S. LAKESHORE DRIVE / SUMMIT RIDGE DRIVE RECONSTRUCTION PROJECT CITY COUNCIL MEETING City of Rockwall, Texas May 7, 2018 CIP No.: CIP 2015-006 Engineering Schematic Design & October 2015 Development: October 2017 Limits (From): SH


  1. S. LAKESHORE DRIVE / SUMMIT RIDGE DRIVE RECONSTRUCTION PROJECT CITY COUNCIL MEETING City of Rockwall, Texas May 7, 2018

  2. CIP No.: CIP 2015-006 Engineering Schematic Design & October 2015 – Development: October 2017 Limits (From): SH 66 (W Rusk St) Public Meetings (3): December 2015- December 2017 (To): FM 740 (Ridge Rd) Schematic Approval: October 2017 Engr. Design Firm: Kimley-Horn & 100% Construction Plans: June 2018 * Associates, Inc. Franchise Utility Relocation Begin: Summer 2018 * Funding: 2012 Road Bonds & Franchise Utility Relocation End: Fall 2018 * Water/Sewer Bonds Bid Date: Summer 2018 * Construction Start: Fall/Winter 2018 * Construction Complete: Summer 2020 * Project Description: Existing: - Lakeshore: 36’ wide concrete roadway with no sidewalks - Summit Ridge: 26’ wide concrete roadway with no sidewalks Proposed: - 2-11 foot lanes - Staggered parallel parking stalls on S. Lakeshore Dr. - Small traffic circles at cross-streets. - 5’ concrete sidewalks (both) - Water line & wastewater line replacements (both) - Storm sewer improvements (both) - Alley reconstruction (select areas) * Anticipated Dates

  3. Project Timeline • October 2015 • Public Input Surveys (Adjacent Property Owners) • 93 surveys sent – to adjacent property owners • 34 responses to survey (36.5%) • 64.7% of respondents were in favor of implementing sidewalks • 79.4% of respondents in favor of traffic calming to slow or discourage cut through traffic • December 12, 2015 • Public Input Meeting (Adjacent Property Owners) • Discuss Survey Results, Traffic Calming Measures, and Traffic Study • Gathered additional input from comment cards: No Significant Change in Sidewalk Favor • July 20, 2016 • Public Meeting (Entire Neighborhood) • Present Preliminary Design Schematic based on survey results and public meeting • Comment Cards: • Adjacent Residents – No Significant Change in Sidewalk Favor • Non-Adjacent Residents (Out of 16 received: 9 – In Favor of sidewalks, 4 – Not in Favor of sidewalks) • October 2017 • City Council Presentation • Typical Section and Schematic approved by City Council • December 1, 2017 • Public Meeting (Entire Neighborhood) – Hosted by Councilman Mike Townsend • Present Final Design Schematic based on survey results and public meeting

  4. @

  5. Existing 2-11 ft lanes (E. Kaufman St.)

  6. Project Information • On-street parallel parking (6 Locations) • Existing driveway and leadwalks will match existing finish type (Concrete, Exposed Aggregate, Pavers, Stamped/Stained Concrete, etc.)

  7. Project Information • Existing irrigation systems to be relocated out of the way of proposed improvements. Any damage irrigation systems will be repaired to same or better condition. • Mailboxes will be salvaged where possible and relocated to new location, if damaged, mailboxes will be reconstructed to match existing to type, material (to extent possible) and style. • Right of Entries will be acquired to reconstruct driveways and leadwalks (58 properties)

  8. Tree Removal (10 Total – 8 crape Myrtles, 1 Magnolia, & 1 ornamental shrub)

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.