Climate change, demand, and winds part of the story
Andrew Renton Senior Principal Engineer, WEANZ AGM Wellington October 2019
1
Climate change, demand, and winds part of the story Andrew Renton - - PowerPoint PPT Presentation
Climate change, demand, and winds part of the story Andrew Renton Senior Principal Engineer, WEANZ AGM Wellington October 2019 1 What this paper Is and Isnt Isnt Is The ultimate answer The issue and system we have The only
Andrew Renton Senior Principal Engineer, WEANZ AGM Wellington October 2019
1
2
3
4
5
6
7
8
9
10
Auckland 544 150 77
GenA Peak GenM
64
Peak 71 GenA GenM 170
Northland 96 60 55
Peak GenM GenA
Bay of Plenty 39 120 50
GenA Peak GenM
Hawkes Bay 78
550 231 GenM Peak GenA
Central Districts 194
885 1,724 Peak GenM GenA
Waikato 53
Peak GenM 148 GenA 330
Taranaki 104 90 38
GenM Peak GenA
Wellington 41 150 63
Peak GenM GenA
Nelson- Marlborough 138
GenA Peak GenM 224 92
Canterbury 82
GenM Peak GenA
South Canterbury 82
GenA GenM Peak 233 554
Otago-Southland 28
GenA Peak GenM
West Coast New Zealand total growth (MW, 2020-2035) 1,580
4,122 Peak Generation max. 1,944 Generation avg.
Wind Gas Geothermal Solar Hydro Different shades of same colour represent different generation assets within the same class
2/3rds new gen expected middle/lower North Island
11
Wairakei Ring upgrade Estimated timing: 2025-2030 Investment driver: Supply Indicative investment: $210m Existing n-1 capacity: 655 MW Upgraded n-1 capacity: 1500 MW CNI upgrade Estimated timing: 2030-2035 Investment driver: Supply Indicative investment: $240m Existing n-1 capacity: 590 MW Upgraded n-1 capacity: 1130 MW OTA-WKM upgrade Estimated timing: beyond 2035 Investment driver: Demand Indicative investment: $190m CUWLP Estimated timing: 2030-2035 (TWI smelter assumed to remain) Investment driver: Supply Indicative investment: $105m Existing n-1 capacity: 660 MW Upgraded n-1 capacity: 950 MW USI upgrade Estimated timing: Beyond 2035 Investment driver: Demand Indicative investment: $900m
Enabling investments required for ENC medium demand scenario
12
13
14
15
16
17
18
19
20
54,824hec, NZ$7.9B, 1013 Turbines
21
54,824hec, NZ$7.9B, 1013 Turbines
22
54,824hec, NZ$7.9B, 1013 Turbines 12,000hec, NZ$3.5B, 1 Lake
23
54,824hec, NZ$7.9B, 1013 Turbines 12,000hec, NZ$3.5B, 1 Lake
24
54,824hec, NZ$7.9B, 1013 Turbines 12,000hec, NZ$3.5B, 1 Lake 16,842hec, NZ$5.8T, 4.2M/2MW Packs
54,824hec, NZ$7.9B, 1013 Turbines 12,000hec, NZ$3.5B, 1 Lake 16,842hec, NZ$5.8T, 4.2M/2MW Packs
25
26
54,824hec, NZ$7.9B, 1013 Turbines 12,000hec, NZ$3.5B, 1 Lake 16,842hec, NZ$5.8T, 4.2M/2MW Packs 2,399hec, NZ$118B, 2,399/35k T tanks
27
