marshalling Lane 1 HGV / Bus Marshalling Area Access Ramp to Shore

slide-9
SLIDE 9

Colintraive and Rhubodach Slipway Rebuild 9

Community Amenity

General Parking and access ramp to foreshore provided by CMAL as part

  • f this project

Pontoon design and specification provided by

  • CMAL. Col/Glen Trust will

now apply for construction funding

slide-10
SLIDE 10

Colintraive and Rhubodach Slipway Rebuild 10

Programme

On-hold awaiting funding from Transport Scotland

slide-11
SLIDE 11

Colintraive and Rhubodach Slipway Rebuild 11

Questions?