Chapter 4: Culvert Hydraulics Jam Aleem Nawaz Amanda Yancoskie - - PowerPoint PPT Presentation

chapter 4 culvert hydraulics
SMART_READER_LITE
LIVE PREVIEW

Chapter 4: Culvert Hydraulics Jam Aleem Nawaz Amanda Yancoskie - - PowerPoint PPT Presentation

Chapter 4: Culvert Hydraulics Jam Aleem Nawaz Amanda Yancoskie Table of Contents Introduction Types Inlet Control Outlet Control Tutorial Example Problem Statement Questions 4.5 Tutorial Example Problem Statement


slide-1
SLIDE 1

Chapter 4: Culvert Hydraulics

Jam Aleem Nawaz Amanda Yancoskie

slide-2
SLIDE 2
  • Introduction
  • Types
  • Inlet Control
  • Outlet Control
  • Tutorial Example
  • Problem Statement
  • Questions

Table of Contents

slide-3
SLIDE 3

4.5 Tutorial Example

slide-4
SLIDE 4

Problem Statement

Several circular, concrete culverts that have square-edged entrances with headwalls (n=0.013, ke=0.5) must be used to carry 54 m3/s. The culverts are 20 meters long, on a 5.5 percent slope with and upstream and downstream invert elevations of 261.0 meters and 259.9 meters, respectively. The maximum allowable headwater elevation is 268 meters, and the elevation of the tailwater is 257.4 meters. a) How many culverts should be used if the diameter of the culverts is 1950mm? b) What is the headwater depth? c) Is the system flowing under inlet or outlet control? d) What is the velocity at the culvert exit? e) Construct a performance curve showing the headwater elevation as a function of discharge. Consider both inlet and outlet control.

slide-5
SLIDE 5

When you start CulvertMaster, you should be prompted with the Welcome to Bentley CulvertMaster dialog. Select Create New Project.

slide-6
SLIDE 6

Navigate to the folder where you want to save your project, enter a filename, and click Save.

slide-7
SLIDE 7

The Project Setup wizard will

  • appear. Add a project title,

project engineer, and appropriate comments, and click Next.

slide-8
SLIDE 8

In this example we will not be defining a rainfall table or a rainfall equation, so select Next.

slide-9
SLIDE 9

We need to check the unit system before creating an element , so select the None radio button and Finished to exit.

slide-10
SLIDE 10

Select Options from the Tools pulldown menu.

slide-11
SLIDE 11

Change the unit system to System International. Click OK to exit the dialog.

slide-12
SLIDE 12

Click the Quick Culvert Calculator button on the left hand side

  • f the window.
slide-13
SLIDE 13

Provide a title for the worksheet and click OK.

slide-14
SLIDE 14

Click the drop-down arrow next to the Solve For: data entry field and Select Discharge from the list.

slide-15
SLIDE 15

Enter: Maximum Allowable HW: 268 m Tailwater Elevation: 257.4 m Invert Upstream: 261 m Invert Downstream: 259.9 m Length: 20 m Shape: Circular Material: Concrete Size: 1950 mm Mannings: 0.013 Note: You can change the units by double-clicking the units label next to the variable. Entrance: square edge w/headwall Ke: 0.5

slide-16
SLIDE 16

The default value for the number of culvert barrels is 1. Run the model using one culvert barrel by clicking the Solve button.

slide-17
SLIDE 17

The Discharge value that is calculated is displayed in the Exit Results part of the worksheet. Run the model several times, increasing the number of culvert barrels until the calculated discharge is ≥ 54 m3/s.

slide-18
SLIDE 18

a) How many culverts should be used if the diameter of the culverts is 1950 mm? Answer: 3 culverts with 1950 mm diameter will carry 61 m3/s

slide-19
SLIDE 19

b) What is the head water depth? Answer: The headwater depth is equal to the difference between the Computed Headwater and the Inverted Upstream: 268.0 m - 261.0 m = 7.0 m

slide-20
SLIDE 20

c) Is the system flowing under inlet or outlet control? Answer: The system is flowing under inlet control, because the inlet control elevation is greater then the outlet control. Inlet: 268.00 m > Outlet: 266.34 m

slide-21
SLIDE 21

d) What is the velocity at the culvert exit? Answer: 8.19 m/s.

slide-22
SLIDE 22

e) Construct a performance curve showing the headwater elevation as a function of

  • discharge. Consider both inlet

and outlet control. Click the Output button.

slide-23
SLIDE 23

Select the Plot Curves button.

slide-24
SLIDE 24

Under the Compute heading, select Inlet Control HW

  • Elev. (m) and Outlet Control
  • Elev. (m).

Click the drop-down arrow next to Vary: and select Discharge (m3/s). Set the graph scale to, Minium: 0.0 m3/s Maximum: 100 m3/s Increment: 20 m3/s Click the Refresh button.

slide-25
SLIDE 25

The graph shows the performance curve for the three-barrel culvert set.

slide-26
SLIDE 26

Any Questions?