54,824hec, NZ$7.9B, 1013 Turbines 12,000hec, NZ$3.5B, 1 Lake 16,842hec, NZ$5.8T, 4.2M/2MW Packs 2,399hec, NZ$118B, 2,399/35k T tanks 0hec, NZ$1.8B, 6 injection facilities
28
54,824hec, NZ$7.9B, 1013 Turbines 12,000hec, NZ$3.5B, 1 Lake 16,842hec, NZ$5.8T, 4.2M/2MW Packs 2,399hec, NZ$118B, 2,399/35k T tanks 0hec, NZ$1.8B, 2.5 injection facilities
54,824hec, NZ$7.9B, 1013 Turbines 12,000hec, NZ$3.5B, 1 Lake 16,842hec, NZ$5.8T, 4.2M/2MW Packs 2,399hec, NZ$118B, 2,399/35k T tanks 0hec, NZ$1.8B, 6 injection facilities
29
30
54,824hec, NZ$7.9B, 1013 Turbines 12,000hec, NZ$3.5B, 1 Lake 16,842hec, NZ$5.8T, 4.2M/2MW Packs 2,399hec, NZ$118B, 2,399/35k T tanks 0hec, NZ$1.8B, 6 injection facilities 190hec, NZ$7.3B, 190/35kT NH3 tanks
54,824hec, NZ$7.9B, 1013 Turbines 12,000hec, NZ$3.5B, 1 Lake 16,842hec, NZ$5.8T, 4.2M/2MW Packs 2,399hec, NZ$118B, 2,399/35k T tanks 0hec, NZ$1.8B, 6 injection facilities 190hec, NZ$7.3B, 190/35kT NH3 tanks
31
32
54,824hec, NZ$7.9B, 1013 Turbines 12,000hec, NZ$3.5B, 1 Lake 16,842hec, NZ$5.8T, 4.2M/2MW Packs 2,399hec, NZ$118B, 2,399/35k T tanks 0hec, NZ$1.8B, 6 injection facilities 190hec, NZ$7.3B, 190/35kT NH3 tanks Nett 239hec, NZ$3.1B, 239/35k LOHC tanks
33
Option NH3 CH4 LOHC Pumped Hydro Overbuild Option NH3 CH4 LOHC Pumped Hydro Overbuild Storage NZ$7.3B NZ$1.8B NZ$3.1B NZ$3.5B
NH3 CH4 LOHC Pumped Hydro Overbuild Storage NZ$7.3B NZ$1.8B NZ$3.1B NZ$3.5B
NZ$1.3B NZ$1.5B NZ$0.8B
NH3 CH4 LOHC Pumped Hydro Overbuild Storage NZ$7.3B NZ$1.8B NZ$3.1B NZ$3.5B
NZ$1.3B NZ$1.5B NZ$0.8B
NZ$3.8B NZ$3.3B NZ$3.8B NZ$1.5B NZ$8B Option NH3 CH4 LOHC Pumped Hydro Overbuild Storage NZ$7.3B NZ$1.8B NZ$3.1B NZ$3.5B
NZ$1.3B NZ$1.5B NZ$0.8B
NZ$3.8B NZ$3.3B NZ$3.8B NZ$1.5B NZ$8B TOTAL NZ$12.B NZ$6.7B NZ$7.8B NZ$5B NZ$8B Option (NPV) NH3 CH4 LOHC Pumped Hydro Overbuild Storage NZ$2.3B NZ$0.18B NZ$1.5B NZ$2.2B
NZ$0.07B NZ$0.08B NZ$0.04B
NZ$0.35B NZ$0.31B NZ$0.36B NZ$0.14B NZ$0.75B TOTAL NZ$2.72B NZ$0.57B NZ$1.9B NZ$2.3B NZ$0.75B
34
Option (NPV) NH3 CH4 LOHC Pumped Hydro Overbuild Storage NZ$2.3B NZ$0.18B NZ$1.5B NZ$2.2B
NZ$0.07B NZ$0.08B NZ$0.04B
NZ$0.35B NZ$0.31B NZ$0.36B NZ$0.14B NZ$0.75B TOTAL NZ$2.72B NZ$0.57B NZ$1.9B NZ$2.3B NZ$0.75B
35
36
NH3 CH4 LOHC Pumped Hydro Overbuild Positive Moderate Known Tech Modular/Scalable Minimal Known Tech Utilises Existing Modular/Scalable Repurposes existing assets Moderate Std Petro chem Modular/Scalable Enables innovative finance and energy for export Repurposes existing assets Large Scale Established Tech Large Scale Business as Usual Can make sustainable pipeline
Modular/Scalable Negative Known but not at this sclae New Tech Consents Environmental Implications 40m
Single large scale Large
37
38