Facility Needs Update
CITY COUNCIL MAY 20, 2019
Facility Needs Update CITY COUNCIL MAY 20, 2019 Overview At the - - PowerPoint PPT Presentation
Facility Needs Update CITY COUNCIL MAY 20, 2019 Overview At the April 1 City Council Workshop, staff presented information on the existing Public Works, Parks Maintenance, and Animal Control Facilities. The City Council asked staff to
CITY COUNCIL MAY 20, 2019
existing Public Works, Parks Maintenance, and Animal Control Facilities.
would look like in size/scope/cost. Staff has prepared a preliminary scope and cost estimate for discussion.
at Fire Station #2 which are in need of addressing.
equipment
$3,000,000.00
$300,000.00
$300,000.00
$300,000.00
$4,100,000.00
$2,000,000.00
$300,000.00
$200,000.00
$200,000.00
$2,800,000.00
Available Land Available Land
functions as a project manager of both the designer and the contractor. The owner often mediates between the two teams, and routes information between the two teams. Costs can be difficult to control as differences between the two team’s recommendations may result in lost time and less efficient solutions.
combined design/construction team.
single point of responsibility. The designer and contractor work together from the beginning as a team, providing unified project recommendations to fit the Owner's schedule and budget. Project changes are more efficient, and response times are faster. In addition, cost is easier to control.
constructed in 2004.
through walls, particularly along the north and east sides of the building.
hallways, kitchen, bedroom, workout room, and the lounge.
slope away from the building, in addition to doorways and building floor being at the same elevation as the ground outside.
detailed cost estimates and funding options for the City Council to utilize in exploring this further.
will be used by the Engineering Department to develop a project scope and cost estimate.
consideration.