Coastal Resiliency Along Neshaminy Creek for Creating, Enhancing - - PowerPoint PPT Presentation

coastal resiliency along neshaminy creek for creating
SMART_READER_LITE
LIVE PREVIEW

Coastal Resiliency Along Neshaminy Creek for Creating, Enhancing - - PowerPoint PPT Presentation

Coastal Resiliency Along Neshaminy Creek for Creating, Enhancing and Preserving Former Wetlands at Abandoned and Degraded Jacks Marina Presented by: Sachin Apte, P.E. Louis Berger Co-Authors: Peg McBrien, P.E. Louis Berger Lisa


slide-1
SLIDE 1

Coastal Resiliency Along Neshaminy Creek for Creating, Enhancing and Preserving Former Wetlands at Abandoned and Degraded Jack’s Marina

Presented by: Sachin Apte, P.E. Louis Berger Co-Authors: Peg McBrien, P.E. Louis Berger Lisa Magee, PRPA

slide-2
SLIDE 2

2

Jack’s Marina Compensatory Wetland Mitigation

Aerial View of Site

  • Wetland, Open Water and Sensitive

Species Mitigation for Southport Marine Terminal Project

  • Philadelphia Regional Port Authority

is primary client

  • Protection and enhancement of

Pennsylvania’s coastal resources and fostering sustainable development

  • Louis Berger and AP Construction

Design-Build Team

  • Permits from US Army Corps of

Engineers, PADEP, PADCNR, Bucks County Cons. District and PA Fish & Boat Commission

slide-3
SLIDE 3

3

Abandoned and Degraded Jack’s Marina Site

  • 35 acre site purchased by

PRPA for compensatory wetland mitigation

  • Much of site formerly

dredged/filled for recreational marina

  • Existing freshwater tidal

wetlands contain invasive species

  • Shoreline stabilization

required for coastal resiliency

  • Unsafe public access
slide-4
SLIDE 4

4

Louis Berger Preliminary Field Investigations

Prior to actual construction

  • Baseline design studies

for habitat restoration

  • Detailed soil analyses for

material disposal offsite

  • Plant and wildlife surveys
  • Wetland delineation and

bio-benchmark survey

  • Topographic, bathymetric

surveys verification

  • Permitting requirements

for state, federal and local agencies for compliance

  • Construction plan sets
slide-5
SLIDE 5

5

Design/Build Team- Task Force

  • ut to work

Initial Clearing of Site

  • Re-establishment of 11.52

acres of tidal freshwater wetland and mudflat

  • Enhancement of 13.65

acres of tidal wetland by removal of invasive species and debris

  • Establishment of 3.29

acres of SAV within former boat basins

  • Creation of 0.45 acres of

red belly turtle nesting habitat (PA threatened species)

  • Creation of 4.26 acres of

upland buffer.

slide-6
SLIDE 6

6

Soil Erosion & Sediment Control Measures

Bucks County E&S Permit

  • Isolate and protect

existing wetlands with super silt fence

  • Stabilized construction

entrance for material disposal traffic at site

  • Silt fence around

perimeter of site boundary

  • Installation of

temporary sheet pile and turbidity barriers for water control during dredging

slide-7
SLIDE 7

7

Rescuing Fish & Red Belly Turtles from Basins

PAFBC Permit Compliance

  • Threatened Species -

Red Belly Turtles

  • Fish relocated from the

work area during dewatering

  • Extra care taken for

native bird species relocation during construction

  • Other wildlife carefully

kept away from entering construction site.

slide-8
SLIDE 8

LOCATION: CLIENT: 8

  • Excavation and grading of

the south basin.

  • PADEP site visit to
  • versee construction

progress at project site

  • Surveyor for collecting as-

built grades information

South Basin Construction

slide-9
SLIDE 9

9

Refurbished public access trail

Reintroduction of public access

  • Former trail to fishing

pier refurbished

  • Fishing pier completely

reconstructed

  • Ease of access for

nearby residents and fishing enthusiasts

  • Walkway provides

access for emergency vehicles with turnaround area

  • Walkway provides

expansive views of restored & enhanced wetlands

slide-10
SLIDE 10

10

Rebuilt fishing pier platform

Enhancing the waterfront

  • Existing fishing pier

structure rebuilt

  • Structural analysis

performed to develop cost effective pier design

  • ADA compliant path

and pier access

  • Low maintenance

metal fence provided around fishing pier

  • Provides views of

south basin, turtle nesting habitat and wetland

slide-11
SLIDE 11

LOCATION: CLIENT: 11

  • Excavation and Grading
  • f the upland slope.
  • North basin grading to

create more open water

  • Minimal dewatering for

north basin to excavate perimeter grades

Upland Slope Construction

slide-12
SLIDE 12

12

Installation of E&S measures & turtle basking structures

Taking care of wildlife

  • Enhancing turtle

habitat in deepened and widened south basin

  • Excavation around

south basin slope tor reconnecting restored and existing wetlands

  • Wildlife returning to

project site during construction

  • Upland slope erosion

control matting and seeding operation

slide-13
SLIDE 13

13

Planting Intertidal wetland & scrub shrub vegetation

Creation of new wetlands

  • Spatterdock planted

from elevation 0 to 2

  • Pickerelweed,

Sweetflag, Taperleaf water horehound and duck potato from elevation 2.0 to 3.5

  • Black willow, smooth

alder and buttonbush from elevation 3.5 to 4.0

slide-14
SLIDE 14

14

Excavation of waste/disposal

Piece of history uncovered

  • Newspapers dating as

back to 1947

  • Debris varying from

railroad ties, tires, trash, mattresses, old concrete pipes etc.

  • Depth and volume of

excavated material required mechanical

  • nsite separation
  • Special screening

equipment bought

  • nsite to separate

material for proper

  • ffsite .
slide-15
SLIDE 15

15

Permitting Agencies site visit to monitor compliance

Project found to be compliant

  • USACOE, PADEP And

PRPA site visits to monitor progress

  • Recommendations were

kindly provided by the permitting agencies to stay within permit compliance

  • Agency representatives

walked entire site within keen interest in latest updates to schedules

  • Coordination meetings to

tackle key issues during construction progress

slide-16
SLIDE 16

16

State Endangered Species special attention

Specially design habitats

  • Sand brought in for red

belly turtle nesting habitat

  • Special attention given

for in-water zones for endangered species

  • Rip-rap stone protection

for nesting mounds

  • Osprey nest platform

installation

  • Submerged aquatic

vegetation transplanted from Southport impact site to Jack’s Marina mitigation site

slide-17
SLIDE 17

LOCATION: CLIENT: 17

  • Interpretive signage

designed by sub consultant to be installed this spring on fishing pier

  • Warning sign of shallow
  • bstructions at south basin

for boaters

Interpretive & Warning Signs

slide-18
SLIDE 18

18

Site status before winter 2014

Site construction complete

  • All excavation/disposal

and slope stabilization complete

  • Erosion control

measures in place before winter season

  • Keeping fingers

crossed for site to withstand harsh winter season

  • Remaining planting

and slope stabilization to be completed in spring 2015

slide-19
SLIDE 19

19

Spring 2015 site visit-Monitoring

Site restoration complete

  • 3 to 5 years of

performance monitoring as per permit compliance requirements

  • Adaptive management

goals to be met

  • Achieve waterfront

development goals

  • Site will be transferred to

Neshaminy Creek State park system

slide-20
SLIDE 20

Questions?